Draft01_Specifications.pdf
PDF 5 MB Posted
- Attached to
- Repair PRIDE Parking Lot Federal contract opportunity
- Solicitation number
- FA4528-15-R-0014
About this file
Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Contractor_Q A_-_15_May_15.docx | DOCX document | |
| SF_30_-_Add_Attachments.doc | DOC document | |
| Attachment_8_-_Contractor_Q A.docx | DOCX document | |
| Attachment_7_-_Revised_SOW_ _Drawings.pdf | ||
| Attachment_4_Past_Performance_Questionnaire.docx | DOCX document | |
| Attachment_1_Specifications.pdf | ||
| Attachment_2_Drawings.pdf | ||
| 15-R-0014_Repair_Pride_Parking_Lot.doc | DOC document | |
| Attachment_3_DB_Wage_Rates_ND_150002.pdf | ||
| Attachment_5_Financial_Responsibility.docx | DOCX document | |
| Attachment_6_Detailed_Construction_Breakdown.xlsx | XLSX spreadsheet | |
| Draft02_Drawings.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
S P E C I F I C A T I O N S
FOR PROJECT
QJVF 13-0067
REPAIR PRIDE PARKING LOT PHASE 2
AT
MINOT AIR FORCE BASE, NORTH DAKOTA
PREPARED BY:
5 CES, ENGINEERING FLIGHT
June 23, 2014
100% FOR REVIEW
Draf t
REPAIR PRIDE PARKING LOT PHASE 2
Project # QJVF13-0067
SPECIFICATIONS
OWNER Minot Air Force Base
5 CONS
165 Missile Avenue
Minot AFB, ND 58705-5027
ENGINEER FourFront Design, Inc.
517 Seventh Street
Rapid City, SD 57701
P (605) 342-9470 F (605) 342-2377
ENGINEER’S PROJECT NO. 13-2014-C07
DATE June 23, 2014
CERTIFICATION I hereby certify that the Specifications, together with the accompanying documents, were prepared by me or under my direct supervision and that I am duly registered under the laws of the State of North Dakota.
REPAIR PRIDE PARKING LOT PHASE 2 100% SUBMITTAL
MINOT AIR FORCE BASE, ND PROJECT NO. QJVF 13-0067
Specifications
Table of Contents
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 02/11 LIST OF DRAWINGS
DIVISION 01 – GENERAL REQUIREMENTS
01 11 00 02/14 GENERAL REQUIREMENTS
01 33 00 05/11 SUBMITTAL PROCEDURES
01 42 00 08/10 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.10 20 02/14 QUALITY CONTROL FOR MINOR CONSTRUCTION
01 57 20 02/14 ENVIRONMENTAL PROTECTION
01 78 00 02/14 CLOSEOUT SUBMITTALS
01 78 39 02/14 AS-BUILT DRAWINGS
DIVISION 26 - ELECTRICAL
26 00 00 00 20 07/06 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 00.00 40 08/13 COMMON WORK RESULTS FOR ELECTRICAL
26 05 19.00 10 11/08 INSULATED WIRE AND CABLE
26 05 71.00 40 05/11 LOW VOLTAGE OVERCURRENT PROTECTIVE DEVICES
26 55 53.00 10 10/07 EXTERIOR LIGHTING INCLUDING SECURITY AND CCTV
APPLICATIONS
26 56 00 05/13 EXTERIOR LIGHTING
26 56 13.00 40 11/08 LIGHTING POLES AND STANDARDS
26 56 23.00 40 11/08 AREA LIGHTING
DIVISION 31 – EARTHWORK
31 00 00 08/08 EARTHWORK
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 11 16 08/08 BASE COURSE FOR RIDGID PAVING
32 11 23 08/08 AGGREGATE AND/OR GRADED-CRUSHED AGGREGATE BASE
32 12 17 04/08 HOT MIX BITUMINOUS PAVEMNT
32 16 13 04/08 CONCRETE SIDEWALKS AND CURBS AND GUTTERS
32 17 23.00 10 04/08 PAVEMENT MARKINGS
32 92 19 10/06 SEEDING
DIVISION 33 – UTILITIES
33 11 00 02/11 WATER DISTRIBUTION
33 40 00 02/10 STORM DRAINAGE UTILITIES
APPENDIX A GEOTECHNICAL ENGINEERING REPORT
- - END OF PROJECT TABLE OF CONTENTS - -
PROJECT TABLE OF CONTENTS Page 1
Repair Pride Parking Lot Phase 2 100% Submittal Minot AFB, ND Project No. QJVF 13-0067
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
DOCUMENT 00 01 15
LIST OF DRAWINGS
02/11
PART 1 GENERAL
1.1 SUMMARY
1.2 CONTRACT DRAWINGS
1.3 SUPPLEMENTARY DRAWINGS
1.3.1 Boring Logs
1.3.2 Subsurface Data
-- End of Section Table of Contents --
DOCUMENT 00 01 15 Page 1
DOCUMENT 00 01 15
LIST OF DRAWINGS
02/11
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
G-001 Cover Sheet G-002 Design Analysis V-101 Site Topographic Survey CD-100 Site Demolition CP-100 Site Plan CP-101 Sidewalk Layouts CP-700 Erosion Control Plan CG-100 Overall Grading Plan CG-101 North Grading Plan CG-102 West Grading Plan CG-103 East Grading Plan CG-104 Loading Dock Grading Plan CU-101 Utility Plan Watermain Adjustments CU-102 Storm Sewer Plan & Profiles SD-1, SD-2, SD-3 CU-103 Storm Sewer Plan & Profile SD-4 CU-104 Storm Sewer Plan & Profile SD-5 C-501 Details Sheet 1 C-502 Details Sheet 2 E-001 Electrical Notes, Symbols and Abbreviations ED-100 Electrical Site Demo Plan EP-100 Electrical Site Plan E-500 Electrical Details
1.3 SUPPLEMENTARY DRAWINGS
1.3.1 Boring Logs
The Government does not guarantee that borings indicate actual conditions, except for the exact locations and the time that they were made.
