SON_Dock_3_Hexavalent_Chromium_and_Lead_Abatement-__Aug_2016.pdf
PDF 18 KB Posted
- Attached to
- Bldg 1075 Dock 3 Chromium 6 and Lead Abatement
- Solicitation number
- FA4686-16-T-0044
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site_Visit_Q A.pdf | ||
| Site_Visit_Sign_In_13_Sept_16.pdf | ||
| AF_Form_813_Dock_3_Bldg_1075.pdf | ||
| Wheatland_Gate.jpg | JPG image | |
| route_to_CONS.jpg | JPG image | |
| Latest_EAL_Template.xls | XLS spreadsheet | |
| Combo_for_Dock_3.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Need (SON)
Project Title: Chromium 6 and Lead Abatement, B1075 Dock 3 Date: 29 Aug 2016
SUMMARY OF WORK
1. Contractor-Provided Performance Work Statement: The Government Scope of Work documents the major line items of work the Government expects to see accomplished, but it does not attempt to explain the details and/or method for Contractor execution. The contractor shall provide a detailed narritive on how they intend to abate all hazardous material.
2. Project Scope: The project is to abate all hexavalent chromium and lead in hanger at
Dock 3. The Contractor shall furnish all materials, labor, plans, tools, equipment, transportation, supervision, hazardous waste identification/disposal, management, quality assurance, services items, and incidentals necessary to accomplish this task order in accordance with the contract and all applicable regulatory requirements.
3. Major Items of Work: Work includes, but is not limited to the following items:
3.1 Abate all hexavalent chromium and lead found throughout the hanger of Dock 3.
Contractor will be required to remove and dispose approx. 35K sf of bird netting using a 65’ man lift, and clean approx. 229K sfca (square foot contact area), along with 800 LF of HVAC system. Hanger will be deemed clean when a total of 100 wipe samples taken at random positions throughout hanger by 3rd party are below 7.5 micrograms per 100 cm2 for hexavalent chromium and 4.3 micrograms per 100 cm2 for lead are achieved. Preferred method of cleaning is by using HEPA filter vacuums, but gov’t is open to other methods if proposed.
4. Work Restrictions: Work will be performed at Beale AFB in Bldg. 1075 Dock 3. Base access passes are required in this area the same as for the main base areas and no unauthorized entry is permitted by any Contractors or by any delivery vehicles except by normal base entry procedures. Standard contract work hours of 8am to 5pm shall be in effect.
5. Desired Performance Period: 90 days after award of contract.
6. APPLICABLE STANDARDS: Contractor will demonstrate that they can complete the work safely in accordance with commercial practices and all federal, state and local regulations. Commercial Abatement processes and procedures include (As may be Applicable):
Federal Occupational Safety and Health Administration (OSHA) 29 CFR 1910.1025.
Federal Occupational Safety and Health Administration (OSHA) 29 CFR 1910.1026.
Federal Respiratory Protection Standard, 29 CFR 1910.134.
7. Site Visit: Due to the size of the hangar and the nature of the cleaning that is being requested a site visit is MANDATORY for this requirement prior to submitting your proposal. You will be required to submit and EAL 3 days in advance for all personnel that will be coming on base to look at the site. Pay close attention to the REAL ID Act requirements that were implemented 15 Aug 2016.
8. If you have any questions about this request for proposal you can contact SSgt Brian
Bilello at 530-634-2574 or brian.bilello@us.af.mil.
BRIAN BILELLO, SSgt, USAF Contracting Officer mailto:brian.bilello@us.af.mil