Questions_Answers_29_Mar_2016.pdf
PDF 152 KB Posted
- Attached to
- Repair Fire Suppression, Bldg 90028 Federal contract opportunity
- Solicitation number
- FA4417-16-R-0007
About this file
FA4417-16-R-0007 Questions and Answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions_Answers_5_Apr_2016.pdf | ||
| Amendment_0001 _Change_PoP.docx | DOCX document | |
| Site_Vist_Sign_In_Sheet_and_MFR.pdf | ||
| Solicitation_FA4417-16-R-0007.docx | DOCX document | |
| Atch_1_-_Specifications_FTEV_15-1065 _16R0007.pdf | ||
| Atch_5_-_Financial_Worksheet _16R0007.docx | DOCX document | |
| Atch_3_-_Wage_Determination _16R0007.pdf | ||
| Atch_4_-_PPQ _16R0007.docx | DOCX document | |
| Atch_2_-_Drawings_FTEV_15-1065 _16R0007.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION NO. FA4417-16-R-0007
PROJECT NO. FTEV 15-1065, Repair Fire Suppression, Bldg 90028
QUESTIONS – ANSWERS – 1-2 29 March 2016
QUESTIONS:
Question 1: Can you please clarify for this solicitation as it relates to FAR 52.219-3; the classification of this solicitation as either "General Construction" or "Construction by special trade contractors"?
Answer 1: The classification for this solicitation is "General Construction."
Therefore, FAR 52.219-3(d)(3) applies to this solicitation.
Question 2: When working over the cage in the upstairs exercise area, can we remove the top section of the cage to demo the existing pipe and install the new pipe?
Answer 2: After proper coordination with the Contracting Officer’s Representative, the contractor can remove the top section of the cage to demo the existing pipe and installing the new pipe. The contractor shall reinstall the cage top once work in that section is completed.