Subsurface data, not specified or indicated, have been obtained by the Government at this station. The data are available for examination by prospective bidders in the office of the Contracting Officer.
1.3.2 Subsurface Data
Subsurface data, not specified or indicated, have been obtained by the Government at the station. The data are available for examination by prospective bidders in the office of the Contracting Officer. The soils report is included as part of the solicitation.
-- End of Document --
DOCUMENT 00 01 15 Page 2
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
GENERAL REQUIREMENTS
02/14
PART 1 GENERAL
1.1 LOCATION OF WORK
1.2 DESCRIPTION OF WORK
1.3 REFERENCES
1.4 SUBMITTALS
1.5 USE OF PREMISES
1.5.1 Area Designation
1.5.2 Coordination
1.6 EQUIPMENT PARKING
1.7 WORK SCHEDULE
1.8 CONSTRUCTION PROGRESS SCHEDULE
1.9 REFERENCE STANDARDS
1.9.1 Products
1.9.2 Standard Date
1.10 SAFETY
1.10.1 Regulations
1.10.2 Instructions
1.11 TRAFFIC CONTROL
1.12 HAULING MATERIALS
1.13 DRAWINGS AND SPECIFICATIONS
1.14 AS-BUILT DRAWINGS
1.15 WORK CONDUCT, CORRELATION, EXECUTION, ETC.
1.15.1 Work Performance
1.15.2 Storage
1.16 SUPERVISION
1.17 UTILITIES
1.18 PERMITS
1.18.1 Clearance Work Request
1.18.1.1 AF Form 103
1.18.1.2 Processing
1.18.1.3 Scheduling
1.18.1.4 Maintenance
1.18.1.5 Request Approval
1.18.1.6 Utility Protection
1.19 BASE ACCESS
1.19.1 [Enter Appropriate Subpart Title Here]
1.20 SECURITY REQUIREMENTS
1.20.1 Base Regulations
1.20.2 Identification of Employees
1.21 SANITARY FACIITIES
1.22 BUILDING INFORMATION CHECKLIST
1.23 RADIOACTIVE MATERIALS
1.24 ASBESTOS AND LEAD PAINT ABATEMENT
PART 2 PRODUCTS
SECTION 01 11 00 Page 1
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 11 00 Page 2
SECTION 01 11 00
GENERAL REQUIREMENTS
02/14
PART 1 GENERAL
1.1 LOCATION OF WORK
The work is located in the parking lot area surrounding Building 475 at Minot Air Force Base (MAFB). See location map on Drawing Sheet G-001 of the project drawing set for location. The work is in a controlled area.
1.2 DESCRIPTION OF WORK
1.2.1 Remove existing asphalt, base course, sidewalk, curb and gutter and miscellaneous electrical facilities. Contractor may remove and mill existing asphalt and blend with existing base course to specified depth.
1.2.2 Install new asphalt, base course, sidewalk, curb and gutter, concrete pans, inlets, storm sewer pipes and electrical lighting fixtures and poles.
1.3 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. DEPARTMENT OF DEFENSE (DOD)
UFC 1-300-08 (2010) Criteria For Transfer And Acceptance of DoD Real Property
1.4 SUBMITTALS
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Construction Progress Schedule Contract Progress Report Project Manager Project Superintendent Base Civil Engineering Work Clearance Request Personnel Listing Welding Permit Radioactive Materials
SD-11 Closeout Submittals
Building Information Checklist
1.5 USE OF PREMISES
1.5.1 Area Designation
The site is located within an uncontrolled area. Areas adjacent to the
SECTION 01 11 00 Page 3 site will remain occupied by the Government for the duration of the contract. The contractor shall limit the use of premises for work and construction operations to allow for Government occupancy.
1.5.2 Coordination
Coordinate use of premises under direction of the Contracting Officer.
1.6 EQUIPMENT PARKING
Space for the contractor's equipment will be allotted on MAFB. The exact location will be chosen during the preconstruction conference and shall be approved by the Contracting Officer at that time. The Government shall not be liable for the security of any of the contractor's equipment or material while on MAFB.
1.7 WORK SCHEDULE
Working hours for the contractor will normally be between the hours of 7:30 a.m. and 4:00 p.m., excluding Saturdays, Sundays, and federal holidays. If the contractor desires to work during periods other than above, additional Government inspection forces may be required. The contractor shall make his/her request to the Contracting Officer three days in advance of his/her intention to work during other periods to allow assignment of additional inspection forces. If such force is reasonably available, the Contracting Officer may authorize the contractor to perform work during periods other than normal duty hours/days. However, if inspectors are required to perform in excess of their normal duty hours/days solely for the benefit of the contractor, the actual cost of inspection at overtime rates will be charged to the contractor. These adjustments to the contract price may be made periodically as directed by the Contracting Officer.
