Solicitation FA4608-15-R-0004
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Removable_Bollard_Detail-Bollard_Detail_(Standard)a.pdf | ||
| BOLLARDS_Permanent.pdf | ||
| Questions_and_Answers__1.docx | DOCX document | |
| FA4608-15-R-0004-0001.pdf | ||
| Attachment_11_-_Vendor_Bid_Sheet_(Revision_1).xls | XLS spreadsheet | |
| Site_Visit_Attendance_Sheet.pdf | ||
| Attachment_6_-__AFI_32-1001.pdf | ||
| Attachment_2_-_Environmental_Req'ts_(Oct_14).pdf | ||
| Attachment_1_-_Specifications.pdf | ||
| Attachment_9_-_Past_Performance_Questionnaire.pdf | ||
| Attachment_5_-_Insurance.pdf | ||
| Attachment_7_-_Storm_Water.pdf | ||
| Attachment_3_-_AF66.pdf | ||
| Attachment_11_-_Vendor_Bid_Sheet.pdf | ||
| Attachment_10_-_PPQ_Cover_Letter.pdf | ||
| Attachment_4-_BAFBI_33-2.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
This is a Firm Fixed Price Indefinite Delivery Indefinite Quantity (IDIQ) contract for the repair and/or replacement of Barksdale pavements. This contract w ill be for one (1) base year and four (4) option years.
This requirement is being set aside for Small Businesses in accordance w ith FAR 19.5.
In accordance w ith FAR 236.204(i) Magnitude of Construction Projects, the price range of this project is anticipated to be betw een $10,000,000 and $25,000,000. MINIMUM GUARANTEE FOR THIS CONTRACT IS $2,000.00. MAXIMUM CONTRACT VALUE WILL NOT EXCEED $12,000,000.00.
SITE VISIT: A site visit w ill be held on 7 January 2015 at 10:00 am at the 2d Contracting Squadron, 41 Vandenberg Ave, Barksdale AFB, LA.
Please contact SSgt Jeff Hairston at (318) 456-6943 or Marla Poirier at (318) 456-6833 to confirm attendance and number of personnel attending. For contractors w ithout base access, please report to the East Gate (Industrial Drive/Contractor’s gate) on the day of the site visit by 9:30 am to be signed on. Contractor’s must have a valid picture ID. Anyone driving a vehicle on base must provide driver’s license and proof of insurance.
JEFFERY D HAIRSTON 318-456-4489
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
22-Dec-2014
(RFP)
(IFB)
X
CALL:
Base Pavements
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______15 calendar days and complete it w ithin ________365 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________30 Jan 2015 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
2 CONS/LGC - FA4608
41 VANDENBERG AVE
BARKSDALE AFB LA 71110-2079
FA4608
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
01:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
AWUB 13-9005
8. ADDRESS OFFER TO (If Other Than Item 7)
318-456-3294FAX:TEL: 318-456-2113 TEL: FAX:
FA4608-15-R-0004 61
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
FA4608-15-R-0004
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Base Year - Barksdale Pavements
FFP
AWUB 13-9005: The contractor shall supply all materials, tools, labor, equipment, transportation, supervision, administration, and quality control necessary to perform repair and/or replacement of various types of pavements and pavement related work as described in the Statement of Work, "Pavements Indefinite Delivery and Indefinite Quantity Contract", contained in Section C. The base period shall be one year (365 days) from 1 June 2015 to 31 May 2016.
FOB: Destination NSN: Z2LB-15-Rpr-Pave
SIGNAL CODE: A
NET AMT
OPTION Option Year 1 - Barksdale Pavements
FFP
AWUB 13-9005: The contractor shall supply all materials, tools, labor, equipment, transportation, supervision, administration, and quality control necessary to perform repair and/or replacement of various types of pavements and pavement related work as described in the Statement of Work, "Pavements Indefinite Delivery and Indefinite Quantity Contract", contained in Section C. The option year 1 period shall be one year (365 days) from 1 June 2016 to 31 May 2017.
FOB: Destination
OPTION Option Year 2 - Barksdale Pavements
FFP
AWUB 13-9005: The contractor shall supply all materials, tools, labor, equipment, transportation, supervision, administration, and quality control necessary to perform repair and/or replacement of various types of pavements and pavement related work as described in the Statement of Work, "Pavements Indefinite Delivery and Indefinite Quantity Contract", contained in Section C. The option year 2 period shall be one year (365 days) from 1 June 2017 to 31 May 2018.
FOB: Destination
OPTION Option Year 3 - Barksdale Pavements
FFP
AWUB 13-9005: The contractor shall supply all materials, tools, labor, equipment, transportation, supervision, administration, and quality control necessary to perform repair and/or replacement of various types of pavements and pavement related work as described in the Statement of Work, "Pavements Indefinite Delivery and Indefinite Quantity Contract", contained in Section C. The option year 3 period shall be one year (365 days) from 1 June 2018 to 31 May 2019.
