Questions_for_LF_Surface_Drainage_Set_1.pdf
PDF 78 KB Posted
- Attached to
- Repair LF Surface Drainage Federal contract opportunity
- Solicitation number
- FA4626-18-R-0015
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_1.pdf | ||
| Attach_5_Wage_Determinations_MT_67,_76,78.pdf | ||
| Solicitation_FA4626-18-R-0015.pdf | ||
| Attach_6_Installation_Perimeter_Access.pdf | ||
| Attach_3_Schedule_of_Drawings.pdf | ||
| Attach_1_Specifications.pdf | ||
| Attach_7_Special_Contract_Requirements.pdf | ||
| Attach_8_Past_Performance_Questionaire.pdf | ||
| Attach_4_Drawings.pdf | ||
| Attach_2_Submittal_Schedule.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions for LF Surface Drainage Set 1
1. Can the Superintendent also be the QC Officer?
Response: Yes, the superintendent can also be the QC Officer.
2. N-07--I didn't see an item for precast on the submittal log, would precast be acceptable for the catch basins?
Response: Yes, precast catch basins are acceptable.
3. N-07--Is there a length for the 18" CMP?
Response: The length of new 18" CMP is approximately 35 feet.
4. N-07--What type of fill is acceptable between the catch basins, over the new 18" CMP?
Response: Acceptable fill is a gravel backfill, 3/4" minus.
5. E-10--Will the access road require any import gravel?
Response: E-10 access road does not require any additional gravel.
6. N-06--Other than the crushed top course for the new culvert installation and approach, will the access road need a lift of top course?
Response: N-06 access road does not require a full lift of top course. However, some additional material may be required for reshaping to replace the material that has been eroded away.
7. 22 13 16-1 Piping and Related Materials has in bold print a list of materials to be submitted to the Government Inspector.
I cannot find where this material is used in the contract?
Response: My apologies, the materials listed on 22 13 16-1 do not apply to this project. Please disregard.