Attachment 1 FA4626 341 MW Missile Cable Erosion/ Conduit Repair
CAO 20-1001
01000-1
SECTION 01000
341 MW MISSILE CABLE EROSION/CONDUIT REPAIR
GENERAL REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY OF WORK FOR PROJECT CAO 20-1001
A. This place of performance will be for up to 40 locations throughout the 10th, 12th and 490th Missile Squadrons in the Malmstrom AFB Missile Field located within a 140 mile radius of Great Falls, MT. These 40 sites will vary on type of work from directional bore to erosion repair. The directional boring will consist of placing a continuous length of 4” or 6” conduit a minimum of 5’ below the creek or river bank. The conduit will start and stop within the Missile Cable Right of Way/Easement. The erosion repair will include placement of rip rap, fill dirt, topsoil, the installation of broad based dips, water turns outs and wattles. During construction, the Government will make every effort to provide the Contractor with sites in close proximity to each other in order to facilitate ease of construction and to keep mobilization efforts to a minimum. The Contractor shall provide all plant, labor, equipment, supervision, services, and materials to execute and satisfy the requirements of this Contract.
B. Whenever brand names of products are listed throughout this Specification it shall be implied that the brand specified or approved equal may be used.
C. Recycling Initiative: The Contractor shall provide recycled products specified in this Section to the extent obtainable IAW the provisions of Executive Order 13423, the requirements specified in Section 01360, and the Specification requirements in this Section. If conflicts exist between the products specified in this Section and the recycled product, the Contractor shall provide a recycled product that most nearly matches the salient features of the specified product.
D. Winter Shutdown. No winter exclusion for this project.
E. The period of performance for this contract shall be 1 Base year plus 4 additional years.
1.2 SITE VISITS
A. It shall be the responsibility of each Offeror to visit the work site to determine the nature, extent, and pertinent details of the Contract. The drawings attached to the specifications show the general arrangement and approximate dimensions at the site.
The successful Offerors shall be responsible for determining number of items, dimensions and details required for the proper accomplishment of the work as covered in the solicitation. The Contracting Officer will schedule only one pre-proposal site
01000-2 visit. The Contractor must notify the Contracting Officer a minimum of twenty-one
(21) days prior to the scheduled date of visit with intent to attend the site visit.
1.3 QUANTITIES AND LOCATIONS
A. Offerors must satisfy themselves by personal examination of the quantities and locations of the proposed Work.
1.4 LUMP SUM PRICES ON CONTRACTS
A. Where lump sum prices are required, the lump sum price shall include all work required to complete each item listed as lump sum in the Proposal Schedule.
1.5 CODES AND STANDARDS
A. Refer to drawings for codes and standards date that project was designed. Work shall meet the requirements of the plans and specifications and shall not be less than the minimum requirements of applicable sections of the latest Codes and Standards of following organizations (Not All Inclusive - See Each Division
ACI American Concrete Institute
AWWA American Water Works Association
ASTM American Society for Testing and Materials
AASHTO American Association of State Highway and Transportation
Officials
NFPA National Fire Protection Association
NEC National Electrical Code
NESC National Electrical Safety Code
OSHA Occupational Safety and Health Association
UL Underwriters Laboratories
USASI United States American Steel Institute
1.6 SAFETY
A. The Contractor shall comply with all existing Occupational Safety and Health Act (OSHA) standards of safety at all times in the performance of this Contract. Hazards to the safe use of the premises due to the Contractor's work and/or equipment shall be suitably marked at all times. Pedestrian and vehicle traffic ways shall be kept clear and unobstructed.
01000-3
B. The Contractor shall submit with the Quality Control Plan, the name of the designated on-site safety persons responsible for ensuring that all safety and accident prevention provisions of this Specification are implemented and enforced. The Contractor shall ensure his personnel receive safety training and briefings and that all safety inspections, practices, and procedures are within compliance. The name of the designated on-site safety persons, safety training, briefings, inspections, practices and procedures shall be included in the Quality Control Plan.