FOB: Destination
OPTION Option Year 4 - Barksdale Pavements
FFP
AWUB 13-9005: The contractor shall supply all materials, tools, labor, equipment, transportation, supervision, administration, and quality control necessary to perform repair and/or replacement of various types of pavements and pavement related work as described in the Statement of Work, "Pavements Indefinite Delivery and Indefinite Quantity Contract", contained in Section C. The option year 4 period shall be one year (365 days) from 1 June 2019 to 31 May 2020.
FOB: Destination
CONTRACT/CLIN MINIMUM AND MAX
CONTRACT MINIMUM/MAXIMUM QUANTITY AND CONTRACT VALUE
The minimum quantity and contract value for all orders issued against this contract shall not be less than the minimum quantity and contract value stated in the following table. The maximum quantity and contract value for all orders issued against this contract shall not exceed the maximum quantity and contract value stated in the following table.
MINIMUM
QUANTITY
MINIMUM
AMOUNT
MAXIMUM
QUANTITY
MAXIMUM
AMOUNT
1.00 $2,000.00 250.00 $12,000,000.00
DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND ORDER VALUE
The minimum quantity and order value for each Delivery/Task Order issued shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for each Delivery/Task Order issued shall not exceed the maximum quantity and order value stated in the following table.
MINIMUM
QUANTITY
MINIMUM
AMOUNT
MAXIMUM
QUANTITY
MAXIMUM
1.00 $2,000.00 250.00 $750,000.00
CLIN MINIMUM/MAXIMUM QUANTITY AND CLIN VALUE
The minimum quantity(s) and CLIN value(s) for all orders issued against the CLIN(s) on this contract shall not be less than the minimum quantity(s) and CLIN value(s) stated in the following table. The maximum quantity(s) and CLIN value(s) for all orders issued against the CLIN(s) on this contract shall not exceed the maximum quantity(s) and CLIN value(s) stated in the following table.
CLIN
MINIMUM
QUANTITY
MINIMUM
AMOUNT
MAXIMUM
QUANTITY
MAXIMUM
AMOUNT
0001 1.00 $2,000.00 50.00 $2,400,000.00 1001 1.00 $2,000.00 50.00 $2,400,000.00 2001 1.00 $2,000.00 50.00 $2,400,000.00 3001 1.00 $2,000.00 50.00 $2,400,000.00 4001 1.00 $2,000.00 50.00 $2,400,000.00
CLIN DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND CLIN ORDER VALUE
The minimum quantity and order value for all Delivery/Task Orders issued for this CLIN shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for the all Delivery/Task Orders issued for this CLIN shall not exceed the maximum quantity and order value stated in the following table.
CLIN
MINIMUM
QUANTITY
MINIMUM
AMOUNT
MAXIMUM
QUANTITY
MAXIMUM
0001 1.00
$2,000.00
100.00
$750,000.00
1001 1.00
2001 1.00
3001 1.00
4001 1.00
Section C - Descriptions and Specifications
STATEMENT OF WORK
STATEMENT OF WORK
1. Specifications:
1.1. All work performed under AWUB 13-9005 shall comply with The 2006 Louisiana Department of
Transportation and Development Specifications regulations pertaining to the design and construction of roadways, driveways, sidewalks, parking lots, drainage and other associated structures and/or tasks.
1.1.1. Additionally, the contractor shall follow all applicable UFCs and the Barksdale AFB Design Guide.
2. Location of Work:
2.1. The work is located on Barksdale Air Force Base, Louisiana. Barksdale AFB is located in Bossier Parrish, LA, four (4) miles east of Shreveport, LA and just South of Interstate 20.
2.2. The work shall be performed on Barksdale AFB roads, parking lots, driveways, sidewalks, and related structures. The limits of construction is everything outside the physical boundaries of the airfield, nothing within the confines of the housing area and stops where the hot mix asphalt ends on the Flag Lake Dam road and the gravel portion begins.
2.3. Working hours for the contractor will normally be between the hours of 7:30 a.m. and 6 p.m. excluding Saturdays, Sundays and Federal Holidays (New Year’s Day, Birthday of Martin Luther King, Jr., Presidents Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving Day and Christmas Day). If the contractor desires to work during periods other than above, additional Government inspection forces may be required. The contractor must notify the contracting officer three days in advance of his/her intention to work during other periods to allow assignment of additional inspection forces when the contracting officer determines they are reasonably available. If such force is reasonably available, the contracting officer may authorize the contractor to perform work during periods other than normal duty hours/days, however, if inspections are required to perform in excess of their normal duty hours/days solely for the benefit of the contractor, the actual cost of inspection at overtime rates will be charged to the contractor. These adjustments to the contract price may be made periodically as directed by the contracting officer.
