Attachment 7 - FA301022R0033 Q and As.pdf
PDF 209 KB Posted
- Attached to
- Airfield Management - Keesler AFB Solicitation Federal contract opportunity
- Solicitation number
- FA301022R0033
About this file
This document includes a request for proposal for airfield management services at Keesler Air Force Base, Mississippi. The 81st Contracting Squadron is seeking proposals for a non-personal services contract to provide airfield management in accordance with the requirements in the performance work statement. The period of performance is expected to be from 1 October 2022 to 30 September 2023, with three optional one-year extensions not exceeding 54 months total. The acquisition is set aside for Service-Disabled Veteran-Owned Small Businesses. Interested parties must register in the System for Award Management and submit any questions by 29 August 2022. Proposals are due as indicated in the solicitation package. A site visit is also planned.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 6 - PWS Attch 2 - Work Area Layout.pdf | ||
| Solicitation Amendment 0002.pdf | ||
| Attachment 8 - Site Visit Sign-in Sheet.pdf | ||
| Attachment 1 - PWS dated 1SEP22.pdf | ||
| Solicitation Amendment 0001.pdf | ||
| Attachment 5 - Keesler Current CBA dated 23 Aug 21_Redacted.pdf | ||
| Attachment 3 - Past Performance List of References.pdf | ||
| Attachment 2 - GFE.pdf | ||
| Attachment 4 - Past Performance Questionnaire (PPQ).pdf | ||
| Attachment 1 - PWS - 25JULY2022.pdf | ||
| Solicitation - FA301022R0033.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
No. Questions Reference Answer
Is there a minimum team compliment (MTC) for the passenger terminal staff? PWS paragraph
1.2., NOTE, states that AMS shall ensure minimum team compliment (MTC) provided of 7 full‐time employees (AFM, AAFM, and five (5) AMSL’s) but there is no mention of passenger terminal staffing.
Reference: PWS 5.6. Service Summary –
Passenger Terminal, Performance Objective
#1, Al Passenger Terminal personnel shall be fully staffed, trained/qualified and provide safe, professional and timely services to all customers.
No, Contractors shall determine required staffing for
Passenger Terminal services.
Is the incumbent staffed to the requirement of the performance work statement? N/A
Current contract is not staffed with the required MTC of full‐time employees. One additional full‐time employee must be hired to meet the minimum MTC requirement for
Airfield Management section. Current staffing consists of:
(2) staff personnel, (4) AMSL's, and (2) part‐time employees (estimated 24 work days a year). Does NOT apply to passenger service.
Solicitation Amendment document published on
16 August 2022, indicates in section (b)
Contractors shall submit questions pertaining to the solicitation package to the CA no later than 08
September 2022, 12:00pm Central time, however the document later states questions shall be submitted no later than Monday 29 August 2022 at 12:00pm Central time. For accuracy which no later than date is correct for submission of question?
29 August 2022 is/was the deadline for questions submittals.
Instruction to offerors do not provide requirement for the submission of proposals in response to this request for service. Can the government provide guidance if there is any on submission requirements?
All submission requirements can be found in the the
Addendum to FAR 52.212‐1 Instructions to Offerors ‐‐
Commercial Items, page 49 of the SF 1449 Solicitation.
Can the government provide historical data for the amount of after‐hours service were provided during the incumbent’s term of service for AMS?
Yes; however, this is not pertinent information, as this has already been factored in the CLINs, with the requirement of 350 additional after‐hours (its own CLIN) (see tabs on bottom of excel spreadsheet
Can the government provide expected number of
UTA weekend annually?
Minimum of 10 UTA's annually. UTA is usually one‐ weekend a month. Some months are held virtually, so AMS services are not always required
Can the government provide historical data on for number of in‐transit services (shuttles) were provided by Passenger Terminal personnel?
Unsure exactly what "in‐transit services (shuttles) were provided by Passenger Terminal personnel" means. If this question is referring to "shuttle service" as in ferrying passengers to and from aircraft, that is not a metric that is currently tracked. If referring to aircraft shuttles (such as
UTA operations), those passengers are normally processed by 41 APS personnel with support from the contracted
Passenger Service agents as needed. Each UTA weekend supports two shuttle services: one bringing in the reservists from other locations for their duty weekend, and one ferrying them back to their local areas. There are typically 10 in‐residence UTA weekends per year; so, an average total of 20 UTA shuttles per year
Can the government provide historical data for the amount of after‐hours service were provided during the incumbent’s term of service for
Passenger Terminal Operations?
