Questions_for_LF_Surface_Drainage_Set_1.pdf

PDF 78 KB Posted

Attached to
Repair LF Surface Drainage Federal contract opportunity
Solicitation number
FA4626-18-R-0015
Issued by
Department of the Air Force Global Strike Command

View the file

Other files for this federal contract opportunity

Other files attached to Repair LF Surface Drainage, newest first.
File Type Posted
Amendment_1.pdf PDF
Attach_5_Wage_Determinations_MT_67,_76,78.pdf PDF
Solicitation_FA4626-18-R-0015.pdf PDF
Attach_6_Installation_Perimeter_Access.pdf PDF
Attach_3_Schedule_of_Drawings.pdf PDF
Attach_1_Specifications.pdf PDF
Attach_7_Special_Contract_Requirements.pdf PDF
Attach_8_Past_Performance_Questionaire.pdf PDF
Attach_4_Drawings.pdf PDF
Attach_2_Submittal_Schedule.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions for LF Surface Drainage Set 1

1. Can the Superintendent also be the QC Officer?

Response: Yes, the superintendent can also be the QC Officer.

2. N-07--I didn't see an item for precast on the submittal log, would precast be acceptable for the catch basins?

Response: Yes, precast catch basins are acceptable.

3. N-07--Is there a length for the 18" CMP?

Response: The length of new 18" CMP is approximately 35 feet.

4. N-07--What type of fill is acceptable between the catch basins, over the new 18" CMP?

Response: Acceptable fill is a gravel backfill, 3/4" minus.

5. E-10--Will the access road require any import gravel?

Response: E-10 access road does not require any additional gravel.

6. N-06--Other than the crushed top course for the new culvert installation and approach, will the access road need a lift of top course?

Response: N-06 access road does not require a full lift of top course. However, some additional material may be required for reshaping to replace the material that has been eroded away.

7. 22 13 16-1 Piping and Related Materials has in bold print a list of materials to be submitted to the Government Inspector.

I cannot find where this material is used in the contract?

Response: My apologies, the materials listed on 22 13 16-1 do not apply to this project. Please disregard.