Question and Answers from Solicitation

View the file

Other files for this federal contract opportunity

Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions about IDIQ Contract

Solicitation #FA4625-14-R-0001

Page 01010-3(6) - Government furnished Materials and Tools.

Location for Job Trailer: Can the old LaFarge Concrete Plant location be used as a location for a job trailer? It is fenced separately from the base and only access to the main base is through a gate.

Answer: No

Page 01010-5(16) - Maintenance of Documents.

Government requires the Contractor to maintain documents at the job site. We will need a job trailer to comply with this requirement. IDIQ is a base wide contract.

Answer: No, documents can be maintained in site superintendent’s vehicle.

Page 01010-6(26) - Solid Construction, Demolition and Deconstruction Waste Requirements.

Clarify disposal of Reusable and Recyclable Material.

A) Is this Government or Contractor Material?

Answer: Contractor

B) Where are these items to be disposed?

Answer: In accordance with Page 01010-6(26) (g) - Solid Construction, Demolition and Deconstruction Waste Requirements These shall be properly disposed, diverted, recycled, or reused.

Note: Line “C” items to be diverted off base.

C) Does concrete with wire or rebar inside need to be broken up to segregate material completely?

Answer: No

D) Does removable items going off base need to be weighed on scales?

Answer: No, Volume (cubic yards, etc.) is sufficient.

Section 02964 – Cold Milling of Bituminous Pavements. Line 3.3 Removal of Milled Material.

In Section 01010 – Summary of Work Page 01010-6 #26 it states in Line “C” Reusable and Recyclable Material to be diverted off-base. Milled asphalt is a recyclable material used in making new asphalt. Please clarify.

Answer: The millings will remain the property of the Government, and will be stockpiled on base.

Question: The Seed Project does not contain a bid schedule to complete.

Answer: The Seed Project is informational only and will be the first delivery order awarded under this

IDIQ. Upon award of the main contract, the guarenteed minimum will be funded toward the Seed

Project.