To date, a total of approximately 40 hours of after‐hours service was provided by Passenger Service during this term of service. There are few passenger operations outside of the normal airfield operating hours. (Passenger Service has their own CLIN for after‐hours support)
Are there any protected species of birds that are found on the airfield?
Currently there are no protected species of birds identified in the base BASH Plan. Per the PWS, Section 6: General
Information, the contractor is required to maintain a depredation permit for as‐needed lethal deterrence of migratory birds
What is the estimated number of UTAs supported each year?
DUPLICATE QUESTION, see question #6 above.
FY23 Airfield Management Q&A's ‐ Solicitation No. FA301022R0033
Thursday, September 1, 2022
What is the estimated number of passengers processed each year?
Approximately 2,500 passengers are processed each year
How many air shows are anticipated in the next 4 years?
Only one airshow currently planned at this time.
Will the government provide the name of the current contractor and award price?
Current contract information may be found here:
https://www.fpds.gov/ezsearch/search.do?q=FA301018C0
028&s=FPDS.GOV&templateName=1.5.2&indexName=aw ardfull&sortBy=SIGNED_DATE&desc=Y
Will the Government provide a CBA rates for
Wages/H&W/Pension to offerors before the solicitation due date, as the provided CBA in the solicitation does not cover the period of performance?
No, the CBA provided is for current rates and will be used for this solicitation. The contractor should accomplish any necessary negotations for the new CBA once the current
CBA expires.
Will the Government provide pyrotechnic/shot gun usage data for BASH program?
Keesler has one shotgun purchased by incumbent company which is not Government Furnished Property.
The required ammunition types are Screamer Sirens, Bird
Bangers, and shotgun shells appropriate for birds and small wildlife. The Explosives Facility License allows for a total of 500 of each type at any one time. Historical data shows an average of approximately 16 boxes (50‐count each) of pyrotechnics (bangers and screamers) and three handheld launchers per year
Will the Government confirm the Unit of Issue for
CLINs X0002 and X0003 are for hours of
“operational support” and not for employee labor hours?
Yes, these CLINS are for operational support. (if airfield is open for 2 hours, 2 hours are deducted from the annual
350 allotted FY hours)
How many UTA's does the contractor support monthly for Airfield Management? PWS Para 2.3.1
UTA weekends are normally one weekend per month; a minimum of 10 UTA's annually.
How many UTA's does the contractor support monthly for Passenger Terminal? PWS Para 3.2
UTA weekends are normally one weekend per month; a minimum of 10 UTA's annually.
Is the passenger terminal staffed by one (1) of the two (2) AMSL during Passenger terminal services hours of operations?
NEGATIVE. AMSL is a 1C7X1 career and passenger service is a 2T2X1. Neither passenger service or AMSL is qualified to support the other agency. Passenger service is a small requirement, so it has been combined with AMS contract.
Technically, 2 separate COR's, 2 seperate agencies; under one contract.
Is there a minimum team compliment (MCT) of
Passenger Processors for staffing Passenger terminal services hours of operations in addition the Airfield Management Service MCT mentioned in the PWS paragraph 1.2. Note ?
The PWS does not specify a MCT for Passenger Service. To our knowledge there is no regulatory requirement for there to be more than one person on duty at a time, such as is required for Airfield Management in AFMAN 13‐
204V2. Hence, Passenger Service it is a one‐deep office during the duty day. Manning must be such as to have a body in the seat during the Passenger Service hours of operation specified in the PWS (para. 3.2.).
Are the maintenance of appropriate levels of bird scare cartridges for wildlife dispersal and non‐ toxic shotgun ammunition for depredation at the expense of the contractor? If yes, what are the required ammunition types and average historical volume of use for pricing considerations?
Yes; ammunition and delivery devices are at the expense of the contractor. The PWS, Section 6: General
Information, states: The contractor shall maintain dispersal/depredation equipment such as bird scare cannons, pyrotechnic equipment, and 12‐guage shotguns.
(Note: Currently, Keesler does not implement bird scare cannons; and we have one shotgun purchased by incumbent company.) The required ammunition types are
Screamer Sirens, Bird Bangers, and shotgun shells appropriate for birds and small wildlife. The Explosives
Facility License allows for a total of 500 of each type at any one time. Historical data shows an average of approximately 16 boxes (50‐count each) of pyrotechnics
(bangers and screamers) and three handheld launchers per year
Are there any contractor required insurance requirements?
