FA4600-15-B-0003.pdf
PDF 777 KB Posted
- Attached to
- Airfield Paint and Rubber Removal Federal contract opportunity
- Solicitation number
- FA4600-15-B-0003
About this file
Solicitation FA4600-15-B-0003
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid_Abstract.pdf | ||
| Airfield_Rubber_Removal_and_Remarking.pdf | ||
| 15-B-0003-0003.pdf | ||
| SGBP_15_0016__Specs_Combined_MAR_15(Revised).pdf | ||
| Questions-Answers_-_2_June_15.docx | DOCX document | |
| FA4600-15-B-0003-0002.pdf | ||
| Questions-Answers_-_2_June_15.pdf | ||
| 15-B-0003_(Current_Version).pdf | ||
| 15-B-003-0001_(Amendment).pdf | ||
| Questions-Answers-21May15.pdf | ||
| SGBP_15-0016_FULL_SET_24X36_ENHANCED.pdf | ||
| 15-B-0003_(Conformed_Copy).pdf | ||
| Wage_Determinations.pdf | ||
| SGBP_15_0016__Specs_Combined_MAR_15.pdf | ||
| SGBP_15-0016_FULL_SET_24X36.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
F3H3G25064AW01
Please see the attached continuation page on Page 4.
X
DANIEL P. HINSLEY 402-294-2883
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
15-May-2015
(RFP)
(IFB)
CALL:
Mnt. Airf ield Paint, Rubber Removal
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________120 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________FAR 52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________15 Jun 2015 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
55 CONTRACTING SQ
101 WASHINGTON SQ BLDG 40
OFFUTT AFB NE 68113-2107
FA4600
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
10:00 AM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
SGBP 15-0016
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: 402-232-6356 TEL: FAX:
FA4600-15-B-0003 41
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued)
(Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
FA4600-15-B-0003
Section A - Solicitation/Contract Form
CONTINUATION PAGE
Maintenance of Airfield Paint and Rubber Removal-Project SGBP 15-0016.
This project consists of removal of 250,000 SF of rubber deposits on Runway 12/30 and removal of approximately
5,000 SF of paint markings on the runway, taxiways and parking aprons. It also includes repainting taxiway/apron center lines ,and select markings not removed on the airfield. The runway and all airfield operations will continue with short outages scheduled to allow work. The performance period for this project is 120 days which includes 45 days for Airfield/Construction waivers and 5 days for mission delays.
Funds are not presently available. NO AWARD WILL BE MADE UNDER THIS SOLICITATION UNTIL
FUNDS ARE AVAILABLE. THE GOVERNMENT RESERVES THE RIGHT TO CANCEL THIS
SOLICITATION AT ANY TIME. IN THE EVENT THE GOVERNMENT CANCELS THIS SOLICITATION,
THE GOVERNMENT HAS NO OBLIGATION TO REIMBURSE THE OFFEROR FOR ANY COSTS.
Project Magnitude: Between $50,000.00 and $150,000.00. NAICS: 237310 - Size Standard of $36.5 Million.
This acquisition is set aside for competitive 100% Small Businesses. One award based on lowest total contract price will be issued. Important: See Clause 52.236-27 for site visit information (Section L). A Bid Bond of 20% will be required with the bid, see clause 52.228-1. Bids are due no later than 2:00 PM CDT on 15 May 2015. The bid amount shall be entered as a lump sum amount in Section B of the solicitation. Bids must be hand delivered or mailed to:
55 CONS/LGCA
Attn: SSgt Daniel Hinsley
101 Washington Sq. Rm. 200
Offutt AFB, NE 68113-2107
All questions must be provided in writing to SSgt Daniel Hinsley by sending an electronic message to daniel.hinsley@us.af.mil no later than 4:00 PM CDT on 28 May 2015. The secondary POC, SSgt Lucas Thomas, can be reached at lucas.thomas1@us.af.mil. PLEASE NOTE: Access to the base is restricted. SEE CLAUSE
52.236-27 FOR SITE VISIT REQUIRED INFORMATION. Registration at “System for Award Management” located at www.SAM.gov is required.
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions
Affecting the Work, will be included in any contract awarded as a result of this solicitation.
Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for :
1 June 2015
(c) Participants will meet at:
Bellevue Welcome Center
2600 Arboretum Drive
Bellevue NE, 68005
(d) All participants are required to meet and sign in.
(e) Photographs are not authorized to be taken by participants. The Government will provide camera and assign a representative to take photographs at the request of participants. All photographs taken will be provided at www.fbo.gov.
(f) Any person wanting to attend this site visit SHALL RSVP with SSgt Hinsley by 4:00 p.m. CST on 27
May 2015 by email to daniel.hinsley@us.af.mil. Any person who fails to RSVP will be excluded from the site visit. If there are any questions contact SSgt Hinsley by the same means listed above.
mailto:daniel.hinsley@us.af.mil mailto:lucas.thomas1@us.af.mil http://www.sam.gov/ http://www.fbo.gov/ mailto:daniel.hinsley@us.af.mil
(g) Below is the required information to participate in the site visit. Contractors with current base access are not required to provide the below information, but must meet at the designated place and sign in.
