8. REC SOW Construct B1196.pdf

PDF 222 KB Posted

Attached to
Construct Two, Single-Bay Munitions Storage Facilities
Solicitation number
FA4497-25-SOURCES-SOUGHT-ECM
Issued by

About this file

This is a Statement of Work (SOW) for a Regional Engineering and Construction Contract (RE&C) to construct a new Earth Covered Magazine (ECM) facility designated as B1196 at Dover Air Force Base, Delaware, under project number FJXT1200027. The SOW outlines requirements for a design-bid-build (DBB) construction project.

The contractor must provide complete construction and warranty services for the new munitions facility, including concrete access pavement, communications, security systems, equipment, and utilities. Key requirements include developing a Construction Work Plan, Accident Prevention Plan, Quality Control Plan, and establishing a Data Collaboration Site for project documentation. The contractor must provide key personnel including a Project Manager, Site Superintendent, CQC Manager, and Site Safety and Health Officer. The work involves site preparation, construction operations, environmental protection measures, and hazardous materials handling. The project schedule must account for anticipated weather conditions at Dover AFB, with specific requirements for material submittal reviews (10 business days standard, 15 business days during holiday periods). The contractor must conduct inspections, provide photo documentation, and deliver as-built documentation in CADD, BIM and PDF formats prior to final payment.

View the file

Other files

File Type Posted
Sources Sought B1196 ECM.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

9 Oct 2024

BASIC CONTRACT

STATEMENT OF WORK

For

REGIONAL ENGINEERING AND CONSTRUCTION CONTRACT (RE&C)

EAST REGION

CONSTRUCT MUNITIONS FACILITY, B1196

AT

Dover AFB, DE

FOR PROJECT NUMBER(S):

FJXT1200027

1.0 SCOPE

This Basic Contract Statement of Work (SOW) defines the scope of a full range of construction and engineering activities necessary to meet Air Force and other customer requirements for the Regional Engineering and Construction Contract (RE&C). This basic contract SOW describes the requirements necessary to complete the design-bid-build (DBB) construction requirements for an RE&C Acquisition Task Order (TO) which describes this DBB construction effort at Dover Airforce Base (AFB). The RE&C Contractor is to provide the Government with a complete construction and warranty in accordance with FAR 52.246-21 to construct a new Earth Covered Magazine (ECM).

All work shall be accomplished in accordance with (IAW) the contract specifications, drawings, and as directed by the Contracting Officer (CO).

This TO will utilize the following Base Bid Items:

Base Bid Item 1 – Construct new Munitions Facility, B1196: Construct a new Earth Covered Magazine (ECM) to include concrete access pavement, communications, security systems, equipment, and utilities.

This SOW encompasses the full range of methods, technologies, and supporting activities necessary to conduct project construction at Dover AFB. Air Force installations and other locations within the United States in accordance with technical and regulatory requirements.

The Contractor shall function as an integral team member in support of the Air Force and other customer missions, to include sharing information with other Contractors and cooperation with communities and other Government entities.

Requirements include efficient management including, but not limited to, the submission of accurate, on-time, quality contract deliverables and timely identification and solution of impediments to successful project execution. The Government will rely on the Contractor’s expertise in recognizing and addressing problematic issues and successful execution of this TO.

The Contractor shall perform all work in accordance with federal, state, and local statutes and regulations.

2.0 APPLICABLE DOCUMENTS

The Contractor shall identify and comply with all applicable federal, state, and local laws; statutes;

Executive Orders; Department of Defense/Air Force manuals, handbooks, regulations, guidance, and policies and includes all changes and amendments in effect on the date of issuance of this task order. The Contractor shall comply with the National Institute of Building Sciences’ Whole Building Design Guide Construction Criteria Base (CCB) Unified Facility Criteria (UFC) and all of the related libraries. It is the Contractor’s responsibility to identify and comply with all applicable requirements.

In addition, the Contractor shall refer to and comply with the current versions of the Department of Defense Policy and Guidelines for Acquisitions Involving Environmental Sampling or Testing and base-specific documents identified herein.