3. Scope of Work:
3.1. This project will consist of the maintenance and repair of base pavements. This may require the complete rebuilding of certain streets, parking lots, and driveways as well as the installation/repair of jogging trails, bike trails, cart paths, drainage pipes and sidewalks. This may include the removal of existing concrete, asphalt, and base materials and replacement with new. Other work will include pavement marking, excavation, backfill, concrete curb, gutter, drainage, structures, seeding/sod, surveying and staking. Pavements in base housing areas are not a part of this work. The period of performance is one base year (365 days) and four option years (365 days each).
3.2. The Contractor shall maintain overall cleanliness of the site at the end of each work day. This daily cleanup will not relieve the Contractor from responsibility of the final cleanup before acceptance of all work. After completion of all activities, the Contractor shall be required to clean the area being worked on by removing all dirt, trash, and debris resulting from their work and shall restore the area to its original state of cleanliness. All areas of disturbed grass shall be repaired at the contractor’s expense if not a part of the individual delivery order.
3.3. Debris will not be dumped on Government property unless a Non-Government owned dumpster is used. The Contractor shall dispose of all t r a s h / debris at an off base site. Federal, State and Local laws and regulations regarding hauling and disposal shall apply.
3.4. Adequate and proficient supervision shall be provided by the Contractor throughout all phases of the work.
3.5. Work performed under this contract will be accomplished on both well-traveled and semi traveled streets and major roads.
3.6. The Contractor is responsible for verifying all measurements, quantities, and specific requirements at an on-site visit. If requested, the Government and the contractor can measure and figure up quantities and discuss the scope of work together, provided a contracting representative is present.
3.7. This scope of work includes but is not limited to: placing of concrete, asphalt milling, leveling, grading, compaction, applying tact as required, apply and install new base course, (asphalt grades include but are not limited to I2, I4, and I5), provide and install new asphalt surface course, seal cracks, remove and dispose of existing base pavement, (depth of milling, paving, concrete and placement of sub-surface shall be identified by individual task order), maintenance, repair, and installation of new:
concrete work, excavation, grading, aggregate, drainage piping, culverts, provide and install new manhole extension rings, provide and install new catch basin extension frames, valve curb boxes and bicycle safe drain grate with frame, new pavement striping, remove and dispose of existing topsoil, vegetation, and tree removal incidental to paving and concrete; proof rolling prior to asphalt base course to detect soft spots, perform vertical concrete form work from sub-grade to a maximum height of twenty feet, small call area to perform new or replacement work, provide survey and layout services, laser and optical, and mechanical grade control.
4. Concrete Crushing:
4.1. The contractor shall make a rock crusher available with the capability of recycling by crushing, base-owned concrete that has been removed from the pavements on base to an aggregate size of 1-1/2 inches or less. The material shall be crushed to LA DOTD standards, Section 1003.01, to be used as a class I or II base course.
4.2. Recycled Portland Cement Concrete (PCC): Will follow the gradation of the 2006 Std. Specs under section 1003.03 (c).
4.3. Bidder shall not charge any related crushing expenses to BAFB. As a part of the bid submittal, Bidder shall provide the percent of the total recycled concrete that will be provided to the Base and bidder shall take ownership of the remaining percentage of recycled concrete to be utilized as Bidder sees fit. The percent of recycled concrete that will be crushed and provided to the Base shall be delivered to a stockpile location on Base to be designated by Project Engineer. Bidder will be provided an area on Base designated by the Base Civil Engineer to set up the crusher and bidder-owned stockpile for recycled concrete.
4.4. Within 60 days, or as mutually agreed upon by the Parties, after expiration of the current Pavements IDIQ contract, bidder shall remove or dispose of all existing recycled concrete owned by Bidder, and in addition, bidder shall aerate and provide topsoil in the area(s) where the bidder owned recycled concrete stockpile and crusher were located.
5. Contractor Lay-down Area:
5.1. The Government shall provide the contractor with an area on base to operate and maintain an office/management trailer, concrete crusher, and equipment. The site shall be maintained and present a neat and orderly appearance at all times.
6. Traffic Management:
6.1. Prior to beginning any work on Barksdale AFB, the contractor shall provide the Government with an initial traffic management plan for approval by base personnel. Traffic management plans must be submitted no later than 14 days before the start of a project.
7. Utilities:
7.1. All reasonable required amounts of water and electricity will be made available to the Contractor by the
Government from Government-owned and operated water and electrical systems without cost to the Contractor. All temporary lines will be furnished, installed, connected and maintained by the Contractor in a workmanlike manner satisfactory to the Contracting Officer or his/her representative and shall be removed by the Contractor at his/her expense prior to final acceptance of the construction.