C. The Contractor shall indoctrinate each employee to ensure clear understanding of the following subject areas, but not limited to:
1. The purpose of the accident prevention program (i.e., to minimize hazards and prevent injuries).
2. A review of the hazards inherent in the work environment and the precautions to be taken.
3. Location of first aid and other emergency facilities.
4. A detailed description of what to do in case of injury, fire, or identification of a safety hazard.
5. Review of cleanup procedures.
6. Required safety equipment including earplugs, goggles, face guards, respirators, protective clothing, hard-hats, etc. (when and how to use).
7. Location of company safety rules (posting or handout).
8. Identification of the Contractor employees responsible for safety/accident prevention.
D. In addition to normal safety practices, the Contractor shall comply with the following requirements:
1. The safety of Contractor personnel on-site is the Contractor’s responsibility.
2. All personnel shall comply with Air Force on-site safety procedures and additional procedures as directed by the Contracting Officer or his designated representative when the Contractor's safety person is not immediately available.
3. The Contractor shall ensure that safety barriers/portable ladders, ladder extensions, or environmental covers are properly installed at access hatches and excavations.
4. Equipment shall be placed so as not to impede normal traffic in and out of the work area, nor to interfere with emergency exit from work area and off-site.
5. Hard-hats shall be worn in accordance with OSHA requirements and hard-toed safety shoes shall be worn by all personnel at all times on the work site. Other safety items such as ear protection, respirators and safety glasses, which are required by OSHA and/or the manufacturer of products for specific hazards, shall be available and used as necessary.
01000-4
6. All heavy equipment shall be equipped with backup alarm in accordance with OSHA regulations.
7. All vehicles shall be in safe operating condition. Vehicles and equipment not in compliance with OSHA requirements shall not be allowed on site.
E. A number of hazards inherent to the work environment must be recognized. They include, but are not limited to:
1. Mechanical devices can pose serious hazards when operated. Appropriate precautions shall be taken.
F. First aid and medical requirements are as follows:
1. The Contractor shall comply with accident response requirements. These requirements are provided in a safety briefing by base personnel at the pre-construction conference. The Contractor shall keep these requirements on file at the working site for inspection by Air Force personnel.
2. The Contractor shall maintain an emergency first aid kit at the work site in accordance with requirements.
3. The Contracting Officer or his designated representative will assist in coordinating emergency medical, ambulance, or airlift requirements.
G. All accidents (employee injuries and vehicle, building, or equipment property damage, etc.), regardless of severity, shall be reported promptly to the Contracting Officer or his designated representative.
1.7 SECURITY AND ENTRY
A. N/A
PART 2 - PRODUCTS
NOT APPLICABLE.
PART 3 - EXECUTION
3.1 PRE-PERFORMANCE MEETING
A. There shall be a pre-performance meeting between the Government and the Contractor a minimum of five (5) working days prior to commencement of work under this Contract (Notice to Proceed).
3.2 INSPECTION
01000-5
A. The Contractor shall schedule with the Inspector during normal work hours the times for inspecting items such as “Concealed Work” or other times for escort duties. The inspector will be the spokesman for compliance with the specifications and drawings.
The Contracting Officer will resolve controversies between the inspector and the Contractor.
3.3 SUBMITTAL SCHEDULE
A. The Contractor shall submit the Schedule of Materials Submittal with “REQUIRED SUBMISSION DATE (BY CONTRACTOR)” dates filled in for each line number within ten (10) days after notice to proceed. It is the responsibility of the contractor to complete the submittal form and insert dates for each submittal item not already designated by the Government as having a mandatory due date. The Contractor shall schedule and submit all required items for major systems at the same time to coordinate and enhance review of interrelated components. It is the Contractor’s responsibility to ensure dates provided on this form do not create any delays in construction. This Contractor completed form will be used by the Government for tracking submittal progress.