1.8 CONSTRUCTION PROGRESS SCHEDULE
The contractor shall prepare and submit to the Contracting Officer for approval prior to construction beginning a Construction Progress Schedule, AF IMT 3064, showing the order in which the contractor proposes to perform the work. The schedule shall separate the work into phases developed in cooperation with the Government. The schedule shall include the dates on which the contractor contemplates starting and completing the salient elements of the work. The contractor shall also specifically identify on each Contract Progress Report, AF IMT 3065, any apparent, anticipated or proposed deviation from the previously approved schedule.
1.9 REFERENCE STANDARDS
1.9.1 Products
For products specified by association or trade standards, comply with requirements of the standard.
1.9.2 Standard Date
The date of the standard is that in effect as of the Request for Proposal date.
SECTION 01 11 00 Page 4
1.10 SAFETY
1.10.1 Regulations
Contractor to comply with all OSHA/NEC/IBC Regulations.
1.10.2 Instructions
Contractor to comply with Minot Air Force Base Instruction (MAFBI) 32-2001, Responsibilities of Base Personnel to Eliminate or Control Fire Hazards.
1.11 TRAFFIC CONTROL
The contractor shall provide all traffic control devices for pedestrian, vehicular and aircraft traffic and will be responsible for maintaining these devices until notified by the Contracting Officer. The contractor's traffic control devices shall comply with MAFB airfield and safety requirements.
1.12 HAULING MATERIALS
The use of base streets for hauling materials will be permitted if the vehicles are equipped with pneumatic tires. The haul route the contractor will take will be determined at the preconstruction conference.
1.13 DRAWINGS AND SPECIFICATIONS
At least one set of specifications and drawings shall be kept at the job site by the contractor's job supervisor or foreman.
1.14 AS-BUILT DRAWINGS
As-Built Drawings shall be prepared and submitted to the Contracting Officer as specified in Section 01 78 39, As-Built Drawings.
1.15 WORK CONDUCT, CORRELATION, EXECUTION, ETC.
1.15.1 Work Performance
Contractor shall conduct all work, including materials distribution in an orderly manner, and shall notify Contracting Officer within two (2) workdays of mobilizing at the job site. Contractor shall confine and limit his personnel to only those areas required for work performance.
All work shall be performed in a neat, orderly fashion, with extreme care exercised to avoid damage to all property in and around project areas.
Any damage caused by the contractor shall be replaced, repaired, or restored to the Contracting Officer's satisfaction at no cost to the Government. Upon completion, all work and storage areas shall be cleaned of all evidence of contractor's debris accumulations. Contractor's proposed work schedule shall be coordinated with the Contracting Officer or his/her designated representative two (2) weeks prior to the start of any work. All work areas shall be barricaded properly for day and nighttime safety warning.
1.15.2 Storage
At close of each day's operations, all materials and equipment shall be moved to the storage area designated by Contracting Officer or his/her designated representative. If contractor should have a storage structure
SECTION 01 11 00 Page 5 or equipment located on base, it shall be removed, and storage area restored to its original condition within seven days after final acceptance of this project.
1.16 SUPERVISION
Provide at least one (1) qualified Project Manager and one (1) on-site Project Superintendent capable of reading, writing, and conversing fluently in the English language. The Project Superintendent shall be on the job site during working hours. The Project Manager must have a minimum 10 years experience as a Project Manager or Superintendent on projects like this contract or similar in size and complexity. The Project Superintendent must have a minimum of 10 years experience as a Superintendent on projects similar in size and complexity.
The Project Manager in this context shall mean the individual with the responsibility for the overall management of the project and the Project Superintendent shall mean the individual with the responsibility for quality and production. Both the Project Manager and Project Superintendent are subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders shall be made the subject of claim for extension of time for excess costs or damages by the Contractor.
Approval of Project Manager and on-site Project Superintendent is required prior to start of construction. Provide resumes for the proposed Project Manager and on-site Project Superintendent describing their experience with references and qualifications to the Contracting Officer for approval. The Contracting Officer reserves the right to interview the proposed Project Manager and on-site Project Superintendent at any time in order to verify the submitted qualifications.
1.17 UTILITIES
Water and electricity required will be furnished by the Government.
1.18 PERMITS
1.18.1 Clearance Work Request
1.18.1.1 AF Form 103
Contractor shall coordinate with appropriate utility locating agencies, including base communications cable maintenance (Item 1 through 15) of AF Form 103, Base Civil Engineering Work Clearance Request. AF Form 103 will be given to the contractor during the pre-construction meeting.
Contractor shall complete and follow all instructions on AF Form 103 before start of work on base. A copy of AF Form 103 instructions will be available to the contractor during the pre-construction meeting.
1.18.1.2 Processing
Before any excavation, alteration, or other construction work is begun, the contractor shall obtain and fully process an AF Form 103, Base Civil Engineering Work Clearance Request. The form requires extensive coordination with several base agencies, including furnishing all locations, detailed information, and sketches regarding any proposed
SECTION 01 11 00 Page 6 excavation(s). Processing a separate request for each planned excavation is required; each phase of processing the form and its attachments shall be completed prior to commencing work involving that phase. The AF Form 103 shall be prominently displayed on the job site at all times for review by the Contracting Officer and/or his or her designated representative. A copy of the signed form shall be submitted to the Contracting Officer and a copy to the project inspector.
1.18.1.3 Scheduling
Contractor shall schedule a meeting time to meet with each utility agency at the work site to locate affected utilities.