8. Dig Permits/Utility Outages:
8.1. Prior to beginning any work on Barksdale AFB, the contractor shall submit digging permits, where applicable, and utility outage requests to the 2nd Civil Engineer Customer Support Section 14 days before the start of construction. Work may not begin until the submitted forms have been approved.
9. Safety Requirements:
9.1. General Safety: The Contractor is responsible for the erection and maintenance of all safety barricades, shoring, fences, and other devices necessary for safe conditions to protect the work, equipment, workmen, public and others IAW OSHA Law. The Contractor shall erect or construct such devices as conditions may require and shall maintain them to provide safe conditions through the construction period and conform to OSHA Regulations and the EM 385-1-1 Safety and Health Requirements.
9.2. Fire Protection Requirements: The Contractor shall comply with Air Force and local fire regulations and
NFPA requirements. The Contractor shall provide fire extinguishers rated and approved by the National Fire Protection Association, of sufficient size, type, and quantity to cope with all known hazards, at the construction site during the execution of this contract.
10. Work Delay For Government:
10.1. The Contractor may be requested to stop work for up to 20 days with five (5) days to be consecutive.
The anticipated time frame for this work delay is unknown at this point in time.
11. Notice Of Final Inspection:
11.1. The Contractor shall give the Contracting Officer or his/her representative five working days advance notice of the date the work will be ready for final inspection.
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government 1001 Destination Government Destination Government 2001 Destination Government Destination Government 3001 Destination Government Destination Government 4001 Destination Government Destination Government
CLAUSES INCORPORATED BY REFERENCE
52.246-12 Inspection of Construction AUG 1996
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
0001 POP 01-JUN-2015 TO
31-MAY-2016
N/A 2 MSG/CES/CERF - F1G3A2
334 DAVIS AVE W
STE 300
BARKSDALE AFB LA 71110
FOB: Destination
F1G3A2
1001 POP 01-JUN-2016 TO
31-MAY-2017
N/A (SAME AS PREVIOUS LOCATION)
2001 POP 01-JUN-2017 TO
31-MAY-2018
N/A (SAME AS PREVIOUS LOCATION)
3001 POP 01-JUN-2018 TO
31-MAY-2019
N/A (SAME AS PREVIOUS LOCATION)
4001 POP 01-JUN-2019 TO
31-MAY-2020
N/A (SAME AS PREVIOUS LOCATION)
PERFORMANCE INFORMATION
F-800 NOTICE TO PROCEED
NOTICE TO PROCEED will be issued within 30 calendar days after award of each delivery order. Award date shall be established as the date of mailing or otherwise furnishing a properly executed award document to the successful offeror.
F-801 WORK SCHEDULE
Working hours for the contractor will normally be between the hours of 7:30 a.m. and 6 p.m. excluding Saturdays, Sundays and Federal Holidays (New Year’s Day, Birthday of Martin Luther King, Jr., Presidents Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving Day and Christmas Day). If the contractor desires to work during periods other than above, additional government inspection forces may be required. The contractor must notify the contracting officer three days in advance of his/her intention to work during other periods to allow assignment of additional inspection forces when the contracting officer determines they are reasonably available. If such force is reasonably available, the contracting officer may authorize the contractor to perform work during periods other than normal duty hours/days, however, if inspections are required to perform in excess of their normal duty hours/days solely for the benefit of the contractor, the actual cost of inspection at overtime rates will be charged to the contractor. These adjustments to the contract price may be made periodically as directed by the contracting officer.
F-802 DELIVERY TIME
The period of performance for each project will be decided prior to issuance of each delivery order.
Section G - Contract Administration Data
ADMINISTRATIVE DATA
ADMINISTRATIVE DATA
(a) Following award, this contract will be administered by the 2d Contracting Squadron. The name, address, telephone number, and fax number of the Contracting Officer and Administrator are as follows:
CO: Marla J. Poirier 41 Vandenberg Ave Barksdale AFB LA 71110-2079 Phone: 318-456-6833 Fax: 318-456-3294 E-mail: marla.poirier@us.af.mil
Admin: SSgt Jeffery Hairston Phone: 318-456-6943 Fax: 318-456-3294 E-mail: jeffery.hairston@us.af.mil
(b) The Contracting Officer (CO), is the only person authorized to approve changes or modify any of the requirements under this contract and notwithstanding any provisions contained elsewhere in this contract, the said authority remains solely in the CO. In the event the Contractor effects any such change at the direction of any person other than the CO, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in costs incurred as a result thereof.
CLAUSES INCORPORATED BY FULL TEXT
252.232-7003 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS AND RECEIVING REPORTS
(JUNE 2012)
(a) Definitions. As used in this clause–
(1) Contract financing payment and invoice payment have the meanings given in section 32.001 of the Federal Acquisition Regulation.
