Attachment_5_-_Cost_Estimate_Breakdown.xls

XLS spreadsheet 165 KB Posted

Attached to
Repair/Replace Running Track, Bldg 9210 Federal contract opportunity
Solicitation number
FA3016-16-R-0010
Issued by
Department of the Air Force Air Education and Training Command

About this file

Attachment 5 - Cost Estimate Breakdown

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ESTIMATE FRONT

CONSTRUCTION COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
CONTRACT FOR (Work to be preformed)PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBERPROJECT NUMBERMPLS 15-0031WORK LOCATIONJBSA LACKLAND
MATERIAL COSTLABOR COSTS
LINEUNITOTHER
NO.ITEMOFMANHOURAVERAGEDIRECTLINE
MEASUREQUANTITYUNITTOTALMANDAYSRATETOTALCOSTSTOTAL
(2)(3)(4)(5)(6)(7)(8)(9)(10)

&R&6Attachment 5 Request for Proposal: FA3016-16-R-0010

ESTIMATE CONT SHT 1

CONSTRUCTION COST ESTIMATE BREAKDOWN CONTINUATION SHEET
CONTRACTORADDRESS
CONTRACT FOR (Work to be preformed)PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBERPROJECT NUMBERMPLS 15-0031WORK LOCATION
MATERIAL COSTLABOR COSTS
LINEUNITOTHER
NO.ITEMOFMANHOURAVERAGEDIRECTLINE
MEASUREQUANTITYUNITTOTALMANDAYSRATETOTALCOSTSTOTAL
(1)(2)(3)(4)(5)(6)(7)(8)(9)(10)

&RAttachment 5 Request for Proposal: FA3016-16-R-0010

ESTIMATE BACK SHT

INSTRUCTIONS FOR COMPLETING FORM
Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.
Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards - SY, cubic yards - CY, square feet - SF, linear feet - LF, board feet - BF, each - EA, pound - LB).
Col 3 Quantity. Contractor's estimate of quantity required in terms of unit of measure (column 2). Items and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issed. Otherwise, the contractor is responsible for determining quantity estimates.
Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (col 5) for item listed in column 1.
Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.
Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1) which are special to the contract and of significant dollar value.
Col 10 Line Total. Self-explanatory.
NOTE: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows:
TOTAL MATERIAL COSTS$- 0
TOTAL LABOR COSTS$- 0
TOTAL OTHER DIRECT COSTS$- 0
TOTAL DIRECT COSTS$- 0
OVERHEAD___%$- 0
SUBTOTAL$- 0
PROFIT___%$- 0
TOTAL PRICE$- 0
DATE ______________________________FIRM NAME ________________________________________
TITLE ______________________________BY _________________________________________________
(Signature)
_________________________________________________________________________________________________________________________
INSTRUCTIONS TO OFFERORS
1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs (and attached supporting information) suitable for detailed review and analysis.
2. In addition to the specific information required by this form, the offeror is expected, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substantiation which are reasonably required for the conduct of an appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clear understanding of
a. The existing, verifiable data.
b. The judgmental factors applied in projecting from known data to the estimate, and
c. The contingencies used by the offeror in his proposed price.
In short, the offeror's estimating process itself needs to be disclosed.
3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate), and made available to the contracting officer or his authorized representative upon request.
4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any negotiations prior to contract award.