1.18.1.4 Maintenance
Contractor shall maintain all marked utilities in the field once they are initially marked by each utility agency. If markings are damaged, contractor shall request new locates and shall give the locating agency 48 hours to perform the new locates. Expenses for time and materials to perform repeat locates shall be borne by the contractor, unless otherwise approved by the Approving Officer. Cost to do the repeat locates will be deducted from the final invoice. Cost will be calculated using the average shop rate of each agency. In cases where utilities were marked late in the year and operations had to be shut down for winter, marked utilities would still have to be maintained by the contractor by placing stakes or transcribing the marks on a drawing. When construction resumes, contractor shall re-mark the site and may request verification of utility locations at no additional cost to him. Off-base utility locates agencies might request additional cost for repeat locates.
1.18.1.5 Request Approval
Clearance request is not valid until signed by the Approving Officer, block 17 of the AF Form 103. Approving Officer will not sign until all locates are marked and all utility locating agencies signatures are on the form. Excavation work shall commence within 30 days after the Approving Officer's signature; otherwise, clearance request is invalid and a new request is required. Notify Contracting Officer immediately if new utilities were installed by others and not marked after all initial locates are made.
1.18.1.6 Utility Protection
The contractor shall safeguard and protect from damage all utilities encountered or uncovered during digging, excavation, and backfilling.
1.18.2 Welding
When any welding, cutting, brazing or use of any open flame device is used, a Welding Permit (AF Form 592) shall be obtained from the Base Fire Department prior to beginning such work.
During such work, a fully charged and operable fire extinguisher, appropriate for the task, shall be provided by the contractor.
1.19 BASE ACCESS
1.19.1 [Enter Appropriate Subpart Title Here] The contractor shall allow a total of 30 minutes processing time to enter or leave Minot Air Force Base (MAFB) installation entry control gates
SECTION 01 11 00 Page 7
(Magic City, Minot or North Gates). This cost shall have been factored into the contractor's bid price.
1.20 SECURITY REQUIREMENTS
1.20.1 Base Regulations
All activities of the contractor and his employees shall be conducted in strict accordance with Minot AFB Security Regulations. Copies of these regulations will be furnished to the contractor upon request.
1.20.2 Identification of Employees
The contractor will submit to the Contracting Officer a Personnel Listing in three copies with each employee's name, address, SSN, home and business phone numbers, date and place of birth, and name, address and telephone number of the firm that will be working at the construction site. This listing must be provided no-later-than the date of the preconstruction conference. Changes to the list will take place prior to employees arriving at the job site. Each employee shall have two forms of identification to be permitted entry into the job site. One form of identification shall have a picture.
1.21 SANITARY FACIITIES
The contractor shall provide a portable sanitary facility at no cost to the Government.
1.22 BUILDING INFORMATION CHECKLIST
The contractor shall provide the Contracting Officer with a completed Building Information Checklist meeting the requirements of UFC 1-300-08 , Criteria For Transfer And Acceptance of DoD Real Property upon close out of the project that identifies all real property incorporated into the project construction. Real property is defined as land and improvements to land (i.e., facilities). It includes equipment affixed and built into the facility as an integral part of the facility (such as heating systems), but not movable equipment (e.g., plant equipment, industrial equipment, buoys). In many instances this term is synonymous with real estate.
1.23 RADIOACTIVE MATERIALS
The contractor shall obtain written approval from the Installation Radiological Safety Officer (IRSO), 5 MDOS/SGOJ), to transport, or use temporary storage areas for radioactive material (RAM) on the installation.
Common RAM used on the installation includes soil density gauges and pipe weld x-rays. THe contractor shall submit the following IRSO approval a minimum of 30 days prior to bringing RAM on the installation.
An NRC or Agreement State license. A copy of the Nuclear Regulatory Commission (NRC) Form 241 must be an adjunct to the Agreement State license for those areas of exclusive Federal jurisdiction. For those areas of concurrent or proprietary jurisdiction in an agreement state, then the respective Agreement State license is a valid authorization;
or, a valid US Navy or Veterans Affairs (VA) RAM permit;
or, written certification from Department of Energy (DOE) organizations or DOE prime contractors that they are exempt from NRC
SECTION 01 11 00 Page 8 license requirements.
The IRSO is authorized to suspend unsafe operations involving the use of RAM and contractor operations that violate Air Force instruction (AFI) 40-201, a permit, or Federal regulations until corrective action is taken.
1.24 ASBESTOS AND LEAD PAINT ABATEMENT
The contractor shall abate existing asbestos containing and lead paint materials disturbed by their construction activities to complete the project. Abatement requirements are specified in specification Section 01 57 20, Environmental Protection which includes the requirement for the contractor to accomplish their own hazard material survey of affected work areas.