SITE VISIT REQUIRED INFORMATION
***NOTE: CONTRACTORS SHALL NOT TRANSMIT THIS INFORMATION OVER UNSECURE EMAIL.
CONTRACTORS CAN EITHER HAND DELIVER OR PHONE IN THE INFORMATION TO THE POINT OF CONTACT
LISTED ON FBO.***
PRIVACY ACT STATEMENT Authority: 10 U.S.C. 8013 and Executive Orders 13478 and 9397 as amended (SSN). Purpose: Information collected by Security Forces personnel will be used to authorize installation entry to persons shown on the entry authority listing for the specific purpose provided by the sponsor.
Information will also be used to notify person(s) designated as the visitor sponsor of arrival and other pertinent information relating to entry on the installation. Routine Uses: Records may be disclosed to applicable Federal, State, or local agency charged with the responsibility of investigating or prosecuting a violation or enforcing/implementing a statute, rule, regulation, order issued pursuant thereto. Disclosure:
Disclosure of requested information is voluntary. Failure to provide all or parts of information requested can result in denial of installation entry. System of records number F031 AF SF B, Security Forces Management
Information System (SFMIS), Defense Biometric Identification Systems (DBIDS) applies.
Legal Name of Guest: Gender: DOB: SSAN Driver’s License # State Issued
Citizenship
(Last, First, MI) (M/F) (1962 Jan 11) (No Dashes) (M19GO62BLU / MI) Yes/No
(End of provision)
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Lot Taxiway Painting/Rubber Removal
FFP
Project Number SGBP 15-0016 - Requirement for removal of 250,000 SF of rubber deposits on runway 12/30 and removal of approximately 5,000 SF of paint markings on the runway, taxiways and parking aprons. Requirement also includes repainting taxiway/apron center lines and other select markings not removed on the airfield IAW attached Drawings and Specifications. The performance period for this project is 120 days which includes 45 days for Airfield/Construction waivers and 5 days for mission delays
FOB: Destination
PURCHASE REQUEST NUMBER: F3H3G25064AW01
SIGNAL CODE: A
NET AMT
Section C - Descriptions and Specifications
DRAWINGS AND SPECIFICATIONS
Drawings and Specifications refer to Section J “List of Attachments
CLAUSES INCORPORATED BY REFERENCE
252.236-7001 Contract Drawings, and Specifications AUG 2000
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government
52.246-12 Inspection of Construction AUG 1996
252.246-7000 Material Inspection And Receiving Report MAR 2008
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
0001 120 dys. ADC 1 55 CES/CENMPC
ANDY VOYLES
106 PEACEKEEPER LN
OFFUTT AFB NE 68113
402-232-1076
FOB: Destination
52.247-34 F.O.B. Destination NOV 1991
Section H - Special Contract Requirements
CLAUSES INCORPORATED BY FULL TEXT
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (MAY 2013)
(a) Definitions. As used in this clause--
Department of Defense Activity Address Code (DoDAAC) is a six position code that uniquely identifies a unit, activity, or organization.
Document type means the type of payment request or receiving report available for creation in Wide Area WorkFlow
(WAWF).
Local processing office (LPO) is the office responsible for payment certification when payment certification is done external to the entitlement system.
(b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall--
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this Web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training
Course and use the Practice Training Site before submitting payment requests through
WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via Web entry, Electronic Data
Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:
(1) Document type. The Contractor shall use the following document type(s).
Construction Invoice
(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in
WAWF, as specified by the contracting officer.
Government
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table*
Field Name in WAWF Data to be entered in WAWF
Pay Official DoDAAC TBD
Issue By DoDAAC FA4600
Admin DoDAAC FA4600
Inspect By DoDAAC FA4600
Ship To Code FA4600
Ship From Code ____
Mark For Code ____
Service Approver (DoDAAC) FA4600
Service Acceptor (DoDAAC) FA4600
Accept at Other DoDAAC ____
LPO DoDAAC ____
DCAA Auditor DoDAAC ____
Other DoDAAC(s) ____
(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request.
(5) WAWF email notifications. The Contractor shall enter the email address identified below in the “Send Additional
Email Notifications” field of WAWF once a document is submitted in the system.
SSgt Daniel Hinsley
SSgt Lucas Thomas
Mr. Andrew Voyles
(g) WAWF point of contact. (1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.
Not applicable.
(2) For technical WAWF help, contact the WAWF helpdesk at 866-618-5988.
(End of clause)
A. INVOICE SUBMISSION AND PAYMENT
ELECTRONIC SUBMISSION OF INVOICES AND RECEIVING REPORTS IS
MANDATORY in accordance with DFARS 252.232-7003
1. ELECTRONIC SUBMISSION VIA WIDE AREA WORKFLOW (WAWF): Contractors must register and begin submitting electronic invoices immediately through the Wide Area Workflow Receipt and Acceptance Internet site:
https://wawf.eb.mil/. On line training is available at http://www.wawftraining.com unless unable to do so. Use the following data elements to invoice for services or supplies procured via this contract. The award document number is located in the lower right-hand corner.
