AF Form 3052 Construction Cost Estimate
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFI_Responses_Radon_Mitigation.doc | DOC document | |
| EVKP_154383_Radon_Solicitation_Amendment.pdf | ||
| As-Built_Drawings_Radon_Mitigation.pdf | ||
| FA5270-15-T-0054_Radon_Mitigation.pdf | ||
| SOW-Radon_Mitigation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OMB No. 0704-0193
CONSTRUCTION COST ESTIMATE BREAKDOWN (CONTRACTOR) Expires 31 October 1989
CONTRACTOR ADDRESS
CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE Install Radon Mitigation, NON-GOH (32UN)
PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION
EVKP 15-4383 Various MFH, Okinawa, Japan
MATERIAL COST LABOR COSTS
UNIT OTHER
LINE ITEM OF QUANTITY MANHOURS AVERAGE DIRECT LINE
NO. MEASURE UNIT TOTAL MANDAYS RATE TOTAL COSTS TOTAL
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
SUMMARY
I 1-Story
II 2-Story
III Tower
IV Remove and Dispose Existing Mitigation System
Total Direct Cost
Design %
Sub-Total
Overhead %
Sub-Total
Profit %
Total Project Cost
@$1.00= 103.9439¥ -$
CONSTRUCTION COST ESTIMATE BREAKDOWN (CONTRACTOR) Expires 31 October 1989
CONTRACTOR ADDRESS
CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE Install Radon Mitigation, NON-GOH (32UN)
PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION
EVKP 15-4383 Various MFH, Okinawa, Japan
MATERIAL COST LABOR COSTS
UNIT OTHER
LINE ITEM OF QUANTITY MANHOURS AVERAGE DIRECT LINE
NO. MEASURE UNIT TOTAL MANDAYS RATE TOTAL COSTS TOTAL
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
AF FORM 3052, JAN 88 PREVIOUS EDITION IS OBSOLETE. FOR OFFICIAL USE ONLY
I Type : 1-Story (Each Unit)
1 Excavation, Remove and dispose M³
2 Aggregate/Concrete M³
3 4" PVC Vent from Suction Pit M
4 Exhaust Fan with Cover include Electrical Work SET
5 Asbestos/ LBP sampling and testing LOT
6 Misc. Materials and Labor (Sodding, Repair Existing Tile, etc.,) LS
Total Direct Cost
AF FORM 3052, JAN 88 PREVIOUS EDITION IS OBSOLETE. FOR OFFICIAL USE ONLY
CONSTRUCTION COST ESTIMATE BREAKDOWN (CONTRACTOR) Expires 31 October 1989
CONTRACTOR ADDRESS
CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE Install Radon Mitigation, NON-GOH (32UN)
PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION
EVKP 15-4383 Various MFH, Okinawa, Japan
MATERIAL COST LABOR COSTS
UNIT OTHER
LINE ITEM OF QUANTITY MANHOURS AVERAGE DIRECT LINE
NO. MEASURE UNIT TOTAL MANDAYS RATE TOTAL COSTS TOTAL
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
II Type : 2-Story (Each Unit)
1 Excavation, Remove and dispose M³
2 Aggregate/Concrete M³
3 4" PVC Vent from Suction Pit M
4 Exhaust Fan with Cover include Electrical Work SET
5 Asbestos/ LBP sampling and testing LOT
6 Misc. Materials and Labor (Sodding, Repair Existing Tile, etc.,) LS
Total Direct Cost
AF FORM 3052, JAN 88 PREVIOUS EDITION IS OBSOLETE. FOR OFFICIAL USE ONLY