The contractor is responsible for including in their price proposal abating asbestos containing and lead paint materials either identified in the hazard material report included in the specifications, identified in the drawings or those materials visible during a site visit of the work areas. However, the contractor is not responsible for abating materials not identified in the specification's hazard material report or drawings, or concealed from view during a site visit.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
SECTION 01 11 00 Page 9
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 9 PAGES
QJVF13-0067
Repair Pride Parking Lot Phase 2
01 11 00 SD-01 Preconstruction Submittals
1.8Construction Progress Schedule
1.8Contract Progress Report
1.16Project Manager
1.16Project Superintendent
1.18.1.1Base Civil Engineering Work
Clearance Request
1.20.2Personnel Listing
Welding Permit
Radioactive Materials
SD-11 Closeout Submittals
1.22Building Information Checklist
01 33 00 SD-01 Preconstruction Submittals
1.3Submittal Form, Submittal
Register
01 45 00.10 20 SD-01 Preconstruction Submittals
1.4.1QC Manager
1.5QC Plan
01 57 20 SD-01 Preconstruction Submittals
1.2Environmental Pollution Control
Proposal
1.4Preconstruction Survey
1.8.1.1.2Storm Water Pollution Prevention
Plan
1.8.1.1.3Notice Of Intent
1.10.1.2Asbestos Survey Report
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 9 PAGES
Repair Pride Parking Lot Phase 2
01 57 20 1.10.1.3Notification Of Demolition And
Renovation
1.10.2.1Lead Based Paint Survey Report
1.11Hazardous Materials
Authorization Information
1.12.2Recycled Content Report
1.15.6Waste Disposal Plan
SD-07 Certificates
Shipping Manifest
Certificate of Destruction
1.11.3Hazardous Material Usage Data
1.13.2C&D Report
1.15.4.5Disposal Documents And Weight
Tickets
1.15.5Solid Waste Diversion Report
SD-11 Closeout Submittals
1.11.5Hazardous Material Usage Data
Final Report
01 78 00 SD-03 Product Data
1.3.1Warranty Management Plan
1.3.4Warranty Tags
SD-08 Manufacturer’s Instructions
1.3.1Instructions
SD-10 Operation and Maintenance
Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 9 PAGES
Repair Pride Parking Lot Phase 2
01 78 00 Operation and Maintenance
Manuals
01 78 39 SD-03 Product Data
1.4.250 Percent Preliminary As-Built
Drawings
1.4.3100 Percent Preliminary As-Built
Drawings
SD-11 Closeout Submittals
1.4.4Final As-Built Drawings
26 05 00.00 40 SD-01 Preconstruction Submittals
2.1Material, Equipment, and Fixture
Lists
SD-03 Product Data
2.1.1Conduits and Raceways
2.1.2Wire and Cable
3.2.1.3Splices and Connectors
2.1.3Receptacles
2.1.4Outlets, Outlet Boxes, and Pull
Boxes
2.1.5Circuit Breakers
2.1.6Lamps and Lighting Fixtures
SD-06 Test Reports
3.3Continuity Test
3.3Insulation Resistance Test
SD-07 Certificates
1.4Certification
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 4 OF 9 PAGES
Repair Pride Parking Lot Phase 2
26 05 00.00 40 SD-08 Manufacturer’s Instructions
Part 2Manufacturer's Instructions
26 05 19.00 10 SD-03 Product Data
3.1Installation Instructions
SD-06 Test Reports
3.2Tests, Inspections, and
Verifications
26 05 71.00 40 SD-02 Shop Drawings
1.3Connection Diagrams
1.3Fabrication Drawings
3.1Control Devices
3.1Protective Devices
SD-03 Product Data
2.1Enclosures
2.2Circuit Breakers
3.1Control Devices
SD-08 Manufacturer’s Instructions
3.1Control Devices
3.1Protective Devices
SD-10 Operation and Maintenance
Data
2.2Circuit Breakers
26 56 00 SD-01 Preconstruction Submittals
1.4.2 GPhotometric Plan
1.6.1 GLED Luminaire Warranty
SD-02 Shop Drawings
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 5 OF 9 PAGES
Repair Pride Parking Lot Phase 2
26 56 00 1.4.1.1 GLuminaire drawings
1.4.1.2 GPoles
SD-03 Product Data
2.1 GLED Luminaires
GLuminaire Power Supply Units
(Drivers)
GLighting contactor
GSteel poles
SD-04 Samples
2.1 GLED Luminaires
SD-05 Design Data
1.4.3 GDesign Data for luminaires
SD-06 Test Reports
1.4.4 GLED Luminaire - IES LM-79 Test
Report
1.4.5 GLED Light Source - IES LM-80
Test Report
3.2Operating test
SD-07 Certificates
1.6.1 GLuminaire Useful Life Certificate
SD-10 Operation and Maintenance
Data
1.7Operational Service
26 56 13.00 40 SD-02 Shop Drawings
1.4.1.1 GPoles
1.4.4 GPoles
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 6 OF 9 PAGES
Repair Pride Parking Lot Phase 2
26 56 13.00 40 1.4.4Installation Details
SD-03 Product Data
GSteel poles
2.3 GBrackets
1.4.4 GAnchorage Systems
SD-05 Design Data
2.1LIGHTING STANDARDS
1.4.4 GManufacturer's Catalog Data
1.4.4 GFactory Color Finish
1.4.4 GMaterial Safety Data Sheets
SD-07 Certificates
1.4.4sustainable acquisition
SD-08 Manufacturer’s Instructions
1.4.4 GFoundation requirements
1.4.3 Gmounting details
SD-10 Operation and Maintenance
Data
1.7 GOperational Service
SD-11 Closeout Submittals
1.4.4 GWarranty
3.5.6 Grecord drawings
26 56 23.00 40 SD-02 Shop Drawings
1.4.1.1 GLuminaire drawings
SD-03 Product Data
1.6.1Energy Efficiency
2.1 GLuminaires
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 7 OF 9 PAGES
Repair Pride Parking Lot Phase 2
26 56 23.00 40 SD-04 Samples
2.1 GLuminaires
SD-05 Design Data
1.4.2 GDesign Data for luminaires
SD-06 Test Reports
3.2Operating test
SD-08 Manufacturer’s Instructions
2.1Mounting Details
SD-10 Operation and Maintenance
Data
1.8Operational Service
32 11 23 SD-06 Test Reports
1.5Sampling and Testing
1.5.2.4Field Density Tests
32 12 16 SD-03 Product Data
2.3Mix Design
3.10Contractor Quality Control
3.11Material Acceptance
1.1.2Percent Payment
SD-06 Test Reports
2.1Aggregates
3.10.3.10QC Monitoring
SD-07 Certificates
2.2Asphalt Cement Binder
3.6Testing Laboratory
32 16 13 SD-03 Product Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 8 OF 9 PAGES
Repair Pride Parking Lot Phase 2