3.4 SUBMITTALS
A. Submittals shall be recorded on AF Form 3000, shall have the Submittal ID No., Specification paragraph number and description of material as labeled on Submittal Schedule. Revised Submittals shall have the same Submission Number followed by a dash with the revision number. The Contractor shall submit to the Contracting Officer for review and approval the following information: Manufacturer’s product brochures and catalog data for all equipment, components and materials to be installed under the terms of this Contract. All material Submittals shall be original vendor information (not copies) and include location on Drawings and/or Specifications with cross referencing information to Drawing schedules and Specifications, dimensional, assembly, and sub-assembly Drawings, parts lists, and other data required to completely describe each item. Include the Drawing schedule letter, symbol, or plan mark on the Submittal. Where more than one product is listed in a document, the item submitted shall be properly identified by circles, arrows, or a description with cross-references. Four (4) copies of each Submittal are required.
B. Circle or arrow all descriptive literature to accomplish identification of specific components/items which are proposed to be furnished. Government will not react to descriptive material/literature, which has not been circled or arrowed, except to reject the Submittal. Highlighting does not appear on subsequent copies and therefore is unacceptable.
C. If Contractor is proposing to use an exact brand name or product specified, a submittal for that item is not required. The Contractor will submit a letter to the Contracting officer stating each item that will be provided exactly as specified and referenced to the original submittal item. In some circumstances, even though a specified product is provided, a submittal may be required for color selection, etc.
01000-6
3.5 PERMITS
A. The Government will be responsible for securing all permits as may be necessary for the completion of all work required by this project. Contractor will adhere to all requirements in the permits.
3.6 WORK SCHEDULE
A. The Contractor shall have a tentative schedule for construction at the pre-performance meeting. This coordinated schedule shall change if it is in the best interest of the Government at no additional cost to the Government. Delays due to weather, to include inability of Government Inspector to travel to the site because of Road master-declared hazardous road conditions, shall result in no cost to the Government.
B. NOT USED.
C. Contractor shall coordinate all work with the Cable Affairs Office at 731-2459.
3.7 WORK TIMES
A. The work schedule will be from 6:00 am – 6:00 pm week days. Work will only be conducted Monday- Friday and no work will be conducted on Federal Holidays.
Additional hours shall be coordinated with the Contracting Officer within three working days prior to implementation of hour change.
3.8 START OF WORK NOTIFICATION
A. The Contractor shall notify the Contracting Officer and the Cable Affairs Office (731- 2459) not later than 9:00 A.M. on Tuesday of the week prior to the scheduled workweek. This shall include, but is not limited to, when the initial construction work shall begin, notifying when work shall resume after a work stoppage of more than three workdays. The Contractor shall be aware that the Notice to Proceed is not sufficient notification when initial work shall begin.
3.9 WASTE, PROCESSING AND STORAGE SITES
A. Processing and storage sites shall be only those areas described at the pre-construction meeting. Location of stockpiled materials will be coordinated with the Cable Affairs Office and approved by the Contracting Officer. Upon Project completion, the storage area shall be restored to original condition (equal to that before Project start) to include all finish grading, leveling, shaping, contouring, and seeding. All waste shall be disposed of at a properly licensed disposal facility, unless otherwise approved.
3.10 UTILITIES
A. No Utilities will be made available to the Contractor. The Contractor shall provide any and all necessary power.
01000-7
B. No restroom facilities are available at the jobsites. It is the responsibility of the Contractor to provide a portable latrine (Porta-Potty) at each site for the duration of construction at each site.
3.11 UTILITY OUTAGES
A. N/A
3.12 MAINTENANCE OF AIR FORCE OPERATIONS AND CONTINUED USE
A. N/A
3.13 QUALITY CONTROL
A. General: THE CONTRACTOR IS RESPONSIBLE FOR QUALITY CONTROL. THIS
IS CONSIDERED BY THE GOVERNMENT TO BE A MAJOR INSPECTION ITEM
OF THIS CONTRACT. In addition to CONTRACT CLAUSE, INSPECTION OF CONSTRUCTION, the Contractor shall comply with the Quality Control Provisions as specified herein. The Contractor shall perform all Quality Control inspection and/or testing required by this contract unless specifically designated to be performed by the Government. The Quality Control system must consist of personnel, plans, procedures, and organization necessary to provide materials, equipment, workmanship, fabrication, construction, and operations that comply with Contract requirements. The system shall cover construction operations, including fabrication both on-site and off-site, and shall be keyed to the proposed construction sequence. If the Contractor fails to submit an acceptable Quality Control Plan, The Contracting Officer will refuse to allow construction to start.