3.0 GOVERNMENT PROPERTY INCLUDING GOVERNMENT FURNISHED

INFORMATION, EQUIPMENT, AND PROPERTY (GFI, GFE, GFP)

FAR 52.245-1 defines Government Property and the procedures for accounting for and disposition of property.

To the extent it is available, the Government will provide information in the form of available plans, reports, maps, drawings, and as-built drawings as necessary to facilitate accomplishment of the work required in the task order SOW. However, these GFIs show conditions as they existed at the completion of the 100% design. The Contractor shall verify (by field investigation) information shown on all GFIs (relevant to the project) for accuracy to ensure a quality project. The Contractor shall document findings of the site survey in a Site Survey Report (SSR). The Contractor shall identify any discrepancies between conditions described by the contract and actual on-site conditions. (Contract Data Requirements List [CDRL] A015) The Contractor shall review the following for specifics provided:

Appendix A – DOVER AFB ECM B1196 IFC Drawings Appendix B – DOVER AFB ECM B1196 IFC Specifications Appendix C – DOVER AFB ECM B1196 Final Geotechnical Report

4.0 MANAGEMENT, PLANNING, AND REPORTING REQUIREMENTS

The Contractor shall implement a full range of construction and engineering activities as specified in each TO and in accordance with all applicable compliance documents. The Contractor shall supply all labor, equipment, and materials necessary to accomplish the work assigned unless otherwise specified in each TO. The Contractor shall perform management and planning functions, including performance measurement and status reporting to effectively secure and monitor prime and sub-contract work, as required.

4.1. Work Breakdown Structure (WBS)

The WBS shall be consistent with the Construction Specifications Institute (CSI) current format for construction activities, and be delivered in .xer format with the Project Schedule, consistent with Specification Section 01 32 01.00 10.

4.2. Schedule and Planning Requirements

The Contractor shall provide schedules for tracking work progress.

4.2.1. Project Planning Chart (PPC) and/or Construction Planning Chart (CPC)

Not Applicable to this TO.

4.2.2. Integrated Master Schedule (IMS)

Within 15 calendar days after contract award, submit the Preliminary IMS and AF Forms 3064/3065 for approval or as otherwise directed by the CO for Government review, evaluation, and approval on an AF Form 3000. The IMS shall be prepared and submitted in Primavera P6 and

.pdf formats and shall be based on the schedule presented in the Contractor’s accepted proposal.

Compliance with contract Specification Section 01 32 01.00 10 PROJECT SCHEDULE is required. The AF Form 3064/3065 shall be derived from the IMS and be structured by major CSI divisions and assigned appropriate value in relationship to overall work and contract value. Within 42 calendar days after contract award submit the Initial Project Schedule for approval. The Initial IMS shall include an advanced level of detail and include all necessary activities, tasks, and subtasks to reflect all remaining construction activities that may have been omitted or highly summarized in the Preliminary IMS. The schedule must provide 10 business days for review and approval of construction material submittals. The Contractor shall allow an additional 5 business days for review and approval of construction material submittals that are delivered to the Government anytime between the Monday before Thanksgiving Day through New Year’s Day.

The Initial IMS, and revised AF Form 3064/3065 shall be provided by the Contractor on an AF Form 3000 and approved by the Government before a full Notice to Proceed (NTP) will be issued by the CO. (CDRL B003) The project schedule calendar must reflect the anticipated adverse weather delays and weather sensitive activities. Weather information is provided in the chart below regarding average temperature, rainfall, and snowfall for Dover AFB

Averages for Dover AFB

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Avg. High (°F) 43 47 55 66 75 83 87 85 79 69 58 47

Avg. Low (°F) 27 29 36 44 54 63 68 67 60 49 40 31 Avg. Rainfall/ snowfall (Inches)

1.46/ 1.65

1.89/ 0.91

2.13

1.54 1.77 2.4 2.64 2.91 3.15 1.89 2.2 1.77 2.09/

0.51

Source: www.weather-us.com

4.3. Status Reporting

4.3.1. Reporting Requirements for Firm Fixed Price (FFP)

Firm Fixed Price TOs are limited to status reports, project schedules, and invoices.

