STATEMENT OF WORK
FOR
B-1B PAINT RESTORATION
1. Background for Requirement
The B-1B aircraft on static display in the museum airpark is in need of new paint in order to mitigate water intrusion and resultant corrosion, and must be repainted in order to provide a quality display appearance.
2. Scope of Work
The contractor shall provide all management, tools, supplies, equipment, parts, and labor necessary to accomplish the painting of the static display aircraft. The contractor will also be responsible for ensuring environmental regulation compliance.
3. Service Delivery Summary
The objective of service is to properly prep, sand, prime, and paint the Barksdale Global Power Museum B-1B static display aircraft. The aircraft engine inlet covers tires and landing gear will be repainted as well. Surface contamination will be removed through use of environmentally approved high-pressure wash cleaner and thorough rinsing. After sufficient drying time, existing paint will be scraped and sanded to feather edge, peeled or otherwise defective paint and to properly scuff surface in preparation for paint application. Care will be taken by contractor during task in order to protect ground underneath and around aircraft from negative environmental impact.
Primer will be applied to ensure solid paint application. The color coats will be Catalyzed Urethane type paint or better (subjective to approval by curator). You must obtain a wet mil thickness of 4.0-
4.5 mils. One coat applied in two medium wet passes may be adequate to accomplish the above specification. If not, a second coat will be applied. Then 2 or more coats of Valspar AC4400 Clear coat HS or better will be applied to give a high gloss and long lasting UV protection. The windows will also be prepped and sprayed and have the same polyurethane clear coat as the rest of the aircraft. The aircraft is to be painted in its current paint scheme with its all current insignia and markings. Insignia and markings (i.e stars and bars, tail number) will be repainted in the same size, color, and location as they are currently. Stenciling will be reapplied in the proper location and size and painted on. Vinyl stickers will not be used unless approved by curator. Unpainted surfaces (landing, taxi lights, navigation and position lights, etc) will be masked off and protected from paint overrun. Care will be taken by contractor during task in order to protect ground underneath and around aircraft from negative environmental impact. Aircraft will be sprayed using HVLP equipment. Rolling, brushing or airless spraying will not be accepted. All stenciling will be reapplied using proper paint in the location and size as well.
4. Services Provided by Museum Staff Personnel
4.1 Local Representative/Point of Contact (POC). Contractor will work with Global Power Museum personnel for coordination of time on site. Contractor will work with Museum personnel to properly match paint colors insignias etc..
4.2 Hours of Operations. Start date of contract 15-30 days once Contract has been awarded.
Pending weather due to exterior work, estimated period of performance is 14-21 days (estimated). Hours of operation 0730-1500 Monday – Friday. In addition a weekly schedule should be provided and coordinated with the Global Strike Museum personnel.
5. Mandatory Contractor Credentials and Requirements
• Contractors MUST perform in person visual site visit prior to bid.
• Contractor must provide at least 3 past performance references within the past 5 years
• Contractor must show proof of performing jobs of the same or larger magnitude on historical aircraft
• Contractor will need to be able to work on military base, meet all background and insurance needs to drive on and off the pass as needing during period of work.
**CONTRACTOR MUST PROVIDE PROOF OF ALL REQUIREMENTS
LISTED ABOVE**
Holidays are as follows:
New Year's Day - 1 January 2021 Martin Luther King's Birthday - 18 January 2021 Washington's Birthday (President's Day) - 15 February 2021 Memorial Day - 31 May 2021 Juneteenth – 19 June 2021 American Independence Day - 5 July 2021 Labor Day - 6 September 2021 Columbus Day - Second Monday in October Veterans Day - 11 November Thanksgiving Day - 25 November 2021 Christmas Day - 25 December 2021
| 1. Background for Requirement |
| 2. Scope of Work |
| 3. Service Delivery Summary |
| 4. Services Provided by Museum Staff Personnel |
| 5. Mandatory Contractor Credentials and Requirements |
| **CONTRACTOR MUST PROVIDE PROOF OF ALL REQUIREMENTS LISTED ABOVE** |
File details come from the government source that posted it. Updated .