Questions-Answers_-_2_June_15.docx
DOCX document 16 KB Posted
- Attached to
- Airfield Paint and Rubber Removal Federal contract opportunity
- Solicitation number
- FA4600-15-B-0003
About this file
Questions / Answers - (most current)
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid_Abstract.pdf | ||
| Airfield_Rubber_Removal_and_Remarking.pdf | ||
| 15-B-0003-0003.pdf | ||
| SGBP_15_0016__Specs_Combined_MAR_15(Revised).pdf | ||
| FA4600-15-B-0003-0002.pdf | ||
| Questions-Answers_-_2_June_15.pdf | ||
| 15-B-0003_(Current_Version).pdf | ||
| 15-B-003-0001_(Amendment).pdf | ||
| Questions-Answers-21May15.pdf | ||
| SGBP_15-0016_FULL_SET_24X36_ENHANCED.pdf | ||
| 15-B-0003_(Conformed_Copy).pdf | ||
| FA4600-15-B-0003.pdf | ||
| Wage_Determinations.pdf | ||
| SGBP_15_0016__Specs_Combined_MAR_15.pdf | ||
| SGBP_15-0016_FULL_SET_24X36.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions/Answers
FA4600-15-B-0003-001
Maintain Airfield Paint and Rubber Removal ALL Q/A MUST BE SUBMITTED BY 4:00p.m. CST on 2 JUNE 2015 2 June 2015
1. Section 2B, Pavement Markings, Scope sections 1.1 and 1.2 do not conform to the drawings or the Q&A’s.
Please confirm that I interpret the markings on the runway to be repainted are threshold bar to threshold bar consisting of those markings and all markings on the inside of runway to include taxiway lead in lines.
Markings that are excluded are the runway edge lines, shoulder markings and overruns.
1. The statement is correct.
2. The solicitation states that there is approximately 5000 SF of paint/marking removal, When reviewing sheet 3 of the drawings there appears to be approximate 9000 SF identified for removal. 6000 LF X 1.5 FT wide.
Please clarify.
2. Synopsis should have read "removal of approximately 10,000 SF of paint markings on the runway, taxiways, and parking aprons." IGE reflects the 10,000 sf number.
SYNOPSIS
Offutt AFB Project SGBP 15-0016, Mnt Airfield Painting, Rubber Removal
This project consists of removal of 250,000 SF of rubber deposits on Runway 12/30 and removal of approximately 10,000 SF of paint markings on the runway, taxiways and parking aprons. It also includes repainting taxiway/apron center lines ,and select markings not removed on the airfield.
The runway and all airfield operations will continue with short outages scheduled to allow work. The performance period for this project is 120 days.
3. On sheet 5 of the drawings, note 5 states "Repaint Runway Hold line" is only one hold line to be repainted or should all Hold Lines be repainted?
3. Only one hold line is being removed and repainted.
21 May 2015 ALL Q/A MUST BE SUBMITTED BY 4:00p.m. CST on 2 JUNE 2015
1. The drawings did not include details?
See Notes on all sheets. Details are in ETL 04-2 and AFI 32-1042, which are available on line or a copy can be requested from Engineering Dept.
1. Drawing sheet 4 shows runway markings that seem more pronounced on the 30 end compared to Sheet 5 on the 12 end?
See Note 1 on both sheets 4 and 5.
1. Request clarification that the only markings being repainted are taxiway centerlines?
Negative. See Notes on all sheets.
1. If select runway markings are to be repainted, please provide specific markings that are to be repainted?
See Notes on all sheets.
Please see the attached enhanced drawings on sheet 5.
Please insure you have read the Notes section!