32 16 13 2.1Concrete
SD-06 Test Reports
3.8Field Quality Control
32 17 24.00 10 SD-03 Product Data
1.2Equipment
1.4.1Qualifications
SD-06 Test Reports
2.2Sampling and Testing
32 92 19 SD-03 Product Data
2.4.3Wood cellulose fiber mulch
2.3.1Fertilizer
SD-06 Test Reports
2.2.3Topsoil composition tests
SD-07 Certificates
2.1.1seed
SD-08 Manufacturer’s Instructions
2.6Erosion Control Materials
33 11 00 SD-03 Product Data
2.1.1Piping Materials
2.1Water distribution main
Water service line
2.1.2.2Hydrants
2.1.2.3Indicator posts
2.1.2.4Valve boxes
SD-05 Design Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 9 OF 9 PAGES
Repair Pride Parking Lot Phase 2
33 11 00 1.2.1Design calculations of water piping
SD-06 Test Reports
2.2.2.1Disinfection
SD-07 Certificates
2.1Water distribution main
2.1.1.1lining
2.1.1.1lining
2.1.1.2lining
2.1.1.2lining
2.1.2.2hydrants
SD-08 Manufacturer’s Instructions
3.1.1Installation
33 40 00 SD-03 Product Data
3.3Placing Pipe
SD-04 Samples
2.1Pipe for Culverts and Storm
Drains
SD-07 Certificates
3.7Pipeline Testing
2.5Hydrostatic Test on Watertight
Joints
3.6.5Determination of Density
2.3.3Frame and Cover for Gratings
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
02/14
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 Submittal Descriptions (SD)
1.2 SUBMITTALS
1.3 PROCEDURES
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 33 00 Page 1
SECTION 01 33 00
SUBMITTAL PROCEDURES
02/14
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals
Submittals which are required prior to start of construction (work) to include:
Section 01 11 00 GENERAL REQUIREMENTS Preconstruction Submittals
SEction 01 14 00 WORK RESTRICTIONS Preconstruction Submittals
Section 01 45.00 10 20 QUALITY CONTROL FOR MINOR CONSTRUCTION Preconstruction Submittals
Section 01 57 20 ENVIRONMENTAL PROTECTION Preconstruction Submittals
Preconstruction Submittals specified in other specification sections
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-04 Samples
Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by
SECTION 01 33 00 Page 2 which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD-05 Design Data
Design calculations, mix designs, analyses or other data pertaining to a part of work.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Confined space entry permits.
Text of posted operating instructions.
SD-08 Manufacturer's Instructions
Preprinted material describing installation of a product, system or material, including special notices and (MSDS)concerning impedances, SECTION 01 33 00 Page 3 hazards and safety precautions.
SD-10 Operation and Maintenance Data
Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.
This data is intended to be incorporated in an operations and maintenance manual or control system.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
1.2 SUBMITTALS
Submit the following in accordance with this section.
SD-01 Preconstruction Submittals
Submittal Form, Submittal Register
1.3 PROCEDURES
Submittal procedures are as follows:.
1.3.1 The contractor shall be required to submit items listed in Submittal Form, Submittal Register.
1.3.2 Transmit each item under AF 3000, Material Approval Submittal form. Identify contract number, project number, and contractor.
Identify section and paragraph reference for each item submitted with the AF 3000. Submit five (5) copies unless otherwise required elsewhere in the specification.
1.3.3 Unless specifically stated otherwise elsewhere in this
specification, each submittal shall be approved by the Contracting Officer prior to incorporation of materials into the work.
1.3.4 The contractor shall allow for ten (10) working days for the Government to review a submittal.
1.3.5 All SD-01 PReconstruction Submittals shall be approved by the Contracting Officer prior to the contractor mobilizing to the work site.
1.3.6 Approvals of submittals which do not conform to the Contract shall not be construed as a change to the contract.
1.3.7 The contractor shall fill in the "Required Submission Date" on
SECTION 01 33 00 Page 4 the Submittal Form, Submittal Register with the date he plans on submitting the submittals to the Government. A copy of the Submittal Register with the required submission date filled in shall be submitted to the Contracting Officer for use by the contract administrator.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
SECTION 01 33 00 Page 5
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 42 00
SOURCES FOR REFERENCE PUBLICATIONS
08/10
PART 1 GENERAL
1.1 REFERENCES
1.2 ORDERING INFORMATION
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 42 00 Page 1
SECTION 01 42 00
SOURCES FOR REFERENCE PUBLICATIONS
08/10
PART 1 GENERAL
1.1 REFERENCES
Various publications are referenced in other sections of the specifications to establish requirements for the work. These references are identified in each section by document number, date and title. The document number used in the citation is the number assigned by the standards producing organization (e.g. ASTM B564 Standard Specification for Nickel Alloy Forgings). However, when the standards producing organization has not assigned a number to a document, an identifying number has been assigned for reference purposes.
1.2 ORDERING INFORMATION
The addresses of the standards publishing organizations whose documents are referenced in other sections of these specifications are listed below, and if the source of the publications is different from the address of the sponsoring organization, that information is also provided. Documents listed in the specifications with numbers which were not assigned by the standards producing organization should be ordered from the source by title rather than by number.
