Schedule Of Materials Submittal 24 Aug 15
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_0003.pdf | ||
| Q_and_A_FA3047-15-R-0061_Airfield_Maintenance.pdf | ||
| Amendment_2_SF_30_Atch_1_SOW_2_Sep_15.pdf | ||
| FA3047-15-R-0061.pdf | ||
| FA3047-15-R-0061.pdf | ||
| SF_1442_Solicitation.pdf | ||
| Atch_5._-_Schedule_B_13_Aug_15.pdf | ||
| Atch_2._-_Appendix__A_-_G_12_Aug_15.pdf | ||
| Atch_4._-_Schedule_Of_Materials_Submittal_13_Aug_15.pdf | ||
| Atch_1._-_Statement_of_Work_JBSA_AIRFIELD_MAINTENANCE_8_10_15.docx | DOCX document | |
| Atch_3._-_Wage_Determination_Heavy__Highway.pdf | ||
| Map__JBSA-Lackland_Visitor_Center.jpg | JPG image |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Schedule
| Project Number: | |||
| JBSA 150001 | Project Title: | ||
| JBSA Airfield Maintenance, Rubber Removal | Solicitation / Contract Number: |
FA3047-15-R-0061
| Line Number | (To be completed by Project Engineer) | (To be completed by Contract Administrator) | ||||||||||||
| Number of Copies Required | Remarks | |||||||||||||
| Item or Description of Item, Contract Reference, Type of Submittal | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURER'S | |||||||||
| RECOMMENDATIONS | MANUFACTURER'S | |||||||||||||
| WARRANTY | CATALOG DATA | OPERATING | ||||||||||||
| INSTRUCTIONS | DOCUMENT | Date Received in Contracting | Date to Civil Engineering | Return Suspense Date | Submittal Numbers | Date Contractor | ||||||||
| Notified | Contractor Resubmittal | Final Approval | ||||||||||||
| Approved | Disapproved | |||||||||||||
| 1 | Contract Progress Schedule AF Form 3064 (SOW 5.2) | 1 | ||||||||||||
| 2 | Integrated Master Schedule (SOW 5.2) | 1 | ||||||||||||
| 3 | Health and Safety Plan (SOW 6.1) | 1 | ||||||||||||
| 4 | Quality Assurance Plan (SOW 6.2) | 1 | ||||||||||||
| 5 | Work Plan (SOW 6.3) | 1 | ||||||||||||
| 6 | Meeting Minutes (SOW 5.4) | 1 | ||||||||||||
| 7 | Permits (SOW 5.7) | 1 | ||||||||||||
| 8 | Sampling and Testing Reports | 1 | ||||||||||||
| 9 | Pre-Final Inspection Report (SOW 9.2) | 1 | ||||||||||||
| 10 | Final Inspection Report (SOW 9.3) | 1 | ||||||||||||
| 11 | As-Built Drawings (SOW 9.3) (Hard Copies) | 2 | ||||||||||||
| 12 | As-Built Drawings (SOW 9.3) (CD) | 2 | ||||||||||||
| 13 | DD 1354 (SOW 9.3) | 2 | ||||||||||||
| 14 | Warranty Letters (SOW 9.3) | 2 | ||||||||||||
| 15 | Sealant Product Data (Ref Div 32 Section 01.17.16.14) | 1 | ||||||||||||
| 16 | Sealant Samples (Ref Div 32 Section 01.17.16) | 1 | 1 | |||||||||||
| 17 | Joint Sealant Product Data (Ref Div 32 Section 01.19.61) | 1 | 1 | |||||||||||
| 18 | Joint Filler Sample (Ref Div 32 Section 01.19 61) | 1 | 1 | |||||||||||
| 19 | Separating Tape Sample (Ref Div 32 Section 01.19 61) | 1 | 1 | |||||||||||
| 20 | Joint Backer Rod (Ref Div 32 Section 01.19 61) | 1 | 1 | |||||||||||
| 21 | Joint Filler (Ref Div 32 Section 01.19 61) | 1 | ||||||||||||
| 22 | Concrete Mix Design (Ref Div 32 Section 01.29`) | 1 | ||||||||||||
| 23 | Concrete Mix Design (Ref Div 32 Section 13 11`) | 1 | ||||||||||||
| 24 | Epoxy-Resin Grout (Ref Div 32 Section 13 11) | 1 | 1 | |||||||||||
| 25 | Paint (Ref Div 32 Section 17.24.00 10) | 1 | ||||||||||||
| 26 | Glass Beads (Ref Div 32 Section 17.24.00 10) | 1 | 1 | |||||||||||
| 27 | Primer (Ref Div 32: Section 32.01 19) | 1 | 1 |
&L&"Verdana,Bold"&12Schedule of Material Submittals&C&12ATTACHMENT 4: 24 Aug 2015 &R&P of &N Enter the date received from the Contractor. (MM/DD/YY) Enter the date submittal was given to CE for review. (MM/DD/YY) Enter the date the submittal is due back from CE
(MM/DD/YY)
Enter the Submittal Number Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
Enter Resubmittal Number Enter the submittal final approval date