AF_Form_3052_Blank.pdf

PDF 13 KB Posted

Attached to
Install Radon Mitigation Non GOH (32 Units) Federal contract opportunity
Solicitation number
FA5270-15-T-0054
Issued by
Department of the Air Force Pacific Air Forces

About this file

AF Form 3052 Construction Cost Estimate

View the file

Other files for this federal contract opportunity

Other files attached to Install Radon Mitigation Non GOH (32 Units), newest first.
File Type Posted
RFI_Responses_Radon_Mitigation.doc DOC document
EVKP_154383_Radon_Solicitation_Amendment.pdf PDF
As-Built_Drawings_Radon_Mitigation.pdf PDF
FA5270-15-T-0054_Radon_Mitigation.pdf PDF
SOW-Radon_Mitigation.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OMB No. 0704-0193

CONSTRUCTION COST ESTIMATE BREAKDOWN (CONTRACTOR) Expires 31 October 1989

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE Install Radon Mitigation, NON-GOH (32UN)

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

EVKP 15-4383 Various MFH, Okinawa, Japan

MATERIAL COST LABOR COSTS

UNIT OTHER

LINE ITEM OF QUANTITY MANHOURS AVERAGE DIRECT LINE

NO. MEASURE UNIT TOTAL MANDAYS RATE TOTAL COSTS TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

SUMMARY

I 1-Story

II 2-Story

III Tower

IV Remove and Dispose Existing Mitigation System

Total Direct Cost

Design %

Sub-Total

Overhead %

Sub-Total

Profit %

Total Project Cost

@$1.00= 103.9439¥ -$

CONSTRUCTION COST ESTIMATE BREAKDOWN (CONTRACTOR) Expires 31 October 1989

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE Install Radon Mitigation, NON-GOH (32UN)

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

EVKP 15-4383 Various MFH, Okinawa, Japan

MATERIAL COST LABOR COSTS

UNIT OTHER

LINE ITEM OF QUANTITY MANHOURS AVERAGE DIRECT LINE

NO. MEASURE UNIT TOTAL MANDAYS RATE TOTAL COSTS TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

AF FORM 3052, JAN 88 PREVIOUS EDITION IS OBSOLETE. FOR OFFICIAL USE ONLY

I Type : 1-Story (Each Unit)

1 Excavation, Remove and dispose M³

2 Aggregate/Concrete M³

3 4" PVC Vent from Suction Pit M

4 Exhaust Fan with Cover include Electrical Work SET

5 Asbestos/ LBP sampling and testing LOT

6 Misc. Materials and Labor (Sodding, Repair Existing Tile, etc.,) LS

Total Direct Cost

AF FORM 3052, JAN 88 PREVIOUS EDITION IS OBSOLETE. FOR OFFICIAL USE ONLY

CONSTRUCTION COST ESTIMATE BREAKDOWN (CONTRACTOR) Expires 31 October 1989

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE Install Radon Mitigation, NON-GOH (32UN)

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

EVKP 15-4383 Various MFH, Okinawa, Japan

MATERIAL COST LABOR COSTS

UNIT OTHER

LINE ITEM OF QUANTITY MANHOURS AVERAGE DIRECT LINE

NO. MEASURE UNIT TOTAL MANDAYS RATE TOTAL COSTS TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

II Type : 2-Story (Each Unit)

1 Excavation, Remove and dispose M³

2 Aggregate/Concrete M³

3 4" PVC Vent from Suction Pit M

4 Exhaust Fan with Cover include Electrical Work SET

5 Asbestos/ LBP sampling and testing LOT

6 Misc. Materials and Labor (Sodding, Repair Existing Tile, etc.,) LS

Total Direct Cost

AF FORM 3052, JAN 88 PREVIOUS EDITION IS OBSOLETE. FOR OFFICIAL USE ONLY