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO)
444 North Capital Street, NW, Suite 249 Washington, DC 20001 Ph: 202-624-5800 Fax: 202-624-5806 E-Mail: info@aashto.org Internet: http://www.aashto.org
AMERICAN WATER WORKS ASSOCIATION (AWWA)
6666 West Quincy Avenue Denver, CO 80235 Ph: 800-926-7337 Fax: 303-347-0804 E-mail: smorrison@awwa.org Internet: http://www.awwa.org
ASTM INTERNATIONAL (ASTM)
100 Barr Harbor Drive, P.O. Box C700 West Conshohocken, PA 19428-2959 Ph: 610-832-9585 Fax: 610-832-9555 E-mail: service@astm.org Internet: http://www.astm.org
ILLUMINATING ENGINEERING SOCIETY OF NORTH AMERICA (IES)
120 Wall Street, 17th Floor New York, NY 10005 Ph: 212-248-5000
SECTION 01 42 00 Page 2
Fax: 212-248-5018 E-mail: IES@IES.org Internet: http://www.IES.org
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
445 Hoes Lane or 2001 L Street, NW. Suite 700 Piscataway, NJ 08855-1331 or Washington, DC 20036-4910 USA Ph: 732-981-0060 or 800-701-4333 Fax: 732-562-6380 E-mail: onlinesupport@ieee.org or ieeeusa@ieee.org Internet: http://www.ieee.org
INTERNATIONAL ORGANIZATION FOR STANDARDIZATION (ISO)
1, ch. de la Voie-Creuse Case Postale 56 CH-1211 Geneve 20 Switzerland Ph: 41-22-749-01-11 Fax: 41-22-733-34-30 E-mail: central@iso.ch Internet: http://www.iso.org
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
1300 North 17th Street, Suite 1752 Rosslyn, VA 22209 Ph: 703-841-3200 Fax: 703-841-5900 Internet: http://www.nema.org/
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
1 Batterymarch Park Quincy, MA 02169-7471 Ph: 617-770-3000 or 800-344-3555 Fax: 617-770-0700 E-mail: webmaster@nfpa.org Internet: http://www.nfpa.org
UNDERWRITERS LABORATORIES (UL)
2600 N.W. Lake Road Camas, WA 98607-8542 Ph: 877-854-3577 Fax: 360-817-6278 E-mail: CEC.us@us.ul.com Internet: http://www.ul.com/ UL Directories available through IHS at http://www.ihs.com
U.S. ARMY CORPS OF ENGINEERS (USACE)
Order CRD-C DOCUMENTS from:
U.S. Army Engineer Waterways Experiment Station ATTN: Technical Report Distribution Section, Services Branch, TIC 3909 Halls Ferry Road Vicksburg, MS 39180-6199 E-mail: MTC-INFO@erdc.usace.army.mil Internet:
http://gsl.erdc.usace.army.mil/SL/MTC/handbook/handbook.htm Order Other Documents from:
USACE Publications Depot Attn: CEHEC-IM-PD 2803 52nd Avenue Hyattsville, MD 20781-1102
SECTION 01 42 00 Page 3
Ph: 301-394-0081 Fax: 301-394-0084 E-mail: pubs-army@usace.army.mil Internet: http://www.usace.army.mil/publications or http://www.hnc.usace.army.mil/Missions/Engineering/TECHINFO.aspx
U.S. DEPARTMENT OF AGRICULTURE (USDA)
Order AMS Publications from:
AGRICULTURAL MARKETING SERVICE (AMS)
Seed Regulatory and Testing Branch 801 Summit Crossing Place, Suite C Gastonia, NC 28054-2193 Ph: 704-810-8871 Fax: 704-852-4189 E-mail: seed.ams@usda.gov Internet: http://www.ams.usda.gov/lsg/seed.htm Order Other Publications from:
U.S. Department of Agriculture, Rural Utilities Service 14th and Independence Avenue, SW, Room 4028-S Washington, DC 20250 Ph: 202-720-2791 Fax: 202-720-2166 Internet: http://www.usda.gov/rus
U.S. DEPARTMENT OF DEFENSE (DOD)
Order DOD Documents from:
Room 3A750-The Pentagon 1400 Defense Pentagon Washington, DC 20301-1400 Ph: 703-571-3343
FAX: 215-697-1462
E-mail: pia@hq.afis.asd.mil Internet: http://www.dod.gov Obtain Military Specifications, Standards and Related Publications from:
Acquisition Streamlining and Standardization Information System
(ASSIST)
Department of Defense Single Stock Point (DODSSP) Document Automation and Production Service (DAPS) Building 4/D 700 Robbins Avenue Philadelphia, PA 19111-5094 Ph: 215-697-6396 - for account/password issues Internet: http://assist.daps.dla.mil/online/start/ ; account registration required Obtain Unified Facilities Criteria (UFC) from:
Whole Building Design Guide (WBDG) National Institute of Building Sciences (NIBS) 1090 Vermont Avenue NW, Suite 700 Washington, CD 20005 Ph: 202-289-7800 Fax: 202-289-1092 Internet: http://www.wbdg.org/references/docs_refs.php
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
Ariel Rios Building 1200 Pennsylvania Avenue, N.W.