2. SEE DFARS CLAUSE 252.232-7006 Wide Area Workflow Payment Instructions, in full text
3. PAYMENT WILL BE MADE BY:
SEE BLOCK 27. ON FORM 1442
B. CHANGES TO THIS CONTRACT / PURCHASE ORDER / DELIVERY ORDER
The Contracting Officer (CO) is the only person authorized to approve changes or modify any of the requirements under this contract and, notwithstanding any provisions contained elsewhere in this contract, the said authority remains solely with the CO. In the event the Contractor effects any such change at the direction of any person other than the CO, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in costs incurred as a result thereof.
Contractual problems, of any nature, which might occur during the life of the contract must be handled in conformance with public laws and regulations and must be referred to the CO for resolution. Only the CO is authorized to formally resolve such problems. Therefore, the Contractor is hereby directed to bring all such contractual problems to the immediate attention of the CO. Any request for contract changes/modification shall be submitted to the CO.
C. SAM.GOV REGISTRATION
Invoice payment cannot be made if a contractor's System for Award Management (SAM) registration is inactive.
Invoices received from a contractor whO fails to maintain active SAM.GOV registration are considered to be improper and will be returned. The contractor is responsible to maintain active SAM.GOV registration until final payment has been made. SAM.GOV registration must be updated and renewed annually at http://www.sam.gov .
D. DELIVERY / BASE ACCESS REQUIREMENTS
1. Delivery personnel must use the commercial vehicle inspection lane adjacent to the STRATCOM Gate off of
Capehart road south of the Bellevue, Nebraska, Highway 370 exit. Report to the Pass and Registration office for base access pass issuance, and call for escort (if needed) to the final destination. Note: It is important to know the organization name, and name / phone number of the POC prior to arrival at Offutt AFB.
2. Delivery vehicles are subject to inspection/search by Security Forces personnel. All tools, including assembly tools, must be secured within a toolbox in the trailer of the vehicle and should not be transported on base in the cab of the vehicle. All personnel accessing Offutt Air Force Base will be held to safety/security rules of engagement when entering and while on base. These rules include a ban on weapons to include firearms, loaded or otherwise, and the transport of any explosive material.
E. NATIONAL CRIME INFORMATION CENTER (NCIC) BACKGROUND CHECK
1. In addition to the requirements identified in FAR 52.204-9 - Personal Identity Verification of Contractor
Personnel and AFFARS 5352.242-9000 - Contractor access to Air Force installations, all contract employees require a positive NCIC background check prior to being granted access to Offutt AFB in accordance with the installation security policy. To expedite this requirement, the contractor shall make contact with the sponsoring unit/base agency
POC or security manager listed above, and request a copy of the 55 SFS Contractor / Vendor Pass Request & NCIC
Screening Spreadsheet (See information template below). The contractor shall provide the data requested on the spreadsheet for every employee proposed to perform work under this contract requiring physical access to Offutt
AFB. The contractor shall return all completed spreadsheets to the sponsoring unit/base agency POC or security manager no later than 5 business days prior to the contract start date. See below for additional security checks needed for restricted and controlled areas.
55 SFS Contractor / Vendor NCOC Screening & Pass Request Spreadsheet Template
U.S. Citizen
Last First, MI Year Month Day Drivers License/ID # State First 3 Last 6 Days Hrs Dates (MMDDYYYY) Yes / No Mon-Fri 0730-1630 04032015 - 04302015 Yes
Base Sponsor's Phone #: (Work/Cell) (Filled in by base sponsor) Company Representative Name:
Request Date: (Filled in by base sponsor) Company Representative Phone Number:
Full Name Date of Birth SSAN Work Schedule
55 SFS CONTRACTOR/VENDOR NCIC SCREENING & PASS REQUEST SPREADSHEET
Personally Identifying Info rmation (PII) being co llected by this fo rm is authorized fo r co llect ion under p rovis ions o f 10 U.S.C. 8013 , Secretary o f the Air Fo rce, DoD 5200 .2R, DoD Personnel Security Prog ram; AFI 33 -202 , Computer Security, Info rmation will be maintained by local Security
Fo rces Authority while access requirements exis t . Info rmation access is res tricted to personnel responsib le fo r contract adminis trat ion, o r o therwise needed in the perfo rmance o f o fficial DoD duties . Info rmation will be p roperly d isposed o f when its required use has been concluded .
Provid ing this info rmation is vo luntary; however, failure to p rovide all o f the required data shown on the sp readsheet will result in denial o f entry to the ins tallat ion. This info rmation is exempt from OMB licens ing under p rovis ions o f AFI 33 -324 , Info rmation Co llect ions and Reports
Management Prog ram; Contro lling Internal, Pub lic, and Interagency Air Fo rce Co llect ions , parag raphs 3 .16 .11 and 3 .16 .16 .3 .
