SV Questions Answers.pdf

PDF 10 KB Posted

Attached to
SOF Enclose SERE Parachute Trainer 91057 Federal contract opportunity
Solicitation number
FA441720R0007
Issued by
Department of the Air Force Special Operations Command

About this file

This solicitation requests proposals for enclosing and conditioning remaining open bays at an existing Parachute Training Facility at an Air Force base. Work includes selective demolition, construction of CMU walls and metal trim, installation of two new overhead doors, pouring new interior concrete slabs with athletic floor coating, and retrofitting existing structures with additional thermal insulation. The estimated value is between $500,000 and $1,000,000. This is a 100% set-aside for women-owned small businesses. The contract will be a single-award, firm-fixed-price for a 120-day period. Offerors must register in SAM and submit bids electronically. Proposals are due by an unspecified date. The soliciting agency is the Air Force Special Operations Command.

View the file

Other files for this federal contract opportunity

Other files attached to SOF Enclose SERE Parachute Trainer 91057, newest first.
File Type Posted
Site Visit BRIEF.pdf PDF
Site Visit sign-in sheet.pdf PDF
Attch 3 - Wage Determination.pdf PDF
Attch 2 - Drawings 20200302.pdf PDF
Attch 6 - 50 Division Construction Cost Estimate Worksheet.xls XLS spreadsheet
Attch 5 - Financial Worksheet.docx DOCX document
Attch 4 - PPQ.docx DOCX document
Solicitation - FA441720R0007.pdf PDF
Attch 7 - Site Visit Info.docx DOCX document
Attch 1 - Specifications 20200302.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION NO. FA441720R0007

PROJECT NO. CP1033734 – SOF Enclose SERE Parachute Trainer Bldg 91057

QUESTIONS – ANSWERS – 1 through 2

QUESTIONS:

Question 1: Reference drawing E-004 – Is a directional bore for the secondary feeder from primary transformer to New Panel ‘A’ acceptable?

Answer 1: Yes, directional bore is acceptable.

Question 2: In considering the NTP date, it was mentioned that the NTP would be considered for November or December. Is this a preference, or can the NTP be issued closer to the award?

Answer 2: NTP issued closer to award is acceptable to CE.

End of questions