Washington, DC 20004 Ph: 202-272-0167
SECTION 01 42 00 Page 4 for Fax and E-mail see below Internet: http://www.epa.gov --- Some EPA documents are available only from:
National Technical Information Service (NTIS) 5301 Shawnee Road Alexandria, VA 22312 Ph: 703-605-6050 or 1-688-584-8332 Fax: 703-605-6900 E-mail: info@ntis.gov Internet: http://www.ntis.gov
U.S. GENERAL SERVICES ADMINISTRATION (GSA)
General Services Administration 1800 F Street, NW Washington, DC 20405 Ph: 202-501-0800 Internet: www.GSA.gov Obtain documents from:
Acquisition Streamlining and Standardization Information System
(ASSIST)
Department of Defense Single Stock Point (DODSSP) Document Automation and Production Service (DAPS) Building 4/D 700 Robbins Avenue Philadelphia, PA 19111-5094 Ph: 215-697-6396 - for account/password issues Internet: http://assist.daps.dla.mil/online/start/ ; account registration required
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
8601 Adelphi Road College Park, MD 20740-6001 Ph: 866-272-6272 Fax: 301-837-0483 E-mail: contactcenter@gpo.gov Internet: http://www.archives.gov Order documents from:
Superintendent of Documents U.S.Government Printing Office (GPO) 732 North Capitol Street, NW Washington, DC 20401 Ph: 202-512-1800 Fax: 202-512-2104 E-mail: contactcenter@gpo.gov Internet: http://www.gpoaccess.gov
PART 2 PRODUCTS
Not used
PART 3 EXECUTION
Not used
-- End of Section --
SECTION 01 42 00 Page 5
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 45 00.10 20
QUALITY CONTROL FOR MINOR CONSTRUCTION
02/14
PART 1 GENERAL
1.1 SUBMITTALS
1.2 INFORMATION FOR THE CONTRACTING OFFICER (CO)
1.3 QC PROGRAM REQUIREMENTS
1.3.1 Preliminary Work Authorized Prior to Acceptance
1.3.2 Acceptance
1.3.3 Notification of Changes
1.4 QC ORGANIZATION
1.4.1 QC Manager
1.4.1.1 Duties
1.4.1.2 Qualifications
1.4.2 Alternate QC Manager Duties and Qualifications
1.5 QC PLAN
1.5.1 Requirements
1.6 COORDINATION AND MUTUAL UNDERSTANDING MEETING
1.7 QC MEETINGS
1.8 THREE PHASES OF CONTROL
1.8.1 Preparatory Phase
1.8.2 Initial Phase
1.8.3 Follow-Up Phase
1.8.4 Additional Preparatory and Initial Phases
1.8.5 Notification of Three Phases of Control for Off-Site Work
1.9 SUBMITTAL REVIEW AND APPROVAL
1.10 TESTING
1.10.1 Accreditation Requirements
1.10.2 Laboratory Accreditation Authorities
1.10.3 Capability Check
1.10.4 Test Results
1.11 QC CERTIFICATIONS
1.11.1 Contractor Quality Control Report Certification
1.11.2 Invoice Certification
1.11.3 Completion Certification
1.12 COMPLETION INSPECTIONS
1.12.1 Punch-Out Inspection
1.12.2 Pre-Final Inspection
1.12.3 Final Acceptance Inspection
1.13 DOCUMENTATION
1.13.1 Quality Control Validation
1.13.2 As-Built Drawings
1.14 NOTIFICATION ON NON-COMPLIANCE
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 45 00.10 20 Page 1
-- End of Section Table of Contents --
SECTION 01 45 00.10 20 Page 2
SECTION 01 45 00.10 20
QUALITY CONTROL FOR MINOR CONSTRUCTION
02/14
PART 1 GENERAL
1.1 SUBMITTALS
The following shall be submitted in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
QC Manager QC Plan
Submit a QC plan within 15 calendar days after receipt of Notice of Award.
1.2 INFORMATION FOR THE CONTRACTING OFFICER (CO)
Prior to commencing work on construction, the Contractor can obtain a single copy set of the current report forms from the CO. The report forms will consist of the Contractor Production Report, Contractor Production Report (Continuation Sheet), Contractor Quality Control (CQC) Report, CQC Report (Continuation Sheet), Preparatory Phase Checklist, Initial Phase Checklist, Rework Items List, and Testing Plan and Log.
Deliver the following to the CO:
a. CQC Report: Original and one copy, by 10:00 AM the next working week after each week that work is performed;
b. Contractor Production Report: Original and one copy by 10:00 AM the next working week after each week that work is performed;
c. Preparatory Phase Checklist: Original attached to the original CQC Report and one copy attached to each copy;
d. Initial Phase Checklist: Original attached to the original CQC Report and one copy attached to each copy;
e. Field Test Reports: One copy, within the week after the test is performed, attached to the CQC Report;
f. QC Meeting Minutes: One copy, within the week after the meeting; and
g. QC Certifications: As required by the paragraph entitled "QC Certifications."
1.3 QC PROGRAM REQUIREMENTS
Establish and maintain a QC program as described in this section. The QC program consists of a QC Manager, a QC plan, a Coordination and Mutual Understanding Meeting, QC meetings, three phases of control, submittal review and approval, testing, and QC certifications and documentation
SECTION 01 45 00.10 20 Page 3 necessary to provide materials, equipment, workmanship, fabrication, construction and operations which comply with the requirements of this contract. The QC program shall cover on-site and off-site work and shall be keyed to the work sequence. No work or testing may be performed unless the QC Manager is on the work site.
1.3.1 Preliminary Work Authorized Prior to Acceptance
The only work that is authorized to proceed prior to the acceptance of the QC plan is mobilization of storage and office trailers, temporary utilities, and surveying.
1.3.2 Acceptance
Acce…