Offutt AFB Sponsoring Agency / Unit: (Filled in by base sponsor) Company Name:
Base Sponsor's Name: (Filled in by sponsoring agency) Company Address:
Note: Only use the spreadsheet provided by the base agency POC /or security manager. Input employee data as shown in the above template format. Non U.S. Citizens require additional vetting processes and must physically present their employment authorization card to the Pass & ID office before access can be granted. If airfield access is required, please allow an additional 14 days to process the Entry Authorization List (EAL). Contact base agency POC for more details.
2. If an individual is denied a base pass/access to the installation, the contractor is not prohibited from hiring that individual for work on this contract as long as the work entailed does not require the individual to have physical access to Offutt AFB or any of its facilities. Employees who refuse to complete the form will be denied access to the installation.
3. All illegal aliens are considered unauthorized individuals and will be barred from the base. Illegal aliens attempting entry or found on the installation (if incorrectly issued a pass) will be processed as an unauthorized individual and removed from the installation. In addition to notifying the contractor of the illegal alien, the Offutt
AFB Security Forces will notify AF Office of Special Investigations, local police and the US Immigration and
Customs Enforcement office. Contractors are prohibited from hiring illegal aliens for work on a Government contract and the other Government agencies contacted upon discovery of the illegal may seek corrective and/or punitive actions pursuant to law against the hiring organization if violations occur.
4. The below list identifies reasons why an individual, if they are identified during the NCIC check, would be denied access to Offutt AFB:
Disqualifiers that would deny contract employee’s entry/access to the installation or its facilities:
- U.S. Citizenship, immigration status, or Social Security Account Number cannot be verified.
- Wanted by federal or civil law enforcement authorities, regardless of offense or violation.
- Conviction of firearms or explosives violation within the past three years.
- Incarcerated for 12 months or longer within the past three years, regardless of offense or violation.
- Conviction of espionage, sabotage, treason or terrorism, murder, sexual assault, armed assault/robbery, rape, child molestation, drug possession with intent to sell, or drug distribution.
- Name appears on any federal agency’s “watch list” or “hit list” for criminal behavior or terrorist activity.
- Any other criminal activity identified on the NCIC check that the Wing Commander determines to be so serious as to pose a possible threat to the safety and security of base personnel and facilities.
- Name appears on any federal installation debarment list.
5. A 100% Base Pass check is required for all contractors (even if a passenger in an authorized vehicle) and contract vehicles entering the installation. Contractors are not authorized to bring guests or other contract employees onto the installation unless those individuals are personally in possession of a base pass or Government Identification card.
RESTRICTED AREA & CONTROLLED AREA ACCESS REQUIREMENTS
1. In accordance with AFI 31-101, Integrated Defense, and the 55th Wing Integrated Defense Plan, access to controlled and restricted areas is a formal process with strict controls for approving unescorted entry. Unescorted entry to these areas should never be granted solely on the basis of convenience.
a. Offutt AFB uses the AF Form 2586 Unescorted Entry Authorization Certificate, to document, coordinate, and approve unescorted entry authority for issuance of a base restricted area badge.
Issuance of this type of credential requires additional vetting that takes place after the base access approval process.
b. Certain projects will only require the sponsor to submit an entry authority list (EAL) for contract worker entry. Use of EALs for accessing restricted/controlled areas will require additional vetting that takes place after the base access approval process.
2. Sponsoring unit security managers determine need and suitability for access into these areas based on contractual requirements and mission needs. Security managers will coordinate all restricted area access requests to appropriate unit commander(s) for access approval.
3. Contractors must have a “Green Stripe” Common Access Card (CAC), or long term Defense Biometric
Identification System (DBIDS) Card for base access prior to a restricted area badge request being initiated.
RETURN OF BASE / RESTRICTED & CONTROLLED AREA ACCESS IDENTIFICATION
CREDENTIALS
1. AF Federal Acquisition Regulation Supplement (AFFARS) 5352.242-9000, Contractor Access to Air Force
Installations, Jun 02, is incorporated in local contracts. The contractor’s failure to comply with AFFARS requirements may result in withholding of final payment
2. All contractor identification credentials issued for base access and access to restricted/controlled areas must be returned to the issuing agency once the contract is completed or upon employment termination.
F. MOTOR VEHICLE OPERATION ON BASE
1. Contractor personnel are advised that seat belt usage is mandatory at all times on Offutt AFB. Nebraska state law requires the use of restraints in a vehicle. Offutt AFB Instruction 31-204, 20 October 2010, Security, Motor Vehicle
Traffic Supervision states that failing to utilize seat belts or other restraints while moving will result in the issuance of a 7-day driving suspension and the individual’s traffic history on Offutt AFB being assessed points for the first offense. Repeated offenses on Offutt AFB will result in the loss of on-base driving privileges and could have an adverse affect on your ability to perform your contract. Air Force Instruction 31-204, Air Force Motor Traffic
Supervision, prescribes that installation commanders must ensure drivers comply with state and local traffic laws both on and off base. Accordingly, while on Offutt AFB, operators and passengers must wear restraints and may be ticketed by Offutt security personnel for failure to comply. In addition, the following administrative penalties, as a minimum, will be imposed on drivers who are cited for speeding 10 mph - 15 mph over base housing posted speed limits: the first offense will result in the issuance of a 7-day driving suspension and the individual’s traffic history being assessed points. Repeated offenses on Offutt AFB will result in the loss of on-base driving privileges and could have an adverse affect on your ability to perform your contract.
