Updates_changes_in_Statement_of_Work_for_FA4800.pdf
PDF 64 KB Posted
- Attached to
- CCTV Installation
- Solicitation number
- FA4800-17-Q-0012
About this file
Listing of changes made in Statement of Work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Updated_Vendor_Questions_and_Answers.docx | DOCX document | |
| Vendor_Questions_and_Answers_for_FA4800.docx | DOCX document | |
| Security_Equipment_Install_SOW.pdf | ||
| HQ_ACC_A2O_Building_617_Security_Upgrade.pptx | PPTX presentation | |
| FA4800-17-Q-0012.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Updates changes in Statement of Work for FA4800-17-Q-0012 (CCTV Installation)
(Updated 6/27/17)
• 4.1 The amount of power receptacles to be installed has been updated to specify a total of seven (7).
• 4.2 Plenum cable has now been specified as a required material for the installation of the strobe lights.
• 4.3 Switches at the entrance and exit to control the strobe lights has been specified (two).
• 4.4 The front LCD monitor has been specified as being required to have split screen capability (Rear LCD split screen capability optional).
• 4.5 Camera capabilities are required to be of digital quality or equal.