This technical description and related solicitation are for the provision of natural gas services at Yokosuka Naval Base in Japan. The contractor shall supply natural gas at a minimum pressure of 0.3-1.0 MPa and quality of 40.6 MJ/Nm3 to the Cogeneration Plant building at an estimated maximum hourly flow of 9,000 m3/Hr and annual consumption of 49,000,000 m3/Yr. The contractor must conduct regular and emergency inspections of the 100m government-owned gas line and respond to emergency calls within 30 minutes. The contractor shall submit inspection and emergency response plans within 10 days of award. Pricing shall be calculated monthly based on actual usage and gas resource cost adjustments, with the government paying no less favorable rates than applicable to Japanese government agencies. The minimum annual order is 44,100,000 m3 for the first year.

Attachment 1 Technical Description

View the file

Other files for this federal contract opportunity

Other files attached to Natural Gas at Yokosuka, newest first.
File Type Posted
Q&A_20190131.pdf PDF
10._Amendment02.pdf PDF
Pre-proposal_Conf_Minutes.pdf PDF
Q&A-2.pdf PDF
9_TD_amend01_20190201.pdf PDF
8_Amendment01.pdf PDF
5_Exhibit_A_Pricing_Schedule.pdf PDF
7_Atch_2_Est_consumption.pdf PDF
1_Policies_Procedures_Ltr.pdf PDF
2_NTO.pdf PDF
3_NTO_ID_instruction.pdf PDF
4_FA520919R8000.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1 to Solicitation No. FA520919R8000

Technical Description for

Natural Gas at

Yokosuka Naval Base

20 Dec 2018

1. General Description of the Natural Gas Requirements: The contractor shall provide all personnel, equipment, tools, materials, supervision and other items and services necessary to provide natural gas, twenty four (24) hours a day, seven (7) days a week, to the Cogeneration Plant, Bldg. #3030 at Yokosuka Naval Base. The contractor shall conduct periodic and emergency inspections on the US Government-owned gas line from the Yokosuka Naval Base property boundary to the on-base facility connection point in accordance with Japanese Gas Business Act (Act No. 51 of March 31, 1954) and all other relevant laws. The distance from the existing gas supply point at the property boundary near Route 16 to the facility connection point is approximately 100 meters. A drawing of the existing gas line will be provided a later date.

1.1. Required Natural Gas Pressure/Volume at the Cogeneration Plant at Supply:

Contractor shall ensure the following pressure, quality, and type of gas is provided to the boiler plant listed above, twenty-four (24) hours a day, seven (7) days a week:

- Supply Pressure at the plant: 0.3 – 1.0 MPa at normal supply temperature of 30 deg C or below

- Quality of gas/heat content: 40.6 MJ/Nm3(LHV)

- Type of gas: City Gas 13A

It is estimated that the following natural gas volumes will be required:

- Projected Hourly Maximum Flow: 9,000 m3/Hr

- Projected Annual Consumption: 49,000,000 m3/Yr

- Annual Minimum Order Amount: 44,100,000 m3/Yr

- Minimum Guarantee Amount: 44,100,000 m3 for the first year of the contract

1.2. Required Technical Submittals: The contractor will provide the following technical submittals as part of this contract within 10 business days after award: Inspection/Maintenance Plan, and Emergency Response Plan.

1.2.1. Inspection/Maintenance Plan: The contractor shall submit an Inspection/Maintenance Plan for government acceptance. The contractor’s Inspection/Maintenance Plan shall include maintenance in accordance with the manufacturer’s recommendations, as well as all relevant gas and construction laws, including but not limited to: the governor systems, all filters and valves, the emergency shut-off valve system, and all above ground gas piping systems to include leak detection as outlined by the following:

- Maintenance of Governor: Maintenance will include stopping the governors and disassembling them, replacing each component, cleaning the filters, and cleaning up following the work. This inspection will occur at least once every 36 months or as often as recommended by the manufacturer (whichever time is shorter).

- Leak-Detection of Gas Pipes: Leak-detection will be accomplished by closing the main valve and measuring and recording the pressure to check that it is possible to stop the gas supply. If it is not possible to stop the gas supply, the pipelines will be inspected with a gas leak detector. This inspection will occur at least once every 40 months according to Gas Utility Industry Law or upon request.

- Open-close Test of Valve: Each valve will be inspected by shutting it half-way to ensure that it is functioning properly. This inspection will be provided upon request by NAVFAC Far East.

- Measurement of Potential at Each Magnesium-Electrode: The potential of each magnesium-electrode will be measured and the condition of buried gas pipes checked as part of this inspection. The inspection will occur once every 40 months or as recommended by the manufacturer, whichever is shorter.

- Inspection of Emergency Shut-Off Valve: This inspection will only occur under the condition that the gas supply will be interrupted. It will include an operation test and a total test. There will be an inspection of the appearance, inside equipment, and batteries.

Measurement of the insulation resistance and a horizontal check of seismometer will also be performed. The inspection will be performed as recommended by the manufacturer.

1.2.2. Emergencies: The contractor shall provide an Emergency Response Plan to the government for acceptance. The Emergency Response Plan shall define the procedure by which service shall be restored in the event of an emergency, including but not limited to: the size and composition of the response team, the initial equipment brought to diagnose the issue, the maximum response time to an emergency call, and any leak detection/damage sensing methods employed. For the purposes of this statement of work, an emergency is defined as any unscheduled interruption of service, including but not limited to: natural disasters, leaks and line maintenance performed without prior notification., The Contractor must be able to receive trouble calls from the Government, 24 hours a day, 7 days a week, and respond within thirty (30) minutes of an emergency call and inspect the gas system. The Contractor shall report to the Contracting Officer/Technical Representative upon arrival on site.