4.3.1.1. Contractor’s Progress, Status, and Management Report (CPSMR)

Submit monthly Contractor’s Progress, Status, and Management Report (CPSMR), progress updated project schedule, invoices derived from the approved cost loaded project schedule, and AF Forms 3064/3065. The monthly status report shall be submitted NLT the 15th calendar day of the following month and shall include a summary of events that occurred during the reporting period, discussion of performance, identification of problems, proposed solutions, corrective actions taken, and outstanding issues. (CDRL B004)

4.4. Meeting and Conference Requirements

4.4.1. Meeting/Teleconference Support

Attend meetings necessary to support the construction activities, etc. The Contractor also shall attend and support weekly meetings and/or teleconferences. Prepare and maintain the weekly meeting report which shall include the record of new and old discussion of technical issues, weekly earned value progress showing percent complete actual versus plan, tabular report of late tasks derived from the progress updated project schedule, a three week look ahead, and tabular report for RFIs and submittals (open and upcoming).

Prepare, and submit for review presentation materials and an agenda three (3) business days prior to scheduled meetings. Prepare minutes for all meetings attended, including teleconferences, and Red Zone Meetings, and distribute meeting minutes to attendees within two (2) business days following meetings. (CDRLs B005, B006, B007)

4.4.2. Red Zone Meeting

The Contractor shall support “Red Zone Meetings” as part of the closeout of the project. The “Red Zone” shall commence at 80-percent of construction completion. At this meeting, the Contractor and the project stakeholders shall discuss, define, and achieve consensus on actions necessary to complete construction and support user occupancy. (CDRLs B005, B006, B007)

4.4.3. Senior Advisory Group (SAG) and Senior Executive Review Group (SERG)

Not Applicable to this TO.

4.4.4. Airfield Workshop(s)

Not Applicable to this TO.

4.5. Contractor Documentation

Create and maintain a Master Document List (MDL) that includes all documents prepared during the performance of the TO, whether the documents are a deliverable or not. The MDL will contain the material and data submittal register, contract progress/status reports and daily construction log documentation. Maintain the MDL and its documents in libraries readily available for submittal to the Government. The Government requires 10 business days for review and approval of submittals.

Allow an additional 5 business days for review and approval of construction material submittals that are delivered to the Government anytime between the Monday before Thanksgiving Day through New Year’s Day. All Material Submittals shall be accomplished in accordance with the instructions pertaining to AF Form 3000, Material Approval Submittal.

4.6. Notification Requirements

The Contractor is required to notify the CO and COR of critical issues that may affect the contract performance and/or human health and the environment. Immediately implement the appropriate safety precautions. Field activities shall not continue until clearance is received from the CO. On critical issues, verbal notification should be made immediately, followed by written notification within 48 hours. (CDRL A001)

4.7. Permits

The Contractor shall develop, coordinate, and apply for and obtain all applicable permits, access (including off-base easements and leases), agreements, licenses, and certificates required to perform and complete the effort as specified. The Contractor shall maintain a library of these documents at the Contractor’s site office as well as the corporate facility. The Contractor shall comply with all applicable permit conditions and shall keep all permits “current” until construction is 100% complete. The Contractor may be required to provide the permits to the Government as required. (CDRL A002)

4.8. Photo Documentation

Prepare digital photo documentation, including site(s) and building(s) under construction, field activities, and sample locations if applicable. Digital photos will be submitted in accordance with specification 01 30 00. Provide an index for each set of photographs submitted, identifying the base or facility, project number, Contractor, and a brief description. Photography of any kind must be coordinated through the installation, customer, or facility POC. Photo documentation shall be loaded to the project website. (CDRL B009)

4.9. Remote and/or Austere Sites

Not Applicable to this TO.

