Attachment 10 AF FORM 66.xlsx

XLSX spreadsheet 54 KB Posted

Attached to
Repair Arctic Warrior Chapel Bldg. 3 Project HJZH211093
Solicitation number
FA500021R0078
Issued by

About this file

This document is a submittal schedule for a federal contract to renovate the multi-purpose room at the Arctic Warrior Chapel Building 3 on Joint Base Elmendorf-Richardson in Alaska. The schedule outlines 22 required submittals including plans for interior paint, flooring, wall panels, lighting layout, fire alarms and hazmat usage. Submittals are due between 15 and 30 days after notice to proceed. The contract will be awarded by the Department of the Air Force Pacific Air Forces to renovate the room by installing a new drop ceiling, perimeter walls, flooring, doors and room divider. Electrical work will include new lighting and devices. Work will also include asbestos and lead abatement.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittal 1

SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBERPROJECT NAMESOLICITATION /CONTRACT NUMBER
HJZH 21-1093Repair Arctic Warrior Chapel B3
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
LINE NUMBERNote: 3 copies required per submittal. Government will retain all submittals.Provide an electronic copy for each submittal.CERTIF. OF COMPLIANCESHOP DRAWINGSCOLOR SELECTIONMANUFATURUR'S RECOMMENDATIONCATALOG DATAO&M RECOMMENDATIONSCALCULATIONSWARRANTYDRAWINGSREPORTSAFETY DATA SHEETSOTHERTEST RESULTSREQUIRED SUBMISSION DATEDATE TO CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSAPPROVEDDISAPPROVEDCONTRACTOR SUBMITTALFINAL APPROVALNOTES
GENERAL
1Project Specific AF Form 66XNTP + 15Required if there is deviation from this AF Form 66
2AF Form 3064 Contract Progress ScheduleXNTP + 10Government approval required before on site work proceeds.
3Contractor's Health, Safety, and Environment PlanXNTP + 15
4Contractor's QA/QC PlanXNTP + 15
ARCHITECTURAL
5Interior PaintXXNTP + 15Finish coat shall be satin
6Cove Base, rubber, 4" High x 1/8" thickXXNTP + 15
7Wainscot, FRP, 48"XXNTP + 15
8Flooring, Athletic Sports Rubber Tile, 3/8" Thick, 24" x 24", Glue Down,XXXNTP + 15Provide physical sample. Provide specs showing ASTM fire resistance
9Full room height paneled and sound proofed (minimum 50 STC) manual operable folding partition with a single viewing glazeXXXXNTP + 15Partition finish shall be white marker board
10Interior Wall PaintXXNTP + 15
11Floor self leveling compoundXNTP + 15
12Suspended Ceiling System, 24" x 24" gridXNTP + 15
13Suspended Ceiling mineral fiber tegular acoustical Tiles, 24" x 24" X 5/8"XXXNTP + 15
14Suspended Ceiling, resilient rubber sound isolation hangersXXNTP + 15Manufacture's recommendation to include installation instructions
155 1/2" thick mineral wool batt insulationXXNTP + 15
16Gypsum Wall Board, Type "X"XXNTP + 15
17Door, Metal, hollow core, Dutch wirh glazeXXNTP + 15
18Door, Metal, hollow CoreXXNTP + 15
19Door, Metal FrameXXNTP + 15
20Door, LocksetXXNTP + 15
21Carpet Transition Strip, High Profile, rubberXXNTP + 15
ELECTRICAL
22Troffer Light Fixture, LED, 24" x 24", 5000 KelvinXXXNTP + 15Drawings: Provide reflected ceiling fixture layout and calculations to illustrate that a 50ft candle lighting level is achieved.
23Fire alarm strobe and hornXXNTP + 15Provide product specifications and NFPA compliance
HAZMAT
28JBER HAZMAT Usage Tracking FormXNLT 10 working days prior to material being brought onto installation
29JBER HAZMAT Usage Tracking FormXNLT 7 Working Days After Final Acceptance
30$_FINAL_ENV_PRECON ChecklistXNTP + 10
CLOSEOUT
31Folding partition operating instructionsXInstall + 4
32As Builts (electronic CAD and PDF)XFinal + 7Government will provide cad bid drawings for as-built development

&"Arial,Bold"&6AF FORM 66, OCT 99 &"Arial,Regular"Previous Edition Will Be Used