Questions and Answers.pdf

PDF 88 KB Posted

Attached to
Storage Removal and Replacement Federal contract opportunity
Solicitation number
FA4626-22-Q-0011
Issued by
Department of the Air Force Global Strike Command

View the file

Other files for this federal contract opportunity

Other files attached to Storage Removal and Replacement, newest first.
File Type Posted
Atch 1 - SOW Revised 8 June 22.pdf PDF
Amendment 002.pdf PDF
Amendment 001.pdf PDF
Space Saver Photo Four (4).jpg JPG image
Space Saver Photo Three (3).jpg JPG image
Space Saver Photo Five (5).jpg JPG image
Space Saver Photo One (1).jpg JPG image
Space Saver Photo Two (2).jpg JPG image
Combined Synopsis Solicitation 22-Q-0011.pdf PDF
Atch 1-SOW.pdf PDF
Atch 2-Installation Perimeter Access Control.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUIREMENT NAME AND SOLICITATION NUMBER

Questions and Answers

Question # Question Answer

Will the lights above the cage impede the illumination inside the cage? If so, can lights be placed inside the new storage system (cage).

No. Lights above the cage will not impede illumination inside the cage. Lights cannot be placed inside the cage due to concerns with machines operating inside the cage to access the top shelves.

Would a crane be too big for removal? What equipment is best suited for the job? Yes. A crane would be too big. The current storage system is located in a warehouse, and there is access to get smaller machinery (i.e. forklifts) inside for removal.

3 What is the weight of the Rolodex Space Saver System? Unknown due to the system being currently assembled.

4 How high are the ceilings in the warehouse? Estimated 25 feet.

5 Can the existing fence be used to build off of? Yes.

6 Is there a specific gauge of fence requested? No. However, the gauge must be thick enough to ensure entry cannot be gained if the chain link fabric is pulled on.

7 Does the Government already have the chain link, sliding door, and cypher lock for the contractor's use? No. The contractor is responsible for all material and equipment to perform the job.