2. Contractor personnel are advised that vehicle operators on a DoD installation and operators of Government owned vehicles will not use cell phones unless the vehicle is safely parked or unless they are using a hands-free device. The wearing of any other portable headphones, earphones, or other listening devices (except for hands-free cellular phones) while operating a motor vehicle is prohibited (DoD Joint Motor Vehicle Traffic Supervision
Regulation, paragraph 4-2). Using a cell phone while driving, without a hands free device will be considered a
"primary offense", meaning that violators are subject to being stopped and ticketed solely for this offense and the individual’s traffic history on Offutt AFB being assessed points for the first offense. Repeated offenses on Offutt
AFB will result in the loss of on-base driving privileges and could have an adverse affect on your ability to perform your contract.
G. WORK SCHEDULE
See project specifications for working hours. If no working hours are listed, hours will be between the hours of 7:30
A.M. and 5:00 P.M., excluding Saturdays, Sundays, and Federal holidays. If the contractor desires to work during periods other than working hours listed in the contract specifications or listed above if not in the specifications, additional Government inspection forces may be required. The contractor must notify the Contracting Officer (CO) three days in advance of this intention to work during other periods. This allows assignment of additional inspection forces when the CO determines that they are reasonably available. If such force is reasonably available, the CO may authorize the contractor to perform in excess of their normal duty hours/days solely for the benefit of the contractor, and the actual cost of the inspection at overtime rates will be charged to the contractor. These adjustments to the contract price may be made periodically as directed by the CO.
LEGAL HOLIDAYS OBSERVED AT MILITARY INSTALLATIONS
* New Years Day 1 January
Martin Luther King’s Birthday Third Monday in January
President’s Day Third Monday in February
Memorial Day Last Monday in May
*Independence Day 4 July
Labor Day First Monday in September
Columbus Day Second Monday in October
*Veterans Day 11 November
Thanksgiving Day Fourth Thursday in November
*Christmas Day 25 December
*The above marked Federal holidays which fall on Saturday or Sunday will be observed either on Friday or Monday.
WINTER EXCLUSION
The winter exclusion is applicable to this contract. No work will be required during the period of 15 Oct – 1 May
(inclusive). The contractor may, however, perform work during all or any part of this period by submitting written request to the Contracting Officer. The contractor shall submit, along with their request to work, a schedule of work to be performed during said exclusion period.
NOTE: Winter Exclusion days have not been integrated into the Delivery Schedule provided in Section F.
H. PROGRESS SCHEDULE
(1) The Contractor shall submit a completed AF Form 3064 within ten days after effective date of the Notice to
Proceed.
(2) The Contractor shall submit a completed revised AF Form 3064 within ten days after effective date of a modification if required or if requested by the Contracting Officer.
(3) Progress payments shall not be made unless an approved AF Form 3064 is on file.
(4) Should the contractor fail to submit a completed AF Form 3064, as stated in para. (1) & (2), the Contracting
Officer may, at his/her option, suspend work at no cost to the Government, until a satisfactory AF Form 3064 is submitted
(5) The Contractor shall submit a completed AF Form 3065, Progress Report, on a weekly basis beginning after the issuance of the Notice to Proceed (NTP).
I. ADMINISTRATIVE AUTHORITY
(1) Following award, this contract will be administered by the 55 th
Contracting Squadron. The following address and telephone number of the Contracting Officer are as follows:
th
Contracting Squadron/LGCA
101 Washington Square, Bldg 40
Offutt AFB NE 68113-2107
Contracting Officer: SSgt Lucas Thomas
Telephone Number: 402-232-5993
Contract Administrator: SSgt Daniel Hinsley
Telephone Number: 402-294-2883
Fax Number: 402-294-7280
(2) All correspondence concerning this contract, such as requests for information, explanation of terms, and contract interpretations, shall be submitted to the CO.
J. REQUIRED INSURANCE (IAW FAR 28-306(b))
Reference FAR clause entitled "Insurance . . . “ the Contractor shall, at its own expense, procure and thereafter maintain the following kinds of insurance with respect to performance under the contract.
(1) Workmen's Compensation and Employers Liability Insurance as required by law except that if this contract is to be performed in a State which does not require or permit private insurance, then compliance with the statutory or administrative requirements in any such State will be satisfactory. The required Workmen's Compensation insurance shall extend to cover employer's liability for accidental bodily injury or death and for occupational disease with a minimum liability limit of $100,000.
(2) General Liability Insurance. Bodily injury liability insurance, in the minimum limits of $500,000 per occurrence shall be required on the comprehensive form of policy.
(3) Automobile Liability Insurance. This insurance shall be required on the comprehensive form of policy and shall provide bodily injury liability and property damage liability covering the operation of all automobiles used in connection with the performance of the contract. At least the minimum limits of $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage shall be required.
