Atch 1 - SOW Revised 8 June 22.pdf
PDF 111 KB Posted
- Attached to
- Storage Removal and Replacement Federal contract opportunity
- Solicitation number
- FA4626-22-Q-0011
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions and Answers.pdf | ||
| Amendment 002.pdf | ||
| Space Saver Photo Three (3).jpg | JPG image | |
| Space Saver Photo Five (5).jpg | JPG image | |
| Space Saver Photo One (1).jpg | JPG image | |
| Space Saver Photo Two (2).jpg | JPG image | |
| Amendment 001.pdf | ||
| Space Saver Photo Four (4).jpg | JPG image | |
| Atch 2-Installation Perimeter Access Control.pdf | ||
| Combined Synopsis Solicitation 22-Q-0011.pdf | ||
| Atch 1-SOW.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
STORAGE SYSTEM
REMOVAL AND
INSTALLATION
MALMSTROM AFB, MT
1. GENERAL
1.1. Summary of work: The contractor shall provide all labor, equipment, tools, accessories and materials to properly remove existing Rolodex Space Saver System and install a secured chain link asset storage caged area in Building 400 on Malmstrom
AFB, MT.
2. MATERIALS
2.1. The contractor shall provide all material to complete the removal and installation.
3. EXECUTION
3.1. The performance period will be 60 calendar days after award date.
Working hours will be from 7:00 AM to 4:00 PM, Monday through Friday.
3.2. The contractor shall coordinate all activities with the LRS Chief Inspector, this facility will be in use during installation.
3.3. REMOVAL
• Current Rolodex Space Saver System needs to be removed, palletized & secured, and transported by the contractor to Defense Logistics Agency Disposition Services (DLADS), with the exception of specifically marked cabinets contained in the location.
• Current lighting for the Rolodex Space Saver system may be reused, but the contractor may supply new lighting. The lighting after installation of the cage needs to be approximately 1 foot above the new cage ceiling but allows enough access for changing bulbs/maintenance.
• Wooden flooring under the Rolodex Space Saver system needs to be disassembled and removed.
• Concrete flooring under wooden flooring needs to be leveled and all holes filled.
3.4. INSTALLATION
• Install a secure chain link asset storage caged area.
• Chain link must be secured to the poles and roof to prevent anyone from pulling the chain link fabric to gain entry.
• Chain link should cover all four sides and the ceiling portion of the caged area.
• Cage area will be installed roughly in the same location of the removed
Rolodex Space Saver system.
• Cage will cover an area of 33 feet wide by 36 feet long and 11 feet high.
• Install a sliding door on the northern corner with the door sliding to the right and measuring 12 feet long by 9 feet high.
• Install a cypher lock on the door to the caged area to ensure only authorized personnel can access the area.
The government will inspect and accept the area when completed by the contractor to ensure the final product meets the standard set forth in this document.
4. SECURITY AND FPCONs
All personnel are required to abide by all real world (Force Protection Conditions) FPCON measures, RAMs, shelter-in-place, lock-down notices as directed (i.e. mandatory badge/ID check and hand carried items will be searched). During periods of heightened security and FPCONs, the Contractor shall still be responsible for meeting the same contractual agreements unless notified by the Contracting Officer that access has been temporarily suspended or restricted. During times of heightened security, delays at the entry gates should be expected; also movement on to and around the base will be significantly restricted.
5. CLEAN UP
5.1. Clean up of the job site shall be the responsibility of the contractor.
5.2. Waste generated by the Contractor in performance of the services specified with this SOW shall be disposed of by contractor off base in compliance with State and Local ordinances.
6. SITE VISIT
6.1. A site visit may be arranged for all interested parties to get a complete understanding of the requirement.
| 1. GENERAL |
| 2. MATERIALS |
| 3. EXECUTION |
| 5. CLEAN UP |