(2) Electronic form means any automated system that transmits information electronically from the initiating system to all affected systems. Facsimile, e-mail, and scanned documents are not acceptable electronic forms for submission of payment requests. However, scanned documents are acceptable when they are part of a submission of a payment request made using Wide Area WorkFlow (WAWF) or another electronic form authorized by the Contracting Officer.
(3) Payment request means any request for contract financing payment or invoice payment submitted by the Contractor under this contract.
(4) Receiving report means the data required by the clause at 252.246-7000, Material Inspection and Receiving Report.
(b) Except as provided in paragraph (c) of this clause, the Contractor shall submit payment requests and receiving reports using WAWF, in one of the following electronic formats that WAWF accepts: Electronic Data Interchange, Secure File Transfer Protocol, or World Wide Web input. Information regarding WAWF is available on the Internet at https://wawf.eb.mil/.
(c) The Contractor may submit a payment request and receiving report using other than WAWF only when–
(1) The Contracting Officer administering the contract for payment has determined, in writing, that electronic submission would be unduly burdensome to the Contractor. In such cases, the Contractor shall include a copy of the Contracting Officer's determination with each request for payment;
(2) DoD makes payment for commercial transportation services provided under a Government rate tender or a contract for transportation services using a DoD-approved electronic third party payment system or other exempted vendor payment/invoicing system (e.g., PowerTrack, Transportation Financial Management System, and Cargo and Billing System);
(3) DoD makes payment for rendered health care services using the TRICARE Encounter Data System (TEDS) as the electronic format; or
(4) When the Governmentwide commercial purchase card is used as the method of payment, only submission of the receiving report in electronic form is required.
(d) The Contractor shall submit any non-electronic payment requests using the method or methods specified in Section G of the contract.
(e) In addition to the requirements of this clause, the Contractor shall meet the requirements of the appropriate payment clauses in this contract when submitting payments requests.
(End of clause)
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (MAY 2013)
(a) Definitions. As used in this clause--
Department of Defense Activity Address Code (DoDAAC) is a six position code that uniquely identifies a unit, activity, or organization.
Document type means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
Local processing office (LPO) is the office responsible for payment certification when payment certification is done external to the entitlement system.
(b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall--
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this Web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via Web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:
(1) Document type. The Contractor shall use the following document type(s).
Construction Invoice
(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer.
Not Applicable
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table* Field Name in WAWF Data to be entered in WAWF Pay Official DoDAAC F87700 Issue By DoDAAC FA4608 Admin DoDAAC FA4608 Inspect By DoDAAC F1G3A2 Ship To Code Not Applicable Ship From Code Not Applicable Mark For Code Not Applicable Service Approver (DoDAAC) F1G3A2 Service Acceptor (DoDAAC) F1G3A2 Accept at Other DoDAAC Not Applicable LPO DoDAAC Not Applicable DCAA Auditor DoDAAC Not Applicable Other DoDAAC(s) Not Applicable
(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request.
(5) WAWF email notifications. The Contractor shall enter the email address identified below in the “Send Additional Email Notifications” field of WAWF once a document is submitted in the system.
Jeffery.hairston@us.af.mil
Marla.poirier@us.af.mil
(g) WAWF point of contact. (1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.
Not Applicable
(2) For technical WAWF help, contact the WAWF helpdesk at 866-618-5988.
Section H - Special Contract Requirements
SPECIAL CONTRACT REQUIREMENTS
H-001 REQUIRED INSURANCE
(IAW FAR 28.306(b) and FAR 52.228-5)
Reference FAR clause entitled "Insurance..." the Contractor shall, at its own expense, procure and thereafter maintain the following kinds of insurance with respect to performance under the contract.
a. Workmen’s Compensation and Employers Liability Insurance as required by law except that if this contract is to be performed in a State which does not require or permit private insurance, then compliance with the statutory or administrative requirements in any such State will be satisfactory. The required Workmen's Compensation insurance shall extend to cover employer's liability for accidental bodily injury or death and for occupational disease with a minimum liability limit of $100,000.
b. General Liability Insurance. Bodily injury liability insurance, in the minimum limits of $500,000 per occurrence shall be required on the comprehensive form of policy.
c. Automobile Liability Insurance. This insurance shall be required on the comprehensive form of policy and shall provide bodily injury liability and property damage liability covering the operation of all automobiles used in connection with the performance of the contract. At least the minimum limits of $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage shall be required.
H-002 BONDS
a. Bid Guarantee – Not required
b. Performance and Payment Bonds. In accordance with the Miller Act (40 U.S.C. 3131), the bidder to whom the award is made shall within fifteen (15) calendar days after the award of the contract furnish a Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25A), each with good and sufficient surety or sureties acceptable to the Government. (Not required for contracts of $30,000.00 or less).