4.10. Site Access Badges

The Contractor shall obtain and monitor assigned security badges or passes (used by both Contractor and subcontractor personnel) for the duration of this contract. All security badges or passes shall be returned to the base POC upon expiration of the badge, upon completion of the project, or when possession of the badge is no longer necessary (e.g., upon removal of Contractor personnel from specific projects).

4.11. Worksite Activities and Coordination

4.11.1. Coordination of Activities

The Contractor shall be responsible for protecting the lives and health of employees and other persons on the work site, preventing damage to property, materials, supplies, and equipment, avoiding work interruptions and complying with Occupational Safety and Health Administration (OSHA) safety and local safety office requirements. The Contractor shall perform all operations in a prudent, conscientious, safe and professional manner and conform to the safety requirements contained in the contract for all activities related to the accomplishment of the work. The Contractor shall maintain documentation supporting training records on site and have written Health and Safety Plans on site and available for workers and/or regulatory review. The Contractor shall provide the CO copies of any OSHA report(s), regarding a project site, submitted during the duration of the TO. For areas not covered by OSHA, the Contractor shall comply with regulations regarding safety and health and the current edition of the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1. (CDRL A003) The Contractor shall record and report promptly (within 1 hour) by telephone, email or other direct means to the CO, COR, the base POC, and to the military installation’s Safety Office, all available facts relating to each instance of damage to Government property or third party property or injury to either Contractor, Government, or third party personnel. In the event of an accident/mishap, take reasonable and prudent action to establish control of the accident/mishap scene, prevent further damage to persons or property, preserve evidence until released by the accident/mishap investigative authority through the CO, and immediately report the incident to Emergency Services using the most expedient communication means (e.g., dialing 911 in the United States). If the Government elects to conduct an investigation of the accident/mishap, the Contractor shall cooperate fully and assist Government personnel in conducting the investigation until it is completed.

The Contractor agrees that all personnel and equipment are subject to safety inspections by Government personnel while on federal property.

4.11.2. Radiological Waste, Hazardous Material and Hazardous Waste Permitting and Reporting

The Contractor shall sample and handle all radiological waste, hazardous materials and waste that is a requirement for construction of the project in accordance with applicable federal, state, and local requirements. The Contractor shall provide all radiological waste, hazardous materials use and hazardous waste disposal documentation to the Base Environmental Office or Installation Hazardous Waste Program Manager, and shall register with the Hazardous Materials Pharmacy program (if available) at the installation to ensure appropriate and efficient tracking of the Contractor’s hazardous material purchases, inventories, use, and releases such as required by the Emergency Planning and Community Right-to-Know Act (EPCRA), Executive Orders, or any installation reporting requirements.

The Contractor shall also comply with federal, state, and local requirements for any task involving the transportation of radiological waste, hazardous wastes and/or contaminated materials to off-site treatment, storage and/or disposal facilities. The Contractor is responsible for the disposition of all Radiological, Hazardous Material and Waste produced by activities directly involved in the construction related operations. This includes 40 CFR 260, 49 CFR 172, 173, 178, 179 and all other applicable local, state, and federal transportation regulations.

The Government has provided a report of all known hazardous waste materials for Construct In- Transit Munitions Facility, B1202/Dover AFB (Appendix D). Asbestos/Lead-Based Paint Abatement - Quantities for these items will be determined from the percentage of survey results needed per the EPA standards. The report presents hazardous waste materials and test locations.

The Contractor must reasonably associate the results to determine affected areas and interpret the report to define quantities within a variance of 15% above or below actual conditions. The Contractor shall ensure that all personnel involved in handling and packaging the hazardous waste be trained for the level of expertise required for the proper performance of the task and, in particular, in the areas of chemical incompatibility, general first aid procedures and spills. The Contractor shall provide handling and personnel protective equipment to ensure safe handling of the hazardous/asbestos waste. The Contractor agrees that all personnel and equipment are subject to safety inspections by Government personnel while on federal property. (CDRL A004)

4.12. Project Data/Project Deliverables

Project data and deliverables must be provided to personnel by the Contractor to support multiple projects with real-time or near real-time access. (CDRL A005)

4.12.1. Protecting Unclassified DoD Data

All DOD and Government data that is shared, stored or created on non-DOD information systems must be protected and any breach or loss of that data must be reported. The Contractor shall comply with the security requirements defined in DoD Instruction 8582.01.

