Attachment_6_-_Questions_and_Answers_part_2.docx

DOCX document 15 KB Posted

Attached to
Replace Lighting Bldg 286 Federal contract opportunity
Solicitation number
FA4528-17-R-0004
Issued by
Department of the Air Force Global Strike Command

About this file

Attachment 6 - Questions and Answers part 2

View the file

Other files for this federal contract opportunity

Other files attached to Replace Lighting Bldg 286, newest first.
File Type Posted
SF30_Hubzone.pdf PDF
17-R-0004-0004.pdf PDF
Attachment_6_-_Questions_and_Answers_part_2.docx DOCX document
SF_30.pdf PDF
AF66_Submittal_Register_revision_3.pdf PDF
B286_specifications_v9_(with_amendments).pdf PDF
Building_286_pdf.pdf PDF
FA4528-17-R-0004_Amendment_2.docx DOCX document
Attachment_1_-_Revised_Specifications.pdf PDF
Attachment_6_-_Revised_Questions_and_Answers.docx DOCX document
286.pdf PDF
SF-30.pdf PDF
BuildingFixture_Heights.docx DOCX document
Attachment_6_-_Questions_and_Answers.docx DOCX document
15-0041_AS_BUILT.pdf PDF
AF66_Submittal_Register_revision_2_(with_amendments).pdf PDF
Combined_Drawings_15-0041.pdf PDF
286.dwg DWG drawing
B286_specifications_v7_(with_amendments).pdf PDF
Attachment_5_-_Financial_Responsibility.docx DOCX document
Attachment_1_-_Specification.pdf PDF
Attachment_2_-_Form_66.pdf PDF
FA4528-17-R-0004.pdf PDF
Attachment_4_-_Past_Performance_Information_Form.docx DOCX document
Attachment_3_-_WD.pdf PDF
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-Proposal Offeror Questions and Government Responses QJVF 15-0041, Replace Lighting Building 286

FA4528-17-R-0004

Attachment 6a 14 April 2017

1. Could we get the Reflected Ceiling Plan from the A sheets for reference?

Not Available

2. At the walk, I did not see the lighting control panels to be replaced. What information and pictures do you have to work with?

See drawings and specifications.

3. Where are drawings identified in solicitation FA4528-17-R-0004 spec section 01 11 00, 1.1.1.4?

See new attachments

4. What are the allowable shutdown schedules for switch overs?

See Specifications

5. Who is responsible for providing the design drawings?

See new attachments

6. Has an environmental site assessment been completed and if so can it be provided?

None will be provided.

7. Are there any know environmental hazards?

No.

8. Who is providing the record drawings for solicitations FA4528-17-R-0003 and FA4528-17-R-0004 as shown is specifications section 01 78 00 1.2.2 See Specifications.

9. Why are the two solicitations being separated and not included as one?

N/A

10. Will the Government be requiring the electrical equipment to be painted as identified in section 26 00 00 3.1?

See Specifications.

11. Where are the source drawing identified in section 01 37 00 1.5.2 See Specifications.

12. Will the Government be requiring full compliance with the EM385 as stated in the specifications?

Yes.

13. Will access to each site be escorted or will the contractor be allowed to be badged?

N/A

14. What time restraints for access should be allowed for entry from the front gate to each project site?

N/A

15. What are the access routes are available to each project site?

Bomber Blvd to Peacekeeper place is the primary route.

16. What specific perimeter area lighting of buildings are required to be replaced?

See Drawings.

17. Can a lighting operation plan be provided for each building?

No.

18. Where is the specification section in regards to raceways?

Follow NEC 2017

19. Is there a typical connection detail preferred for fixture connection? Plug in or hard wired?

No.

20. Is there a preferred hanger attachment for each fixture?

No.

21. What are the normal work hours/days allowed?

See specification Addendum

22. What are no work days?

See specifications

23. What is the holiday schedule where the contractor would be limited from working?

See specifications.

24. What are the minimum credentials for the design professional?

See specifications.