Contracts exceeding the $150,000 (Miller Act):
(1) Performance bonds. Unless the contracting officer determines that a lesser amount is adequate for the protection of the Government, the penal amount of performance bonds must equal--
(i) 100 percent of the original contract price; and
(ii) If the contract price increases, an additional amount equal to 100 percent of the increase.
(2) Payment Bonds.
(i) Unless the contracting officer makes a written determination supported by specific findings that a payment bond in this amount is impractical, the amount of the payment bond must equal to:
(A) 100 percent of the original contract price; and
(B) If the contract price increases, and additional amount equal to 100 percent of the increase.
(ii) The amount of the payment bond must be no less than the amount of the performance bond.
c. The contractor will not be allowed to start work prior to furnishing the required bonds, including any necessary reinsurance agreements.
H-003 PROGRESS SCHEDULES AND REPORTS
a. In accordance with FAR 52.236-15, the reports contemplated by the clause titled "Schedules for Construction Contracts" shall be accomplished on and in accordance with instruction pertaining to AF Form
3064, Contract Progress Schedule, and AF Form 3065, Contract Progress Report. Mobilization/demobilization will not be allowed as a line item on the Progress Schedule. Costs for those items must be included in other elements of work.
b. Upon award of the contract and as required, the contractor will be furnished (3) copies of the AF Form 3064, Contract Progress Schedule. The Progress Schedule must be approved by the Government prior to start of physical work on the project job site.
H-004 PREPARATION OF MATERIAL APPROVAL SUBMITTALS
In accordance with FAR 52.236-5, the submittals contemplated by the clause herein entitled "Material and Workmanship" shall be accomplished on and in accordance with instructions pertaining to AF Form 3000, Material Approval Submittal.
H-005 INTERRUPTION OF UTILITY SERVICES
The Government may not be held responsible for interruptions of utility service and will not be liable for contractor delays, damages, or increased costs occasioned by any such interruption of service.
H-006 SUPERINTENDENCE OF CONTRACT
In accordance with FAR 52.236-6, at all times during performance of this contract and until work is completed and accepted, the contractor shall provide a superintendent who will be on the job site at all times when work is being performed. The superintendent will be responsible for ALL employees (including subcontractors) and have the authority to plan work and direct ALL employees. The superintendent will be appointed in writing and this letter submitted to the Contracting Officer, setting forth the authority delegated to the superintendent.
H-007 CONTRACT COMPLETION INSPECTIONS
The contractor will schedule (preferably with 3 working days notice) a pre-completion inspection to be held approximately 10 calendar days prior to the expiration of the contract. This inspection may result in a "punchlist" indicating items to be furnished or work to be completed by the contractor or subcontractors in order to complete the work specified in the contract documents. This list may not be construed to be all inclusive. A copy of the list will be furnished to the contractor within 2 workdays for his use in completing the contractual work. If the pre-completion inspection results in no "punchlist" and the work is complete, this inspection may be considered the "final" inspection as determined by the Contracting Officer. If required, the contractor will be responsible for scheduling the contract completion inspection (preferably with 3 working days notice) to be held no later than the final day of contract performance. Should this inspection result in a "punchlist", the contractor will have 10 calendar days (after receipt of punchlist) to complete all punchlist items and notify the Contracting Officer of this. NO FINAL INVOICE SHALL BE PAID UNTIL ALL
PUNCHLIST ITEMS ARE COMPLETED TO THE SATISFACTION OF THE CONTRACTING OFFICER.
Should a contractor exceed the time allowed for these corrections, it may result in negative past performance which could affect future contract awards.
H-008 CLASS I OZONE DEPLETING SUBSTANCES/CHEMICALS
If this project has any materials or equipment that contains Class I Ozone depleting substances/chemicals, you are required to contact the Contracting Officer, 318/456-6833, for further instructions prior to providing the product or equipment.
H-009 CONSTRUCTION AND DEMOLITION DEBRIS REPORTS
The following requirement is listed in Attachment 2, Environmental Requirements for Contractors Working on Barksdale Air Force Base. These reports are required to be submitted on an AF 3000 Material Submittal and should be incorporated into the AF66 Material Submittal Schedule at time of contract award. Final payment will not be released until C&D reports have been submitted and accepted by the Government.
“Construction and Demolition (C&D) debris is generated as a result of construction, renovation, or demolition activities. Although C&D debris is usually considered a single waste stream, the composition actually varies with each activity and the type, size, and location of the structures involved. Disposing of C&D debris in landfills consumes enormous amounts of space and is both economically and environmentally costly. In accordance with AFI 32-7042 and BAFB’s Integrated Solid Waste Management Plan (ISWMP), ALL WEIGHTS OF C&D MATERIALS RECYCLED AND DISPOSED MUST BE REPORTED TO THE
RECYCLE PROGRAM MANAGER.”