4.12.2. Security Breach Notification

Contractor agrees to comply with all applicable laws that require the notification of individuals in the event of unauthorized release of personally identifiable information or other event requiring notification. In the event of a breach of any of Contractor’s security obligations, or other event requiring notification under applicable law, Contractor agrees to:

a. Notify CO by telephone and e-mail of such an event within 24 hours of discovery, and

b. Notify the US-CERT of such an event within 24 hours of discovery, and

c. Assume responsibility for informing all such individuals in accordance with applicable law, and

d. Indemnify, hold harmless and defend the United States, its trustees, officers, enlisted, and employees from and against any claims, damages, or other harm related to such event.

(CDRL A001)

4.12.3. Data Collaboration Site

The Contractor shall establish a Data Collaboration Site with real-time worldwide access available to AFCEC personnel. The Collaboration Site must include at a minimum, the submittal register, submittals, a comprehensive Request for Information (RFI) log, a change order tracker, a photo log, project schedule record, quality control reports, daily reports with complete record of activities and on-site personnel and other relevant project correspondence. The RFI log shall include a tabular report of all RFIs both historical and expected and contain, no., subject/title, authority routing, and routing dates to include 'need-by' dates. This RFI log must be kept up-to-date, reviewed at weekly meetings, and kept on project website. The site must be demonstrated to the Government. The site shall be tailored to the individual projects and close-out documentation shall include an electronic copy of the site documentation, provided in electronic format – digital video disc (DVD) for historical information. Data Collaboration Site data shall be in accordance with

4.12.1 Protecting Unclassified DOD Data.

4.13. Health and Safety Plan (HSP)

Prepare and execute a written Accident Prevention Plan (APP) in accordance with EM 385-1-1 to include Activity Hazard Analysis (AHA). Submit the APP to the CO 15 calendar days prior to date of the pre-construction conference for acceptance. (CDRL A006)

4.14. Contractor Quality Control (CQC) Plan

Submit no later than 15 calendar days after contract award a CQC Plan compliant with the requirements in the contract Specification Section 01 45 00.00 10, QUALITY CONTROL. The Contractor shall prepare, for Government review and acceptance, a site-specific CQC that consists of plans, procedures, and organization necessary to produce an end product which complies with the contract requirements. The CQC shall cover all definable features of work (construction operations, both onsite and offsite) and be keyed to the construction sequence.

Within the CQCP, clearly present the credentials of each person to show that each possesses the following qualifications; submit for CO approval, the resumes of the following key personnel including a project organization chart illustrating lines of authority. (CDRL A007)

(1) Project Manager: Assign a Project Manager with the responsibility for the overall management of the project. The Project Manager must meet the experience requirements consistent with Specification Section 01 30.00.

(2) Site Superintendent: The Superintendent must be onsite at all times, must be an employee of the Prime Contractor and shall only be assigned the duties of project superintendence. The Site Superintendent must meet the experience requirements consistent with Specification Section 01 30.00.

(3) Contractor Quality Control (CQC) Manager: The CQC Manager must be onsite at all times and cannot be the SSHO on this project, even though the CQC Manager has safety inspection responsibilities as part of the QC duties. The CQC Manager must meet the experience requirements consistent with Specification Section 01 45 00.00 10.

(4) Site Safety and Health Officer (SSHO): The SSHO must be onsite at all times and is not authorized to dual-hat as the Superintendent or CQC Manager. The SSHO must report to a senior project (or corporate official) independent of the CQC Manager. The SSHO must meet the experience requirements listed in EM 385-1-1 and consistent with Specification Section 01 35 26.

4.15. Technical Plans and Reports

The Contractor must provide submittals in accordance with the specifications. All material and equipment submittals must be certified compliant with FAR Subpart 25.2—Buy American— Construction Materials.