No later than the first day of performance, after contract award, the contractor shall provide to the Contracting Officer the Point of Contact (POC) list so that NAVFAC Far East can contact the Contractor POC, 24 hours a day, 7 days a week in case of emergency, including but not limited to gas or gas stoppage. The contractor shall provide an updated list to the Contracting Officer no later than the date the POC list change takes effect during the contract term. The contractor shall contact at least thirty (30) calendar days in advance to schedule periodic inspection, on the Government-owned gas line.

1.3. Periodic and Emergency Inspection on Government-Owned Gas Line: In accordance with Japanese Gas Business Law, the contractor shall conduct periodic and emergency inspections on the Government-owned gas line. A schedule of these inspections will be provided to NAVFAC Far East in accordance with paragraph 1.2.1. The contractor shall notify the Government if it finds the Government-owned gas lines to be in an unsafe condition or needs repair in accordance with industrial standards. All repairs to government owned gas lines will be made at Government expense, except those that have been determined to be caused by the

Contractor’s negligent acts or omissions. Any debris and materials generated from the inspection at the site shall be cleaned and disposed of by the contractor.

1.4. Meter Reading and Calculation of Gas Consumption

1.4.1. Meter Devices: Contractor shall install suitable metering equipment of standard manufacture, and maintain and repair them at Contractor’s expense. When more than a single meter is installed at a service location, the readings thereof may be billed conjunctively, if appropriate. In the event any meter fails to register (or registers incorrectly) the services furnished, the parties shall agree upon the length of time of meter malfunction and the quantity of service delivered during such period of time. An appropriate adjustment shall be made to the next invoice for the purpose of correcting such errors. Meter devices shall be certified and inspected in accordance with Measurement Act (Act No. 51 of May 20, 1992).

1.4.2. Meter Reading: The Contractor shall read all meters at periodic intervals of approximately 30 days or in accordance with the policy of the cognizant regulatory body or applicable bylaws in the presence of Government representatives. The contractor shall include the date of the meter reading in all official communications.

1.4.3. Meter Test: At the written request of the Contracting Officer, the Contractor shall test any and all identified meters in the presence of Government representatives. The cost of such additional tests shall be borne by the Government if the percentage of errors is found to be not more than 1 percent slow or fast. In the event the meter is found to be out of tolerance, the cost shall be borne by the contractor.

1.5. Annual Estimate Order: An annual Estimate Order will be issued each year (prior to gas being supplied) to inform the Contractor of the estimated quantity, estimated monthly usage, and unit price fixed in Attachment 1, Pricing Schedule for the year.

2. Gas Price

2.1. Rates and Charges of Service: In accordance with Article VII of the Agreement Under Article VI of the Treaty of Mutual Cooperation and Security Between the United States of America and Japan, Regarding Facilities and Areas and the Status of United States Armed Forces in Japan (SOFA), the rates and charges of natural gas under this contract shall be no less favorable than those that may be applicable from time to time to the ministries and agencies of the Government of Japan.

2.2. Gas price shall be calculated as follows:

Gas Price = Usage x (Unit Price ± Gas Resource Cost Adjustment Price)

2.3. Gas Resource Cost Adjustments: The unit price shall be adjusted on a monthly basis in accordance with the Ordinance for Enforcement of the Gas Business Act and contractor’s latest version of rules and regulations, so called “Ooguchi Gas Jukyuu Yakkan” in Japanese, submitted to the Ministry of Economy, Trade and Industry of Government of Japan. The Gas Resource Base is ¥57,300/ton.

2.4. Charges: If the certain price factors are in excess or below the specified amount, penalty fees are charged as follows:

2.4.1. Minimum Order: The Government shall order a yearly Minimum Order amount. If the actual yearly usage does not reach the yearly Minimum Order, a settlement amount for shortage of Minimum Order will be charged.

Calculation:

Settlement amount for shortage of yearly Minimum Order = (Yearly Minimum Order - Actual yearly usage) x Average actual adjusted unit price of the year

2.4.1.1 Exceptions: No penalty shall be assessed for failing to achieve the minimum purchase order in the event that circumstances beyond the control of the government prevent the flow of gas from reaching the contracted buildings.

2.4.2. Excess of Hourly Max Flow Volume Charge:

When the Hourly Max Flow Volume exceeds the contract Hourly Max Flow Volume, an overage fee shall be assessed. The fee shall be calculated in accordance with the Contractor’s rules and regulations, so called “Ooguchi Gas Jukyuu Yakkan” in Japanese.

2.4.3. Yearly Load Factor: Yearly Load Factor is calculated as follows:

Yearly Load Factor = Monthly average usage in a year / Monthly average usage in the Peak Demand Season (December, January, February, and March)

When the actual yearly Load Factor is less than 75 %, shortage of yearly Load Factor will be charged.

Calculation Formula:

Settlement amount for shortage of yearly Load Factor = [(Average of monthly usage in the Peak Demand Season x 12 x 75%) - Total Annual Usage] x Average of adjusted annual unit price

2.4.4. Invoices:

An invoice shall include calculation formula to cite evidence for a Gas Resource Cost Adjustment Price of the month. Unit price of Gas Resource Cost Adjustment as well as the gas price shall be listed separately on the invoice. Charges for a settlement amount for shortage of yearly minimum order, excess of hourly max flow volume, and shortage of yearly load factor, if any, shall be listed separately on the invoice.