H-010 ENVIRONMENTAL MANAGEMENT SYSTEM (EMS) AWARENESS TRAINING
The contractor is required to complete EMS Awareness Training in accordance with Attachment 2, Environmental Requirements for Contractors Working on Barksdale Air Force Base. The training will be provided in the form of a power point presentation provided by the Contracting Office. The contractor must submit the Certificate of Completion to the Contracting Officer prior to receiving the Notice to Proceed for this contract.
BOSSIER CITY -- PARISH SALES AND USE TAX
Bossier City and Bossier Parish levy a use tax defined by state and local sales tax law. As such, these sales are taxable at the point of delivery to the "contractor" (consumer). If the sales or use tax is not collected by the vendor, tax is payable directly to the jurisdiction in which delivery is made. Contractors and subcontractors are each individually liable for sales and use tax on the basis of their individual purchase transactions. This tax may extend to equipment leased or rented to the Government. It may also extend to supplies and equipment purchased elsewhere, but brought into Bossier Parish for final use. All contractors are cautioned to assure themselves of any liability for this tax. The local telephone number for questions concerning this tax is A/C 318 741-8551.
CONTRACTOR/VENDOR ACCESS TO BARKSDALE AFB
All commercial vehicles are required to enter Barksdale AFB through the East Gate, just off I-20 and Industrial Drive. This includes construction, food, supply, FedEX, and UPS deliveries, as well as contractors entering with company trucks. Contractors entering in their privately owned vehicles with an approved pass will be allowed entry at any gate. Hours of operation for the East Gate are 0500-2200 Monday through Friday, Saturday 0600-1200.
Background Checks for Contractor Personnel Requiring Entry/Access to Barksdale AFB (Jan 2005)
Security Forces will conduct a National Crime and Information Center (NCIC) background check on all contractor or subcontractor personnel prior to granting access to the installation.
(End of Clause)
CELL PHONE POLICY
The use of cell phones while operating a moving vehicle on Barksdale AFB is prohibited, unless the phone is operated in a “hands free” mode. “Use of cell phones” includes placing calls, retrieving stored information from the phone, programming the phone, talking on the phone, and receiving calls, regardless of the source. Violators may be issued a citation and assessed 3 points on their base driving record. Additional points may be assessed if cell phone use is found to be a contributing factor in a motor vehicle accident.
Lay-down Area Temporary Fencing
1. The Contractor shall furnish all labor, materials, and equipment necessary to provide secure and visually aesthetic temporary fencing for surrounding project equipment and material in lay-down areas.
Work shall include:
a. Clearing area of all encumbrances to safe erection of fencing.
b. Provide fence that is: metal tube frame; metal woven wire mesh (minimum 11 gauge); minimum 6 feet in height.
c. Provide integral to fence visual blocking material, either slat weave or sheet goods.
d. Erecting fence in such manner as to prevent loss of fencing or blocking due to inclement weather.
e. At no time shall fence interfere with fire egress paths or fire equipment ingress, to include periods when gates are in operation.
Contractor shall submit cut sheets on all items for installation, prior to procurement, for approval by the C.E.
Architect. Complete the design as indicated on drawings in accordance with UFC 1-200-01 General Building Requirements which includes the latest editions of the International Building Code and NFPA Life Safety Code, and Americans with Disabilities Act. All required work shall be accomplished in accordance with the Barksdale AFB Design Compatibility Guidelines (DCG). All colors and materials shall be selected by the Civil Engineer Architect in accordance with the DCG. Construction shall be conducted in a quality workmanlike manner. Contractor shall take any steps necessary to protect government and occupant property from damage caused by weather or other occurrence while work is in progress.
2. Upon notification of completion by the contractor a determination will be made as to the satisfactory completion and acceptance of the contract specification(s). Any segment of the operation that is not acceptable because of an unsightly or unprofessional appearance will be justification for rejection of the treatment. The contractor will incur all costs, both labor and materials, for reaccomplishment of any unacceptable work identified.
3. The contractor will be responsible for and incur any and all labor and material costs required to repair any damages to government facilities that occurred during and as result of repair work, replacement operations, or new work, under this contract. This damage will be identified as separate from the condition of the facilities as identified during the initial inspection. The damage will be identified, but not limited, to the following items.
a. Government gas, water and electric transmission and distribution systems
b. Occupant personal property
Additional Information.
a. The contractor will begin work not earlier than 7:30 am each workday. Work will not be performed later than 6:00 pm.
b. Inspections will be conducted by the Contracting Officer and /or Contracting Officer’s Representative and the Contractor’s Manager.
c. Any discrepancies should be noted and forwarded to the Architect.
