18Q0113_Atch_1_SOO_13_Sep_2018.pdf

PDF 873 KB Posted

Attached to
Portable SCIF Federal contract opportunity
Solicitation number
FA462518Q0113
Issued by
Department of the Air Force Global Strike Command

About this file

Updated SOO with correct solicitation number.

View the file

Other files for this federal contract opportunity

Other files attached to Portable SCIF, newest first.
File Type Posted
FA462518Q0113,_Ack-Amd.pdf PDF
18Q0075_Atch_1_SOO_13_Sep_2018.pdf PDF
Q_&_A_SCIF_Portable_FA462518Q0075_9-7-2018.pdf PDF
18Q0113_Atch_3_Bldg_706_Floor_Plan.pdf PDF
FA462518Q0113_Combo_4Sep18.pdf PDF
18Q0113_Atch_2_Clause_Full_Text_Info_9Aug18.pdf PDF
18Q0113_Atch_1_SOO_8Aug18.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S AIR FORCE

Statement of Objectives Portable or Transportable SCIF Options

72 Test Evaluation Squadron

9/13/2018

Table of Contents

1. Objective:

2. Scope:

3. Engineering Objectives:

3.1. Operational Floor Design:

3.1.1. Security & Accreditation (Minimum):

3.1.1.1. The contractor will provide Information Assurance support for Security

Engineering (which includes requirements analysis, design, and testing) in accordance with

ICD 503 3

3.1.1.2. The SCIF will meet or exceed TEMPEST ICS 705-1 standards

3.1.2. Operations Floor Space: (Minimum)

3.1.2.1. Minimal space to support 6 standard workstation consoles (Table A2), Situational

Awareness (SA) wall, and 4 network printers

3.1.3. Power & Cooling: (Minimum)

3.1.3.1. The SCIF's main power supply will be connected to commercially-provided electrical power grid within the vault. Power is located is located as seen in attachment 3 of the solicitation, Building 706 diagram

3.1.3.2. The SCIF will connect and receive heating, cooling, and power from existing vault.

Heating and cooling duct work will attach to 8” vents

3.1.4. IT Infrastructure: (Minimum)

3.1.4.1. The SCIF environment will be capable of supporting a minimum of 10 security enclave/network services (2xNIPR/1xSIPR/1xJWICS/4xSAR/2x spare)

3.1.4.2. The SCIF will provide a method to provide physical separations for a minimum of

10 different security enclaves (2xNIPR/1xSIPR/1xJWICS/4xSAR/2x spare)

3.1.4.3. The SCIF will have weather proof external connection panels for power and fiber optic network connectivity

3.1.4.4. Cables for all security domains will implement the following color coding scheme:

TS = Yellow, Secret = Red, Centrix = Purple, Unclassified = Green (additional details and specifications are outlined in Table A-3, A-4)

3.1.4.5. The contractor will apply the appropriate colored tape and marker labels on all cables per the SCIF interconnect diagram (the interconnect drawings, and the label format will be provided by the Customer)

3.1.5. IT Infrastructure: (Optional)

3.1.5.1. No optional requirements exist at this time

3.1.6. Transportation & Deployment: (Minimum)

3.1.6.1. The contractor will design and deliver a portable SCIF

3.1.7. Miscellaneous: (Minimum)

3.1.7.1. The SCIF will be accessible through an entrapment area

3.1.7.2. 3.1.7.2. The SCIF fire suppression system will be a self contained internal fire suppression system.

3.1.8. Miscellaneous: (Optional)

3.1.8.1. The SCIF will have an integral floor

3.1.8.2. The SCIF will have LED lighting technology where applicable

3.1.9. Maintenance & Support: (Minimum)

3.1.9.1. The contractor will develop and deliver training materials and operating instructions

3.1.9.2. The contractor will create a Standard Operating Procedures (SOP) check list for the prerequisites required for moving the SCIF to include reassembly instructions

3.1.9.3. The contractor will provide a 1 year warranty period to cover all delivered items. . 4

4. Documentation:

4.1. Contract Data Requirements List (CDRL)

4.2. Integrated Master Schedule (IMS)

4.3. Drawings

5. Period of Performance:

6. Non-Disclosure Agreement:

List of Tables

Table A-1 Server Room Specifics:

Table A-2 Operations Floor Specifics:

Table A-3 Fiber Optic and Copper Cabling Specifics:

Table A-4 Server Room Zone Box Distribution to Floor Zone Box Specifics:

Statement of Objectives:

Portable or Transportable SCIF – Options

Prepared By: Whiteman AFB

1. Objective:

The objective of this engineering effort is to discover and contractually engage an experienced contractor/contractor to provide a functionally suitable Sensitive Compartmented Information

Facility (SCIF) interior to an existing Special Access Required (SAR) Vault. The structure will house a Top Secret-level mission operations floor (ops floor). The structure will be constructed interior to the existing SAR Vault that will be accessed by a 4’X7’ vault door so the expectation is the panels will be approximately 24” X 96” with assembled height of 8’. The SCIF will be approximately 20’X26’X8’ with an internal mantrap at entrance leaving a 4’ hallway running the span fo the existing room. Entrance location and hallway are shown in attachment 3 of the solicitation, building 706 diagram. All internal work areas will be provided by the Government.

2. Scope:

This Mobile or Transportable SCIF Solution will be used as a working site, within the existing vault.

