QUESTIONS-RESPONSES_15APR15.doc

DOC document 24 KB Posted

Attached to
REPAIR STREETS & PARKING LOTS Federal contract opportunity
Solicitation number
FA6633-15-B0004
Issued by
Department of the Air Force Reserve Command

About this file

Questions Govt. Responses 15Apr15

View the file

Other files for this federal contract opportunity

Other files attached to REPAIR STREETS & PARKING LOTS, newest first.
File Type Posted
SV_Attendance_Roster_4-8-1.pdf PDF
Revised_Drawing_Sheet_03_-_08Apr15.pdf PDF
FA6633-15-B0004 _IFB.doc DOC document
Drawings.pdf PDF
Financial_Responsibility_Sheet.doc DOC document
Technical_Specifications.pdf PDF
Wage_Determination_MN130.doc DOC document
SF_24_Bid_Bond_Form.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION #FA6633-15-B0004

REPAIR ROADS & PARKING LOTS

QUESTIONS / GOVT. RESPONSES #001

15 APRIL 2015

1. Can the dirt that gets dug up for the two parking lots be left somewhere outside or will it have to be hauled off the site?

GOVT. RESPONSE: THE CONTRACTOR SHALL REMOVE ALL EXCESS DIRT FROM THE SITE AND DISPOSED OF OFF BASE.

1. Can the existing 6" asphalt be reclaimed or does it have to be torn up?

GOVT. RESPONSE: THE CONTRACTOR SHALL REMOVE ALL EXISTING ASPHALT AND NOT RECLAIM

IT FOR THIS PROJECT. PAST CONTRACTORS HAVE REMOVED THE EXISTING ASPHALT BY SEVERAL METHODS AS DESCRIBED IN THE FOLLOWING:

(1) "BREAKING IT UP" WITH AN EXCAVATOR, LOADING THE "ASPHALT CHUNKS" INTO TRUCKS AND HAULING IT AWAY

(2) "PULVERIZING" THE MATERIAL FIRST, LOADING THE "PULVERIZED MATERIAL" INTO TRUCKS AND HAULING IT AWAY