Statement of Work

View the file

Other files for this federal contract opportunity

Other files attached to Renovate Building 2641 at March ARB, newest first.
File Type Posted
SF30_-_Amendment_0001.pdf PDF
Atch_9_-_Questions_and_Answers_22_August_2017.pdf PDF
Atch_1_-_General_Decision_Number_8-4-17.pdf PDF
Site_walk_notes.pdf PDF
Atch_4_-_Schedules_of_Material_Submittal.pdf PDF
Atch_6_-_FEP_March_ARB_June_2016_Signed.pdf PDF
Atch_8_-_Bid_Opening-Bid_Delivery_Pass_Sheet.docx DOCX document
Atch_7_-_Security_Pamphlet.pdf PDF
SF1442_Solicitation_FA4664-17-B-0002.pdf PDF
Atch_3_-_Drawings-Pictures-As-built.pdf PDF
Atch_1_-_General_Decision_Number.pdf PDF
Atch_5_-_Specifications.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 2 to

FA4664-17-B-0002

Air Force Reserve Command

March Air Reserve Base

Riverside, California 92518

STATEMENT OF WORK

RENOVATE EAST SIDE

BUILDING 2641

March Project Number

PDPG 17-0116

Prepared By

452 MSG/CECC

13 July 2017

1. INTRODUCTION

1.1 Contractor shall provide all materials, equipment, labor and supervision necessary to renovate the east side of building 2641 at March Air Reserve Base, California in accordance with the terms and conditions of the contract, contract statement of work, contract specifications, federal, state and local codes, laws and regulations.

1.2 All quantities, dimensions and areas given within the statement of work are an approximation only. Contractor is responsible to verify all quantities, dimensions and areas.

1.3 The construction area is identified on drawing #1.

1.4 All work includes, but is not limited to the following:

2. SCOPE OF WORK

2.1 Remove and dispose approximately 3, 628 square feet of carpet flooring.

2.2 Remove and dispose approximately 825 linear feet of cove base.

2.3 Remove and dispose approximately 3,628 square feet of ceiling tiles only (framing will remain). Any insulation shall be reinstalled when the new ceiling times are replaced. The same style of new ceiling tiles will be installed.

2.4 Remove and dispose approximately 8749 square feet of wall paper from walls and columns. Also, remove approximately 15 corner guards (2” x 2” x 8’).

2.5 Remove and dispose approximately 86 linear feet of wall railing within room 1057.

Also, new wall railing within room 1057 will need to be installed.

2.6 Remove approximately 3 fire alarm devices from the suspended ceiling tiles. After installation of new ceiling tiles, re-attach the fire alarm devices in approximately same location.

2.7 Remove and dispose of approximately 60 outlet receptacles and outlet cover plates; three in floor outlet receptacles and outlet cover plates; 7 double light switches and switch plate covers; and 8 single light switches and switch plate covers. Install new outlet receptacles with outlet cover plates, light switches and switch plate covers and approximately 10 blank cover plates on all open/exposed junction boxes.

2.8 Prepare flooring to install approximately 403 square yards of new glueless carpet tack tile squares and 825 linear feet of 4” vinyl cove base. Preparation may include grinding, surfacing, floor patch and float. Floor shall be one level when repairs are complete prior to installation of carpet floor tiles and cove base.

2.9 Prepare interior walls, columns, door frames, window sills, hard lid ceiling in room

1077 (main entrance area) and men’s and women’s bathrooms (rooms 1087 and 1088 respectively) for interior painting to include rough sanding, wall patching and texturing of damaged areas.

2.10 Paint approximately 9351 square feet of interior walls, columns, door frames, window sills, hard lid ceiling in room 1077 (main entrance area) to include men’s and women’s bathrooms (rooms 1087 and 1088 respectively) with one coat primer and two top coats of paint.

2.11 Furniture is to remain within the construction area. All precautionary measures must be exercised to protect and keep the furniture safe to avoid damage.

3. GENERAL WORKSITE

3.1 As-built and drawings provided are “For Reference Only” however, the contractor shall field verify.

3.2 Contractor will dispose of and remove off base construction debris and materials.

Contactor shall prepare a recycling report for construction and recycled debris removed from March ARB during the course of this project. Report must include name and address of the receiving facility, tonnage and type of material disposed and recycled.

3.3 The contractor shall prepare a pass information sheet identifying contractor personnel, including subcontractor personnel, who will be working on March ARB. The pass information sheet shall be submitted to the Contracting Office no later than the preconstruction meeting. Upon completion of the contract, or expiration of the passes/badges, the contractor must ensure all issued passes/badges are turned into the

Contracting Office. Failure to comply with this requirement may result in withholding of final payment.

3.4 The prime contractor shall appoint a superintendent, in writing to the Contracting Office, with decision making authority prior to start of work. The superintendent will be the

Governments point of contact at the construction site.

3.5 Pre-Final Inspection: The contractor shall request a pre-final inspection with the contracting officer representative (COR). Pre-final inspection shall be requested with sufficient time to allow punch list corrections, if any, prior to contract completion date.

3.6 Final Inspection: The contractor shall request a final inspection, in writing to the

Contracting Officer, upon correction of pre-final punch list items. The final inspection will be formally scheduled by the Contracting Officer upon confirming that pre-final punch list items have been corrected. At a minimum, contractor Superintendent, Contracting Officer and COR will be in attendance.

3.7 The contractor shall submit, to the Contracting Office, material submittals as identified in the Schedule of Material Submittals and as required by applicable specifications.

Submittals shall be submitted by the required submission date as identified on the

Schedule of Materials Submittals. Submittal packages shall be provided to the

Contracting Office accompanied with an AF IMT 3000-Material Approval Submittal. A copy of the approved/disapproved signed AF IMT 3000 will be provided to the contractor upon completion of government review.

3.8 The contractor is responsible for completion and submittal of March Form 103 “Base

Civil Engineering (BCE) Work Clearance Request” to the BCE prior to beginning any work performance. The contractor shall allow a minimum of fourteen (14) calendar days for processing. The March Form 103 will be valid for the duration of the project.

4. PERFORMANCE

4.1. The performance period is 70 calendar days from Notice to Proceed (NTP). The contractor shall begin work as described in the scope of work within 10 days of receiving

NTP. Work including punch list items, must be completed no later than the end of the performance period.