K. MATERIAL PAYMENTS
(1) Payments may be made for major high-value materials, in advance of installation.
(2) Payment for materials stored off-site will not be made unless sound procedures (such as a bonded warehouse) are established for their accountability and control, subject to the same procedures outlined in 3(c) below.
(3) Payment for major high-value materials stored on Offutt AFB may be made subject to the following:
(a) To be eligible for payment in advance of installation, materials must be shown as a percentage of the work and submitted for approval. In order to properly evaluate this item, a complete breakdown by quantity, item description, and cost for each major, high-value item must be furnished. Once approved, no changes will be allowed to include additional materials for payment.
(b) A joint inventory and inspection of such items approved for payment must be made by the contractor and the contract administrator of the Contracting Office to ensure that the quantities are valid, the items are as described, and sufficient security measures have been taken to prevent damage or theft.
(c) Although materials paid for become the property of the Government, the contractor remains responsible for all materials delivered and work performed until completion and acceptance of the construction work. Responsibility for safeguarding material until final inspection and inspection rests with the contractor.
(d) The contractor must prove he has title to the materials (i.e., paid invoices) and will use them to perform the contract.
(e) When requesting payment for approved materials, the contractor must provide a certificate, substantially as shown below, in addition to submitting supplier's paid invoice.
(1) (Contractor’s Name) hereby transfers and assigns to Offutt AFB all its rights, titles, and interest of every kind and character in and to all of the goods described in the attached request for payment. Those who have furnished materials or supplied such goods to us have executed a waiver of claim and lien, a copy of which is attached
(2) (Contractor’s Name) acknowledges that, despite transfer of title, until such goods have been delivered to the job site, incorporated into the work, inspected and accepted, shall
(Contractor’s Name) remain responsible for:
a. Cost and expenses of storage, as applicable;
b. Insurance premiums;
c. Deterioration of such goods.
d. Loss or mysterious disappearance of such goods; and
e. Such portion of goods not in accordance with the contract requirements.
(3) (Contractor’s Name) hereby acknowledges that it has no interest in such goods by virtue of retained possession, and states that it keeps such goods for Offutt AFB and disclaims any claims against such goods for storage cost, for unpaid contract retainage, or for any other reason.
(4) The Contracting Officer will have the final decision on which materials are major, high-value materials.
L. BONDS
SEE FAR Clauses 52.228-1 through 16 if incorporated in contract.
(1) Performance and Payment Bonds. Within ten days after award, the contractor shall furnish two bonds executed on the required forms, each with good and sufficient surety or sureties acceptable to the Government; namely a
Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25A). The penal sums of such bonds shall be as follows (performance bonds are not required for contracts of $150,000 or less):
(a) Performance Bond: The penal amount of performance bonds must equal—
(1) 100 percent of the original contract price; and
(2) If the contract price increases, an additional amount equal to 100 percent of the increase.
(b) Payment Bond: The amount of the payment bond must equal—
(1) 100 percent of the original contract price; and
(2) If the contract price increases, and additional amount equal to 100 percent of the increase.
(3) The amount of the payment bond must be no less than the amount of the performance bond.
(4) Any bonds required will be furnished by the Contractor to the Government prior to commencement of contract performance.
NOTE: Per FAR 28.202, Corporate sureties offered for bonds furnished with contracts performed in the United
States or its outlying areas must appear on the list contained in the Department of Treasury Circular 570. The sureties list can be found at: http://www.fms.treas.gov/c570/c570.html#certified
M. ENVIRONMENTAL COMPLIANCE
In addition to the FAR and DFARS clauses included in this contract,
(1) Contractor warrants that it is familiar with all local, county, state and Federal environmental regulations.
(2) Contractor agrees to perform all required training and notifications concerning hazardous waste or materials related to contractor's activities and maintain an on-site listing of employees so trained.
(3) Contractor agrees to properly manage all hazardous waste and materials related to contractor's activities.
(4) Contractor agrees that it shall reimburse the Government for any penalties assessed against the Government by any Environmental Regulatory Agency for environmental violations related to Contractor activities.
(5) Contractor agrees that it shall reimburse the Government for any civil or criminal costs incurred by the
Government for improper handling or disposal of regulated or hazardous waste by the contractor or any of its’ subcontractors for environmental violations related to Contractor activities.
N. ANTI-TERRORISM INFORMATION AND CONSIDERATIONS
1. Base Entry: All contractor vehicles will enter through the SAC Gate and have a proper vehicle search conducted.
Exceptions to this policy will be coordinated through the contracting officer and appropriate security forces personnel.
2. Areas Off Limits: The following areas are off limits unless given specific permission, an escort, or work is to be performed in the area listed. Restricted areas, flight line area, General’s row, dormitories (Bldgs 324, 326, 365, and
367), Bldg 500 complex, and the Offutt Field House gymnasium. Travel to and from the worksite will be made by the most direct route possible.