B. Quality Control Plan: The Contractor shall submit the Quality Control Plan within ten
(10) working days after Notice to Proceed (NTP). The Contractor's Quality Plan shall identify the personnel, procedures, instructions, records, forms; and, as a minimum, shall include the following:
1. Include the names: Quality Control Manager, on-site safety person, the number, classifications, qualifications, duties, responsibilities, and authorities of personnel. A copy of a letter, signed by an authorized official of the firm, which describes the responsibilities and delegates the authorities of the Quality Control Manager, shall be furnished.
2. The Quality Control Manager shall work directly for the company president or owner and must have a minimum of five years experience as Quality Control Manager or Inspector. Include qualifications in the submitted plan for Government approval.
3. A job-specific, work-item checklist will be developed by the Contractor for inspection purposes. The list will be broken into Sections identical to the Contract Specifications and will contain all inspection actions necessary to ensure full compliance with the Contract. These inspections shall be annotated on the Quality Control Records.
01000-8
4. A Sample Quality Control Record from a simplified and generic project is attached to indicate the level of detail expected.
5. Provide documentation format for Contractor's Quality Control activities and testing. The Sample of Quality Control Record form is to be used for documenting daily inspections, corrective actions, tests, etc.
6. Environmental Compliance and all permits are Quality Control Managers responsibilities.
7. Quality Control testing procedures, including corrective actions to be taken where non-compliance is noted, is the responsibility of the Quality Control Manager.
8. Ensure a complete set of Contract Specifications, Modifications, full size Drawings and all other pertinent information are on each site during construction.
9. N/A
10. The process for addressing varying site conditions, managing work at remote sites, and working with security requirements is part of this Plan.
11. N/A
12. Methods to ensure scheduled appointments are met and documentation to verify arrival and departure times at the work site.
13. Safety program that ensures complete compliance with OSHA and all Safety requirements. The name of the designated on-site safety persons and safety training, briefings, inspections, practices and procedures shall be included in the Quality Control Plan.
14. A Submittal Schedule program that ensures a completed Submittal Schedule is followed.
15. N/A
C. This Contract requires a Quality Control Manager. The individual assigned shall be responsible for this Project.
1. The Quality Control Manager shall be responsible for ensuring all requirements of the Specifications, Drawings, and Quality Control Plan is met.
2. The Contractor's Quality Control activities to be performed at the work site include those of subcontractors, off-site fabricators, and suppliers.
3. The Quality Control Manager is required to dedicate one hour per workday towards this specific duty.
D. Acceptance: The Quality Control Plan will be reviewed and accepted by the Contracting Officer. The Contractor shall make such changes and additions necessary for clarity and completeness as requested by the Contracting Officer. Acceptance is conditional and the Government reserves the right to require the Contractor to make changes in the Quality Control Plan, personnel, and operations to correct deficiencies found by the Government during performance of work. No change shall be implemented prior to acceptance in writing by the Contracting Officer. Non-
01000-9 compliance with the Quality Control Plan will result in one or more of the following actions at the Government's discretion:
1. Directed removal and replacement of the QC Manager.
2. Reduced progress payments until corrections are made.
3. Cure notices, other applicable contracting actions up to, and including possible Contract termination for default.
4. Other contractual actions deemed appropriate by the Contracting Officer.
E. Quality Control Records: The Quality Control Records shall contain a record of daily inspections for each site with all work accomplished. Specific items of work checked each day will be annotated. All work-in-place must be certified as complying with the Contract plans and Specifications. Non-compliance items must be clearly noted.