Section I - Contract Clauses
52.202-1 Definitions NOV 2013 52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees APR 1984 52.203-6 Restrictions On Subcontractor Sales To The Government SEP 2006 52.203-7 Anti-Kickback Procedures OCT 2010 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity
JAN 1997
52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity JAN 1997 52.203-12 Limitation On Payments To Influence Certain Federal
Transactions
OCT 2010
52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights
SEP 2013
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper
MAY 2011
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards
JUL 2013
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment
AUG 2013
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
MAY 2012
52.215-2 Audit and Records--Negotiation OCT 2010 52.215-8 Order of Precedence--Uniform Contract Format OCT 1997 52.219-8 Utilization of Small Business Concerns JUL 2013 52.222-1 Notice To The Government Of Labor Disputes FEB 1997 52.222-3 Convict Labor JUN 2003 52.222-4 Contract Work Hours and Safety Standards Act - Overtime
Compensation
JUL 2005
52.222-6 Davis Bacon Act JUL 2005 52.222-7 Withholding of Funds FEB 1988 52.222-8 Payrolls and Basic Records JUN 2010 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) JUL 2005 52.222-12 Contract Termination-Debarment FEB 1988 52.222-13 Compliance with Davis-Bacon and Related Act Regulations. FEB 1988 52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility FEB 1988 52.222-21 Prohibition Of Segregated Facilities FEB 1999 52.222-26 Equal Opportunity MAR 2007 52.222-27 Affirmative Action Compliance Requirements for
Construction
FEB 1999
52.222-35 Equal Opportunity for Veterans SEP 2010 52.222-36 Affirmative Action For Workers With Disabilities OCT 2010 52.222-37 Employment Reports on Veterans SEP 2010 52.222-50 Combating Trafficking in Persons FEB 2009 52.222-54 Employment Eligibility Verification AUG 2013
52.222-99 Notification of Employee Rights under the National Labor Relations Act.
JUN 2010
52.223-3 Hazardous Material Identification And Material Safety Data JAN 1997 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-6 Drug-Free Workplace MAY 2001 52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts
MAY 2008
52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving
AUG 2011
52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.227-1 Authorization and Consent DEC 2007 52.227-2 Notice And Assistance Regarding Patent And Copyright
Infringement
DEC 2007
52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.228-2 Additional Bond Security OCT 1997 52.228-5 Insurance - Work On A Government Installation JAN 1997 52.228-11 Pledges Of Assets JAN 2012 52.228-12 Prospective Subcontractor Requests for Bonds OCT 1995 52.228-14 Irrevocable Letter of Credit DEC 1999 52.228-15 Performance and Payment Bonds--Construction OCT 2010 52.229-3 Federal, State And Local Taxes FEB 2013 52.232-5 Payments under Fixed-Price Construction Contracts SEP 2002 52.232-17 Interest OCT 2010 52.232-18 Availability Of Funds APR 1984 52.232-23 Assignment Of Claims JAN 1986 52.232-27 Prompt Payment for Construction Contracts JUL 2013 52.232-33 Payment by Electronic Funds Transfer--System for Award
Management
JUL 2013
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business
Subcontractors
DEC 2013
52.233-1 Disputes JUL 2002 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Accident Prevention NOV 1991 52.236-14 Availability and Use of Utility Services APR 1984 52.236-15 Schedules for Construction Contracts APR 1984 52.236-17 Layout of Work APR 1984 52.236-21 Specifications and Drawings for Construction FEB 1997 52.236-26 Preconstruction Conference FEB 1995 52.242-13 Bankruptcy JUL 1995 52.242-14 Suspension of Work APR 1984 52.243-4 Changes JUN 2007
52.244-5 Competition In Subcontracting DEC 1996 52.244-6 Subcontracts for Commercial Items DEC 2013 52.248-3 Value Engineering-Construction OCT 2010 52.249-2 Termination For Convenience Of The Government (Fixed-
Price)
APR 2012
52.249-10 Default (Fixed-Price Construction) APR 1984 52.253-1 Computer Generated Forms JAN 1991 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense- Contract-Related Felonies
DEC 2008
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7005 Representation Relating to Compensation of Former DoD
Officials
NOV 2011
252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Alt A System for Award Management Alternate A MAY 2013 252.209-7004 Subcontracting With Firms That Are Owned or Controlled By
The Government of a Terrorist Country
DEC 2006
252.209-7993 (Dev) Representation by Corporations Regarding an Unpaid Delinquent Tax Liability or a Felony Conviction under any Federal Law -- Fiscal Year 2014 Appropriations (Deviation)
FEB 2014
252.216-7009 Allowability of Legal Costs Incurred in Connection With a Whistleblower Proceeding
SEP 2013
252.223-7006 Prohibition On Storage And Disposal Of Toxic And Hazardous Materials
APR 2012
252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.225-7012 Preference For Certain Domestic Commodities FEB 2013 252.232-7010 Levies on Contract Payments DEC 2006 252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.236-7013 Requirement for Competition Opportunity for American Stell
Producers, Fabricators, and Manufacturers
JU…