Attachment_8_-_Contractor_Q A.docx

DOCX document 15 KB Posted

Attached to
Repair PRIDE Parking Lot Federal contract opportunity
Solicitation number
FA4528-15-R-0014
Issued by
Department of the Air Force Global Strike Command

About this file

Attachment 8 - Contractor Q A

View the file

Other files for this federal contract opportunity

Other files attached to Repair PRIDE Parking Lot, newest first.
File Type Posted
Contractor_Q A_-_15_May_15.docx DOCX document
SF_30_-_Add_Attachments.doc DOC document
Attachment_7_-_Revised_SOW_ _Drawings.pdf PDF
Attachment_2_Drawings.pdf PDF
15-R-0014_Repair_Pride_Parking_Lot.doc DOC document
Attachment_3_DB_Wage_Rates_ND_150002.pdf PDF
Attachment_5_Financial_Responsibility.docx DOCX document
Attachment_6_Detailed_Construction_Breakdown.xlsx XLSX spreadsheet
Attachment_4_Past_Performance_Questionnaire.docx DOCX document
Attachment_1_Specifications.pdf PDF
Draft01_Specifications.pdf PDF
Draft02_Drawings.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 May 2015

QJVF 13-0067

Repair PRIDE Parking Lot – FA4528-15-R-0014

Q1 - Please provide clarification as to what is required for aggregate base course beneath the pavement. Specification 32 11 23 lists several requirements and also state that it shall meet NDDOT Class 5. The plans also discuss using salvaged base as an alternate. Some of these specifications contradict each other.

A1 – The aggregate base course shall meet NDDOT Class 5 requirements. Salvage base course will not be accepted as an alternate on this project. Please, see Amendment No. 1.

Q2 - Please clarify density requirements for aggregate base course. Specification 32 11 23 states 100% and plans show 95% standard proctor.

A2 – Sheet G-002 of the plans has been updated to reflect the correct density requirements for the aggregate base course. Please, see Amendment No. 1 The 100% standard proctor, specified, has been reflected in the plans.

Q3 - Please provide a typical section for the full depth pavement section, clarifying the subgrade requirements beneath the pavement.

A3 – Typical sections details shown on Sheet C-501 and Sheet C-502 have been updated to reflect the full-depth pavement section to include the depth and type of base course. Sheet G-002 has been updated to include the subgrade requirements and compaction requirements. Subgrade shall meet the requirements of the City of Minot 2013 Standard Specification and shall be compacted to 100% standard proctor, as indicated on revised Sheet G-002. Please, see Amendment No. 1.

Q4 - Spec Section 32 12 16 - This specification is for Superpave FAA 43. There are several items listed which are not consistent with superpave such as stability, flow, and natural sand content.

A4 – Superpave FAA 43 shall be used and shall comply with the requirements of the NDDOT Standard Specifications. Where conflicts arise, the NDDOT Specifications shall govern. Where ambiguities are present, the NDDOT Standard Specifications shall be followed. Please, see Amendment No. 1.

Q5 - Spec Section 32 12 16 - Specification does not list density requirements except for the Test Section. Please clarify.

A5 – The density requirements have been included in the revised specification Section 32 12 16 included in Amendment No. 1. Please, see Amendment No.1.

Q6 - Spec Section 32 12 16 Paragraph 3.9.2 - Longitudinal Joints - Spec states that cold joints are to be cut back. This requirement seems excessive for a parking lot. Please verify that this will be required.

A6 – As indicated in the specifications, the item will be required.

Q7 - Please provide a cross section for the Asphalt Dumpster Pads.

A7 – Sheet C-501 and Sheet C-Cp-100 have been updated to reflect the cross section for the Asphalt Dumpster Pads. Please, see Amendment No. 1