Corrective actions must be outlined and detailed for non-compliance items. The Contractor shall maintain daily records, which will be on-the-job site and available for review by the Contracting Officer or his technical representative. Daily reports will be signed by the designated Quality Control Manager and will indicate hours spent on Quality Control at the MAF for that day. A copy of the QC daily reports shall be given to the Project Inspector.
3.14 SUPERVISION
A. There shall be one on-site supervisor at the work site during all work. Submit names with Quality Control Plan.
B. Each on-site supervisor will be responsible for all Contractor and subcontractor workers, and adherence to the Specifications and Drawings.
3.15 SPECIFICATIONS, MODIFICATIONS, AND DRAWINGS
A. A complete set of Contract Specifications, all modifications, and full size Contract Drawings. Other information such as Submittals, etc, shall also be present.
3.16 AS-BUILT DRAWINGS AND DATA
A. ASBUILT DRAWINGS: N/A
3.17 ROAD CLOSURES
A. N/A
3.18 CONTRACTOR VEHICLES, EQUIPMENT AND MATERIALS
A. The Contractor shall provide all vehicles and equipment necessary to accomplish the Contract work. Power equipment shall be equipped with safety and noise limiting devices. The equipment shall be in a safe and efficient operating condition.
01000-10
B. All vehicles shall be maintained in a safe operating condition in accordance with OSHA standards. All vehicles not essential to the job will be left off site.
C. The Contractor will be permitted to store necessary materials and vehicles on site.
Only those materials, storage vehicles or equipment mounted vehicles that must remain overnight or over the weekend and directly pertain to the work being performed at the site may be stored. Material must be placed in a designated area per Waste, Processing, and Storage Site paragraph and will not interfere with site access. Storage must be coordinated with the Contracting Officer or his designated representative. The Contractor shall submit to the Contracting Officer at the pre-construction conference the size of storage area requested. The Government shall not be responsible for the loss of Contractor material, tools, or equipment.
D. The Contractor is hereby informed that the access roads from the main road to the work sites are private property and, in some cases, county or state property. The parking of vehicles on the access road or adjacent property is strictly prohibited unless permission has been obtained from the Contracting Officer.
E. At the end of each workweek, the Contractor shall clean up the work area debris, ensure the security of equipment, tools and work/Contract materials.
3.19 CONCEALED WORK
A. All items of work to be concealed shall be Government inspected prior to concealment.
All Government inspection hours shall be scheduled per Section 01000, Work Times.
3.20 CONSTRUCTION AREA
A. The Contractor shall confine construction operations as much as feasible. Complete restoration of the area to existing conditions shall be the responsibility of the Contractor and shall be at the Contractor’s expense.
3.21 CONSTRUCTION NEAR UTILITY SYSTEMS (AF Form 103)
A. The Contractor is responsible for contacting Montana 811 for all utility locates in the areas were excavation operations will be conducted. TO THE MAXIMUM EXTENT
POSSIBLE, ELIMINATE PERMANENT MARKINGS ON PAVEMENT AND
CURBS. Location marks shall be removed after 14 calendar days. Digging within three feet of buried communications cables, environmental monitoring wells, electrical cables, irrigation systems, and gas lines shall be performed by hand digging until the utility is exposed. The Project Inspector shall be notified three days prior to digging within a three-foot area near this utility. A representative from the Cable Affair Office must be present during excavation of the Missile Communications Cables. The cable piping routes must be marked prior to excavation in the area. The Contractor shall be held responsible for any damage to a marked or identified utility by excavation procedures. Once the utility is exposed, mechanical excavation may be used if there is no chance of damage occurring to the cable or piping system. If required the government shall be responsible for processing the Work Clearance Request (AF
01000-11
Form 103). This permit shall be completed prior to start of any construction work. The approved permit shall be valid for a period not to exceed 180 calendar days.
B. N/A
C. The Contractor shall be held responsible for any damage to the utility by excavation procedures. The Contracting Officer and Project Inspector shall be immediately notified of all damage.