3. Force Protection Conditions (FPCONS): FPCONS describe the progressive level of countermeasures in response to a terrorist threat to US military facilities and personnel. Force Protection Condition measures are used to deter terrorist attacks on DoD facilities and personnel by:
(1) Varying routines.
(2) Being sensitive to changes in the security atmosphere around DoD facilities and personnel.
The five FPCONS are defined as the following:
(1) Normal: This condition applies when a general global threat of possible terrorist activity exists and warrants a routine security posture
(2) Alpha: This condition applies when a general threat of possible terrorist activity against personnel and facilities, the nature and extent of which are unpredictable.
(3) Bravo: This condition applies when an increased and more predictable threat of terrorist activity exists.
(4) Charlie: This condition applies when an incident occurs or intelligence is received indicating some form of terrorist action or targeting against personnel or facilities is likely.
(5) Delta: This condition applies in the immediate area where a terrorist attack has occurred or when intelligence has been received that terrorist action against a specific location or person is imminent.
Contractors may be asked to leave the base or not be allowed to enter the base when in elevated FPCONs.
For further information concerning FPCONs, contact the contracting administrator or contracting officer for additional guidance.
4. Contractors identified as mission essential, have been briefed on additional duties and responsibilities associated with increased FPCONs.
5. Suspicious Activities/Stolen Equipment: Please report any suspicious activity or stolen equipment to the Law
Enforcement Desk at 294-6110.
6. Searches/Spot Checks: During increased Random Force Protection Measures (RAMs) contractors and their equipment are subject to search via RAMs at any time. Spot checks may also be conducted due to RAMs.
7. Identification: Contractor personnel must keep base issued identification on their person while working on base.
O. SALES TAX
Offutt Air Force Base is exempt from paying state and local taxes on purchases that it makes per the United States
Constitution.
Nebraska Revised Statutes, Sec. 77-2704.02 and Nebraska Sales and Use Tax Regulations 1-12 and 1-72 implement this policy and are applicable to this purchase. The Nebraska Form 13, Nebraska Resale or Exempt Sale Certificate, is applicable to exempt taxes for contracts for services and commodities and labor on construction projects. 55
CONS can provide signed Nebraska Forms 17G, Purchasing Agent Appointment and Delegation of Authority for
Sales and Use Tax, to exempt State taxes for construction contract materials. Therefore, for construction only, applicable Nebraska State tax costs for materials should not be included in the bid/proposal submitted by the offeror/contractor.
P. DAVIS BACON
Department of Labor (DOL) Wage Determination NE150028 01/02/2015 NE28 shall be considered incorporated upon award.
Q. CLAUSES AND PROVISIONS
Clauses and Provisions from the Federal Acquisition Regulation (FAR) and supplements thereto are incorporated in the document by reference and full text. Those incorporated by reference have the same force and effect as if they were given in full text.
Clauses and provisions in the document will be numbered in sequence, but not necessarily appear in consecutive order.
Sections K, L and M will be physically removed from any resultant award, but section K will be deemed to be incorporated by reference in that award.
Section I - Contract Clauses
52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011
52.204-10 Reporting Executive Compensation and First-Tier Subcontract
Awards
JUL 2013
52.204-13 System for Award Management Maintenance JUL 2013
52.204-18 Commercial and Government Entity Code Maintenance NOV 2014
52.209-6 Protecting the Government's Interest When Subcontracting
With Contractors Debarred, Suspended, or Proposed for
Debarment
AUG 2013
52.209-10 Prohibition on Contracting With Inverted Domestic
Corporations
DEC 2014
52.211-13 Time Extensions SEP 2000
52.214-18 Preparation of Bids-Construction APR 1984
52.214-19 Contract Award-Sealed Bidding-Construction AUG 1996
52.214-29 Order Of Precedence--Sealed Bidding JAN 1986
52.219-6 Notice Of Total Small Business Set-Aside NOV 2011
52.219-28 Post-Award Small Business Program Rerepresentation JUL 2013
52.222-3 Convict Labor JUN 2003
52.222-4 Contract Work Hours and Safety Standards- Overtime
Compensation
MAY 2014
52.222-6 Construction Wage Rate Requirements MAY 2014
52.222-7 Withholding of Funds MAY 2014
52.222-8 Payrolls and Basic Records MAY 2014
52.222-9 Apprentices and Trainees JUL 2005
52.222-10 Compliance with Copeland Act Requirements FEB 1988
52.222-11 Subcontracts (Labor Standards) MAY 2014
52.222-12 Contract Termination-Debarment MAY 2014
52.222-13 Compliance With Construction Wage Rate Requirements and
Related Regulations
MAY 2014
52.222-14 Disputes Concerning Labor Standards FEB 1988
52.222-15 Certification of Eligibility MAY 2014
52.222-21 Prohibition Of Segregated Facilities FEB 1999
52.222-23 Notice of Requirement for Affirmative Action to Ensure
