Questions-Answers_-_2_June_15.pdf

PDF 180 KB Posted

Attached to
Airfield Paint and Rubber Removal Federal contract opportunity
Solicitation number
FA4600-15-B-0003
Issued by
Department of the Air Force Air Combat Command

View the file

Other files for this federal contract opportunity

Other files attached to Airfield Paint and Rubber Removal, newest first.
File Type Posted
Bid_Abstract.pdf PDF
Airfield_Rubber_Removal_and_Remarking.pdf PDF
15-B-0003-0003.pdf PDF
SGBP_15_0016__Specs_Combined_MAR_15(Revised).pdf PDF
FA4600-15-B-0003-0002.pdf PDF
Questions-Answers_-_2_June_15.docx DOCX document
15-B-0003_(Current_Version).pdf PDF
15-B-0003_(Conformed_Copy).pdf PDF
Questions-Answers-21May15.pdf PDF
SGBP_15-0016_FULL_SET_24X36_ENHANCED.pdf PDF
15-B-003-0001_(Amendment).pdf PDF
SGBP_15_0016__Specs_Combined_MAR_15.pdf PDF
SGBP_15-0016_FULL_SET_24X36.pdf PDF
Wage_Determinations.pdf PDF
FA4600-15-B-0003.pdf PDF
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions/Answers

FA4600-15-B-0003-001

Maintain Airfield Paint and Rubber Removal

ALL Q/A MUST BE SUBMITTED BY 4:00p.m. CST on 2 JUNE 2015

2 June 2015

1. The solicitation states that there is approximately 5000 SF of paint/marking removal, When reviewing sheet 3 of the drawings there appears to be approximate 9000 SF identified for removal. 6000 LF X 1.5 FT wide.

Please clarify.

1. Synopsis should have read "removal of approximately 10,000 SF of paint markings on the runway, taxiways, and parking aprons." IGE reflects the 10,000 sf number.

SYNOPSIS

Offutt AFB Project SGBP 15-0016, Mnt Airfield Painting, Rubber Removal

This project consists of removal of 250,000 SF of rubber deposits on Runway 12/30 and removal of approximately 10,000 SF of paint markings on the runway, taxiways and parking aprons. It also includes repainting taxiway/apron center lines ,and select markings not removed on the airfield.

The runway and all airfield operations will continue with short outages scheduled to allow work. The performance period for this project is 120 days.

2. On sheet 5 of the drawings, note 5 states "Repaint Runway Hold line" is only one hold line to be repainted or should all Hold Lines be repainted?

2. Only one hold line is being removed and repainted.

21 May 2015

ALL Q/A MUST BE SUBMITTED BY 4:00p.m. CST on 2 JUNE 2015

1. The drawings did not include details?

See Notes on all sheets. Details are in ETL 04-2 and AFI 32-1042, which are available on line or a copy can be requested from Engineering Dept.

2. Drawing sheet 4 shows runway markings that seem more pronounced on the 30 end compared to Sheet 5 on the 12 end?

See Note 1 on both sheets 4 and 5.

3. Request clarification that the only markings being repainted are taxiway centerlines?

Negative. See Notes on all sheets.

4. If select runway markings are to be repainted, please provide specific markings that are to be repainted?

See Notes on all sheets.

Please see the attached enhanced drawings on sheet 5.

Please insure you have read the Notes section!