3.22 PROTECTION OF EXISTING FACILITIES
A. The Contractor shall be responsible for the protection of features outside the construction limits and within the construction limits such as existing structures, fences, roads, paving, curbs, sidewalks, utility appurtenances, and equipment. Provide temporary heating as required. The repair or replacement of such items damaged during construction will be at the Contractor's expense.
3.23 CONSTRUCTION STAKING
A. The Contractor shall provide construction staking.
3.24 NUCLEAR DENSOMETERS
A. N/A
3.25 CONFINED SPACE REQUIREMENTS
A. N/A
3.26 NOTICE OF FINAL INSPECTION AND ACCEPTANCE
A. A final inspection will be held after completion at each work site. This inspection must be coordinated with the Contracting Officer and Government Inspector and should include at a minimum these personnel. Any discrepancies found will be corrected within 7 days of final inspection. Final payment SHALL NOT occur until all discrepancies are corrected, final acceptance, and all environmental permits are received. All work at one site must be completed before being allowed to proceed to the next work site.
01000-12
QUALITY CONTROL REPORT TO INSPECTOR
Date: ____________
CONTRACT NO.
FA4626-
TITLE AND LOCATION
MALMSTROM AFB MT
REPORT NO.
CONTRACTOR (Prime or Subcontractor)
NAME OF SUPERINTENDENT OR QC REP
WEATHER TEMPERATURE
WEATHER EFFECTS
PRIME CONTRACTORS/SUBCONTRACTOR WORKFORCE
(If space provide below is inadequate, use additional sheets
NUMBER
TRADE
HOURS
EMPLOYER
ACTIVITY/TASK PERFORMED
COMP
NON
COMP
TOTAL WORK HOURS ON
JOB SITE THIS DATE______
CUMULATIVE TOTAL OF
WORK HOURS FROM
PREVIOUS REPORT_______
TOTAL WORK HOURS
FROM START OF
CONSTRUCTION
KTR INITIALS CERTIFY INSPECTION OF ACTIVITY INITIALS
WERE THERE ANY LOST TIME ACCIDENTS THIS DATE?
� YES � NO
IF YES, A COPY OF THE COMPLETED OSHA REPORT IS REQUIRED
CONSTRUCTION AND PLANT EQUIPMENT LEFT ON JOB SITE UNTIL USE IS
COMPLETED
DESCRIPTION DATE FIRST ON JOB
(FIRST TIME ONLY)
HOURS WORKED THIS DATE HOURS
IDLED
DATE OF FINAL
REMOVAL FROM JOB SITE
01000-13
CONSTRUCTION AND PLANT EQUIPMENT NOT LEFT ON JOB SITE
PERMANENTLY
(This will include pickup trucks and mobile mounted items, such as compressor, that are also used for transportation to and from the job)
DESCRIPTION HOURS WORKED HOURS IDLED
SPEC PARA
AND/OR
DRAWING NO.
LOCATION AND DESCRIPTION OF DEFICIENCIES
(Materials, Equipment, Safety, and/or Workmanship) ACTION TAKEN OR TO BE
TAKEN
REFERENCE
DEFICIENCIES CORRECTED THIS DATE
REPORT
NO.
COMPLIANCE
NOTICE NO.
01000-14
INSPECTION AND/OR TESTING
PERFORMED TODAY-FOLLOW WITH
REPORT
LOCATION
AND/OR ELEMENT
OF WORK
REMARKS
RESULTS OF
INSPECTION/TESTING
SPEC PARA/
DRAWING
NO.
EQUIPMENT/MATERIAL RECEIVED TODAY TO
BE INCORPORATED IN JOB (Description, Sizes, Quantity)
SUBMITTAL NO.
OR
CERTIFICATION
DATE
APPROVED
REMARKS:
(Document Total QC Hours for this Day, Directions Received from Government, and Compliance Notices, Etc)
Quality Control Rep Date
CONSTRUCTION REPRESENTATIVES REMARKS AND/OR EXCEPTIONS TO THIS REPORT
Construction Representative Date
END OF SECTION 01000
QUALITY CONTROL REPORT TO INSPECTOR