4.15.1. Construction Work Plan

Prepare a construction work plan in accordance with the specifications. (CDRL A008)

4.15.2. Technical Reports

The Contractor must provide submittals in accordance with the specifications.

5.0 PROSECUTING THE WORK

5.1. Site Work

The Contractor shall perform site preparation, incidental characterization and field investigation, conservation, and demolition of sites as required.

5.1.1. Conservation

Activities shall be planned and implemented in a manner that protects existing site utilities, structures, surface features, service operations, monitoring and other types of wells, and the general site environment. This includes the protection of trees, shrubs and other vegetation not in the affected zone from dust damage, soil compaction, and physical contact with machines and equipment. If appropriate, the Contractor shall conserve uncontaminated topsoil by removal, storage, or redistribution. All reasonable measures shall be taken to minimize and suppress fugitive emissions of dust, vapors, and other site materials during site work. All fill materials shall be non-contaminated. The Contractor shall conduct all operations and activities with the intent of reducing the amount of pollution generated. Specific areas to be focused on are generation of solid waste, use of hazardous materials, use of ozone depleting chemicals, generation of hazardous waste, and use of energy and water. During site work the Contractor shall plan, construct, operate, maintain, optimize, and decommission systems necessary to control storm water run-on and run-off; and transport surface water drainage to a treatment plant, discharge location, or any other appropriate destination for discharge in accordance with local environmental regulations.

5.1.2. Site Preparation

The Contractor shall perform site work as necessary to prepare sites for construction activities.

Security and access controls shall be implemented to prevent unauthorized entry to sites and to protect wildlife from site exposure. The Contractor shall survey existing utilities to determine adequacy and need for modifications to support site activities. The Contractor shall obtain appropriate approvals and shall construct connections or new systems for electrical power, water, sewer, gas distribution, telephone, and other utilities, as required, to accomplish the activities specified.

5.1.3. Demolition

The Contractor shall demolish facilities, systems, and other improvements as necessary to prepare sites for construction activities. The Contractor shall conduct demolition efforts in conjunction with such activities as new construction or renovation, removal of outdated facilities, and site clearing from natural disasters. The Contractor shall perform surveys as part of demolition efforts to identify conditions and hazardous materials or Asbestos related hazards for mitigation.

Demolition efforts shall include validation of existing utilities for active conditions and evaluation of potential environmental concerns as required. The Contractor shall provide all necessary documentation to the CO/COR for preparation of DD Forms 1354.

5.2. Construction Operation Services

The Contractor shall perform a full range of activities to meet all requirements of the plans and specifications.

5.2.1. Construction

Upon issuance of construction Notice To Proceed (NTP) by the CO, the Contractor may commence on-site construction activities.

Provide the manpower, equipment, material, services, and transportation necessary to review, plan, develop and implement quality control and oversight services during the construction phase of this TO. Details regarding construction management requirements, inspection and testing, construction facilities and temporary controls, environmental protection, quality control system, construction quality control, and project closeout are provided in the project specifications. (CDRLs A005, A007, A008)

5.2.2. Inspections

In all work performed it is the Contractor’s responsibility to perform proper QC inspections throughout the project to ensure a quality product. The Government inspector is responsible for adequate Quality Assurance (QA) for the work accomplished. It is not the role of the Government to perform the Contractor’s QC for the project, especially during inspections. The Contractor shall comply with the standard three phase Contractor Quality Control (CQC) inspection process, referring to contract Specification Section 01 45 00.00 10.