Equal Employment Opportunity for Construction
FEB 1999
52.222-26 Equal Opportunity MAR 2007
52.222-27 Affirmative Action Compliance Requirements for
Construction
FEB 1999
52.222-36 Equal Opportunity for Workers with Disabilities JUL 2014
52.222-50 Combating Trafficking in Persons MAR 2015
52.222-55 Minimum Wages Under Executive Order 13658 DEC 2014
52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts
SEP 2013
52.223-3 Hazardous Material Identification And Material Safety Data JAN 1997
52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011
52.223-15 Energy Efficiency in Energy-Consuming Products DEC 2007
52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts
MAY 2008
52.223-18 Encouraging Contractor Policies To Ban Text Messaging
While Driving
AUG 2011
52.225-9 Buy American--Construction Materials MAY 2014
52.225-10 Notice of Buy American Requirement--Construction Materials MAY 2014
52.225-13 Restrictions on Certain Foreign Purchases JUN 2008
52.227-1 Authorization and Consent DEC 2007
52.227-2 Notice And Assistance Regarding Patent And Copyright
Infringement
DEC 2007
52.227-4 Patent Indemnity-Construction Contracts DEC 2007
52.228-2 Additional Bond Security OCT 1997
52.228-5 Insurance - Work On A Government Installation JAN 1997
52.228-11 Pledges Of Assets JAN 2012
52.228-12 Prospective Subcontractor Requests for Bonds MAY 2014
52.228-14 Irrevocable Letter of Credit NOV 2014
52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014
52.232-17 Interest MAY 2014
52.232-18 Availability Of Funds APR 1984
52.232-23 Assignment Of Claims MAY 2014
52.232-27 Prompt Payment for Construction Contracts MAY 2014
52.232-33 Payment by Electronic Funds Transfer--System for Award
Management
JUL 2013
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013
52.232-40 Providing Accelerated Payments to Small Business
Subcontractors
DEC 2013
52.233-1 Disputes MAY 2014
52.233-3 Protest After Award AUG 1996
52.233-4 Applicable Law for Breach of Contract Claim OCT 2004
52.236-2 Differing Site Conditions APR 1984
52.236-3 Site Investigation and Conditions Affecting the Work APR 1984
52.236-5 Material and Workmanship APR 1984
52.236-6 Superintendence by the Contractor APR 1984
52.236-7 Permits and Responsibilities NOV 1991
52.236-8 Other Contracts APR 1984
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984
52.236-11 Use and Possession Prior to Completion APR 1984
52.236-12 Cleaning Up APR 1984
52.236-13 Accident Prevention NOV 1991
52.236-14 Availability and Use of Utility Services APR 1984
52.236-15 Schedules for Construction Contracts APR 1984
52.236-16 Quantity Surveys APR 1984
52.236-17 Layout of Work APR 1984
52.236-21 Alt I Specifications and Drawings for Construction (Feb 1997) -
Alternate I
APR 1984
52.236-26 Preconstruction Conference FEB 1995
52.242-13 Bankruptcy JUL 1995
52.242-14 Suspension of Work APR 1984
52.243-4 Changes JUN 2007
52.243-6 Change Order Accounting APR 1984
52.246-21 Warranty of Construction MAR 1994
52.248-3 Value Engineering-Construction OCT 2010
52.249-2 Alt I Termination for Convenience of the Government (Fixed-
Price) (Apr 2012) - Alternate I
SEP 1996
52.249-10 Default (Fixed-Price Construction) APR 1984
52.252-3 Alterations in Solicitation APR 1984
52.252-4 Alterations in Contract APR 1984
52.253-1 Computer Generated Forms JAN 1991
252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense-
Contract-Related Felonies
DEC 2008
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013
252.203-7005 Representation Relating to Compensation of Former DoD
Officials
NOV 2011
252.204-7003 Control Of Government Personnel Work Product APR 1992
252.204-7004 Alt A System for Award Management Alternate A FEB 2014
252.204-7006 Billing Instructions OCT 2005
252.204-7015 Disclosure of Information to Litigation Support Contractors FEB 2014
252.209-7004 Subcontracting With Firms That Are Owned or Controlled By
The Government of a Country that is a State Sponsor of
Terrorism
DEC 2014
252.223-7001 Hazard Warning Labels DEC 1991
252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or
Hazardous Materials
SEP 2014
252.223-7008 Prohibition of Hexavalent Chromium JUN 2013
252.225-7002 Qualifying Country Sources As Subcontractors DEC 2012
252.225-7012 Preference For Certain Domestic Commodities FEB 2013
252.227-7033 Rights in Shop Drawings APR 1966
252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
JUN 2012
252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
JUN 2012
252.232-7010 Levies on Contract Payments DEC 2006
252.236-7000 Modification Proposals-Price Breakdown DEC 1991
252.236-7005 Airfield Safety Precautions DEC 1991
252.243-7001 Pricing Of Contract Modifications DEC 1991
252.243-7002 Requests for Equitable Adjustment DEC 2012
252.244-7000 Subcontracts for Commercial Items JUN 2013
252.247-7023 Transportation of Supplies by Sea APR 2014
252.247-7024 Notification Of Transportation Of Supplies By Sea MAR 2000
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the
Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 calendar days after the date the contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP…
This is the start of the file's text. The full file is on GovTribe.