Questions_Set_3.pdf
PDF 179 KB Posted
- Attached to
- Frequency Converters Federal contract opportunity
- Solicitation number
- FA4801-18-Q-1116
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Frequency_Converter_PWS_(REVISED).pdf | ||
| Frequency_Converter_PWS_(REVISED).pdf | ||
| Questions_Set_2.pdf | ||
| Site_Visit.pdf | ||
| Site_Visit.pdf | ||
| Frequency_Converter_PWS_(REVISED).pdf | ||
| Questions_Set_1.docx | DOCX document | |
| Frequency_Converter_PWS.pdf | ||
| Combo-Frequency_Converters.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. In the hangars with the 90-kVA units called out, do you require actual output remote control boxes or do we keep it as stated that the converter will have remote provisions only and a remote box will be installed at another time?
ANSWER: Yes, we would need the remote control boxes in the hangarettes to opporate the SSFC units individually.
2. Can the equipment startup and training be performed after the complete install of all equipment with an additional 5 days?
ANSWER: 1.2 and 1.4.4 have been updated in the Frequency Converter PWS document.
3. Can the bid be extended until Monday for review of the installation information?
ANSWER: The solicitation has been extended to 17 September 2018. It will close 0800 (8:00 am) MT.