Breaker Repair Q&A:

Q - Is it an absolute requirement that this work be accomplished on site, or would the customer be willing to crate the breaker and ship it to our facility for initial test and inspection, with a full report to follow? We would then provide the report with any recommendations for approvals prior to proceeding with the repairs and the required maintenance, per the SOW. This breaker would return to the customer in a "Like-New" Condition, ready for service, with a full warranty, and test reports as required.

A - Electric Shop foreman and I discussed this question. It is beyond our capability to remove the breaker from the substation and prepare for shipment. Also part of the contract is to make the breaker functional again within the circuit it protects and verify the system is operational. This would have to be accomplished onsite.