3. Engineering Objectives:

Winning contractor will provide the following item(s) delivered and received and installed at 72

Test and Evaluation Squadron, Building 706 room 138A, Whiteman AFB, MO

3.1. Operational Floor Design:

3.1.1. Security & Accreditation (Minimum):

3.1.1.1. The contractor will provide Information Assurance support for Security

Engineering (which includes requirements analysis, design, and testing) in accordance with ICD 503

3.1.1.2. The SCIF will meet or exceed TEMPEST ICS 705-1 standards

3.1.2. Operations Floor Space: (Minimum)

3.1.2.1. Minimal space to support 6 standard workstation consoles (Table A2), Situational Awareness (SA) wall, and 4 network printers

3.1.3. Power & Cooling: (Minimum)

3.1.3.1. The SCIF's main power supply will be connected to commercially-provided electrical power grid within the vault. Power is located is located as seen in attachment 3 of the solicitation, Building 706 diagram.

3.1.3.2. The SCIF will connect and receive heating, cooling, and power from existing vault. Heating and cooling duct work will attach to 8” vents.

3.1.4. IT Infrastructure: (Minimum)

3.1.4.1. The SCIF environment will be capable of supporting a minimum of 10 security enclave/network services (2xNIPR/1xSIPR/1xJWICS/4xSAR/2x spare)

3.1.4.2. The SCIF will provide a method to provide physical separations for a minimum of 10 different security enclaves

(2xNIPR/1xSIPR/1xJWICS/4xSAR/2x spare)

3.1.4.3. The SCIF will have weather proof external connection panels for power and fiber optic network connectivity

3.1.4.4. Cables for all security domains will implement the following color coding scheme: TS = Yellow, Secret = Red, Centrix = Purple, Unclassified =

Green (additional details and specifications are outlined in Table A-3, A-

4)

3.1.4.5. The contractor will apply the appropriate colored tape and marker labels on all cables per the SCIF interconnect diagram (the interconnect drawings, and the label format will be provided by the Customer)

3.1.5. IT Infrastructure: (Optional)

3.1.5.1. No optional requirements exist at this time.

3.1.6. Transportation & Deployment: (Minimum)

3.1.6.1. The contractor will design and deliver a portable SCIF.

3.1.7. Miscellaneous: (Minimum)

3.1.7.1. The SCIF will be accessible through an entrapment area

3.1.7.2. The SCIF fire suppression system will be a self

contained internal fire suppression system.

3.1.8. Miscellaneous: (Optional)

3.1.8.1. The SCIF will have an integral floor.

3.1.8.2. The SCIF will have LED lighting technology where applicable

3.1.9. Maintenance & Support: (Minimum)

3.1.9.1. The contractor will develop and deliver training materials and operating instructions

3.1.9.2. The contractor will create a Standard Operating Procedures (SOP) check list for the prerequisites required for moving the SCIF to include reassembly instructions.

3.1.9.3. The contractor will provide a 1 year warranty period to cover all delivered items.

4. Documentation:

Winning contractor will provide the following documentation prior to fabrication delivered and received at Whiteman AFB:

4.1. Contract Data Requirements List (CDRL)

o Document to include Requirements satisfying contractor specifications and concerns listed in Appendix A and other Requirements not yet specified or determined o The contractor will identify and provide a consolidated final as-built Bill of Material

(BOM) per configuration

4.2. Integrated Master Schedule (IMS)

4.3. Drawings

o The contractor will create and deliver drawings in MS Visio format, in compliance with drawing standards. The drawing set includes the following:

o Drawing Tree o Indentured Parts list o Top Level Drawing o SCIF Floor Plan o SCIF Internal network connection and/or cabling diagram o SCIF External connection panel(s) o Data Flow Diagram o Site Layout

5. Period of Performance:

The period of performance and delivery of transportable SCIFs is 6 months from contract award.

6. Non-Disclosure Agreement:

The winning contractor will provide and live by Non-Disclosure Agreements to protect United

States Air Force security, design and Engineering.

Appendix A: Drawings and Specifications

Table A-1 Server Room Specifics:

Space to Accommodate Eighteen Server Racks min.

Desired Ceiling Height Approx. TBD ft. height min.

Ceiling Mounted Basket Cable Raceway 12 in. wide as needed

Cooling and Heating System - Total Must connect to existing duct work

Electrical Power Capacity Approx. 62K Watts

Enclave Network Connectivity NIPR, SIPR, JWICS, Guest Network

Table A-2 Operations Floor Specifics:

Space to Accommodate Six Workstation Consoles

Space to Accommodate One Workstation Table

Space to Accommodate One Printer Table

Ceiling Mounted Basket Cable Raceway 6 in. wide as needed

Individual Circuit 2 per Workstation NEMA 5-20R Double Receptacle

Individual Circuit 1 per Printer Location NEMA 5-15R Double Receptacle

Individual Circuit 1 per Situational

Awareness Location

NEMA 5-15R Double Receptacle

Table A-3 Fiber Optic and Copper Cabling Specifics:

All Cabling Network Security Classification Plenum

Rated Sheath Color

All Fiber Optic Cabling Corning Brand Glass

All Fiber Optic Cabling Multimode/Singlemode 50 micron OM3 or

OM4 where applicable

Infrastructure Cabling Recommendation 12 or 24 Fiber MPO Cassettes

Unclassified Network Copper Cabling Category 6 (CAT6) w Green Plenum or equivalent

Table A-4 Room Zone Box Distribution to Operational Floor Zone Box Specifics:

Operational Floor Zone Box 1 per Workstation Console

Operational Floor Zone Box 1 per GCS Table

Operational Floor Zone Box 1 per Printer Table

Table A-5 Server Room Zone Box Distribution to External Connection Point Specifics:

Operational Floor Zone Box 1 per identified location

Network connections per work area 24 Fiber Strands