Questions FA3016-17-R-0051

Repair Roof Bldg. 1374 JBSA-Ft. Sam Houston

JBSF130221

1. What R value is insulation needing to be?

ANS:

Refer to Specification 07 22 00 Roof and Deck Insulation section 2.1.4. Also, provide a minimum of 1-1/2” thick insulation board.

2. Is the new Roof system to be fully adhered or Mechanically attached?

Refer to section 4 of SOW and Specification 07 54 23 00 Thermoplastic Polyolefin (TPO) Roofing section 1.2.

3. Is there a Cover-board? and what type and size is it?

Refer to Specification 07 54 23 00 Thermoplastic Polyolefin (TPO) Roofing section 2.2.8.

4. The solicitation mentions lead paint, is that to be included in the scope of work since it may not pertain to the roof?

Refer to SOW, to include, but not limited to; section 7.2.6.3 and 7.2.7.1.

5. What is the slope of the tapered system?

One layer of the tapered roof insulation assembly shall be factory tapered to a slope of not less than 1/4 inch per foot. Also, request that Contractor work with roofing manufacturer to provide as much slope as possible to remove water off the roof.

6. Are we to include 25% of deck replacement in the base bid?

Yes include 25% deck replacement in the base bid.