5.2.2.1. Pre-Final Inspection

Conduct a punch-out inspection as per Specification Section 01 45 00.00 10, COMPLETION INSPECTION. Prepare and include in the CQC documentation a punch list of items which do not conform to approved drawing and specifications. Once all punch list deficiencies have been corrected, notify the Government that the facility is ready for the pre-final inspection. The Government will perform the pre-final inspection; a pre-final punch list may be developed as a result of this inspection. Ensure that all items on this list have been corrected before notifying the Government that a final inspection can be scheduled. (CDRL A017)

5.2.2.2. Final Inspection

Conduct a final acceptance inspection as per Specification Section 01 45 00.00 10, COMPLETION INSPECTION. The inspection must concentrate on the items identified at the punch-out inspection and recorded in the punch-out Inspection report. The final inspection report must: (1) certify that all items of the design have been implemented and that the construction is complete, and (2) include a record of as-built drawings and specifications verifying that all development standards have been met. A minimum of 60 calendar days prior to the final acceptance inspection, provide the Interim DD Form 1354 for the transfer and acceptance of Real Property. At the final acceptance inspection present a completed DD Form 1354 for signature and acceptance. Refer to UFC 1-300- 08 for instruction on completing the DD Form 1354. For information purposes, a blank fillable PDF DD Form 1354 may be obtained at the following:

http://www.dtic.mil/whs/directives/forms/eforms/dd1354.pdf. Submit the completed Checklist for DD Form1354 of Installed Building Equipment items. Attach this list to the updated DD Form

1354. (CDRL A018)

5.2.3. Delivery and Warranty

Complete punch-out inspection and commissioning requirements prior to pre-final inspection.

Submit copies of the project operation and maintenance manuals prior to testing the system involved. For final approval, update and resubmit data as per Specification Section 01 78 00, CONFIGURATION, prior to contract completion. At least 30 calendar days before the planned pre-warranty conference, deliver to the CO for approval a Warranty Management Plan as per Specification Section 01 78 00, WARRANTY MANAGEMENT. Issue the warranty in accordance with FAR 52.246-21 (Warranty of Construction). Perform training, instruction and cleanup in accordance with Specification Section 01 78 00, videotape training future use by Government organizations. (CDRLs A005, B012)

5.3. Demobilization

Demobilize facilities as necessary, and restore the site. Remove any temporary facilities and implement erosion control measures such as seeding, mulching, sodding, and erosion control fabrics; restore roads, structures, and utilities.

The Contractor shall abide by FAR 52.245-1 Government Property and Defense Contract Management Agency (DCMA) instructions pertaining to disposal of Government Property and reporting through the Plant Clearance Automated Reutilization Screening System (PCARSS) in the removal and disposition of any Government Property during the Demobilization from the project site. (CDRLs A010)

5.4. Emergency Response

Not Applicable to this TO.

5.5. Maintenance and Repair

Not Applicable to this TO.

5.6. Ordnance Removal and Support

Not Applicable to this TO.

6.0 FACILITY CONSTRUCTION TASK ORDER DELIVERY METHODS

The Contractor shall perform a full range of activities to meet all customers’ construction requirements as designed and specified. Requirements may include construction, demolition, repair.. Provide office space within the temporary construction field office for the Title II http://www.dtic.mil/whs/directives/forms/eforms/dd1354.pdf

Quality Assurance/Inspector, compliant with Specification 01 50 00 Section 3.6.1. Provide enclosed office space with desk, file cabinets, plan racks, shelving, and electronic access.

Electronic access includes internet and phone access, copier/printer/scanner and fax capabilities.

6.1. Design Build (D-B)

Not Applicable to this TO.

6.2. Design-Bid-Build (D-B-B)

The RE&C Contractor shall manage and perform D-B-B construction work as defined in the TO scope.

7.0 ADDITIONAL REQUIREMENTS

7.1. Types of Projects/Work

Not Applicable to this TO.

7.2. As-Built Documentation

Include project record documents compliant with Specification Section 01 78 00, CLOSEOUT SUBMITTALS. Include in as-built drawing documentation a record of as-built drawings and specifications verifying that all development standards have been met. Deliver as-built documentation prior to final payment. Submit As-Built Drawings in CADD, BIM and PDF formats in accordance with A/E/C (Architectural / Engineering / Construction) Standards. One copy of the drawing files shall be provided on CD-RW (Compact Disk-Rewritable) with every submittal to include both PDF and CADD formats. (CDRL A014)

8.0 POINTS OF CONTACT (POCs)

Points of contact will be provided at the preconstruction meeting.