The contractor provides insurance for the airfield response vehicle, as the vehicle is an item required to be provided by the company
Reference Attachment 3. Please define “POP” as used in column titled “Contract Values”.
Period of Performance (POP)
What type of services are provided to passengers traveling through the base? Is it anything appreciable?
Paragraph 3.1 Description of Services
(Passenger Terminal)” states “The Passenger
Terminal shall also provide in‐transit services for all passengers traveling through Keesler
AFB.”
Space‐A passengers are provided the following: briefing of
Keesler AFB and surrounding area, given passenger terminal numbers for other requested locations, provided
Keesler's shuttle schedule, arrange for transportation, escort passengers to/from aircraft
Would the Government please provide the number of passengers per aircraft that the contractor usually handles.
Reference PWS paragraph 3.1 Description of
Services (Passenger Terminal).
Dependent upon type of aircraft. On average, passenger count is between 40‐50 personnel
Please explain the difference in the statements within the CLINs which read “Each hour invoiced under this CLIN shall be for each hour of support occurring after duty hours, not for actual hours worked for each employee.” Is this stating that the provided hourly rate is sufficient to cover the
2‐man coverage requirement? Please clarify.
Reference 1449 Solicitation Supplies or
Services & Prices or Costs p. 3 of 54, CLINs
0002 and 0003.
The statement, “Each hour invoiced under this CLIN shall be for each hour of support occurring after duty hours, not for actual hours worked for each employee.”, is meant to provide clarity that in order to invoice under the After
Duty Hour CLINS (0002 & 0003), services must have been provided outside of operational hours.
2.3.2 is titled Special Events and doesn’t appear to be an appropriate link. Please clarify
Reference PWS paragraph 2.3.1 Normal
Airfield Operating Hours and 2.3.2 Special
Events. The paragraph states “All other times personnel shall be on‐call IAW paragraph
2.3.2”
The following sentence has been deleted from para. 2.3.1.
of the PWS with Amendment 0002: “All other times personnel shall be on‐call IAW paragraph 2.3.2” as it was included by mistake. All on‐call procedures are outlined in:
2.3.1.2., 2.3.1.3., 2.3.1.4., 2.3.1.6.
28 Is there more than 1 UTA per month?
Reference PWS paragraph 2.3.1. The paragraph states “On Unit Training Assembly
(UTA) weekends…”.
UTA is usually one‐weekend a month. Some months are held virtually, so AMS services are not always required
Do the Reservists take over operation of the
Passenger Terminal during any part of the UTA weekend?
Yes, 41APS (aeriel port) takes over the UTA shuttle processing during UTA weekends. Contracted Passenger service is required to be on duty during UTA weekends to support space‐a passengers
Is the Contractor required to have a Passenger
Terminal employee on site during all of the Hours of Operation as shown in the table found in paragraph 3.2 ?
Yes
What type of aircraft will the contractor be working with? i.e. C‐12, C‐21, C‐130
Can be dependent on missions in/out of Keesler however, most common aircraft supported are: (C‐17, C‐130, B‐737, C‐21)
Are airfield management personnel (other than the AFM and AAFM) permitted to assist in passenger processing, as the areas are adjacent to each other?
NEGATIVE. Airfield Management is a 1C7X1 career and passenger service is a 2T2X1. Neither passenger service or
Airfield Management is qualified to support the other agency; regardless of office locations within building.
Passenger service is a small contract so it has been combined with AMS contract. Technically, 2 separate
COR's; under one contract.
33 Are passengers walked or driven to/from aircraft?
Reference PWS paragraph 3.1 Scope of Work
(Passenger Terminal). Both
Reference PWS paragraph 3.1, Scope of Work
(Passenger Terminal) and 3.2, Hours Of
Operation (Passenger Terminal). Paragraph
2.1 states as an exception that “Monthly UTA shuttles will be handled by the 403rd Air
Reserve Wing.”
Is Passenger Processing required to be manned during all hours of operation including Saturday and Sunday hours?
Reference PWS paragraph 3.2 Hours of
Operation (Passenger Terminal).
Passenger service is manned Monday‐Friday (except holidays) and every UTA weekend. Under rare circumstances the FSM may require passenger service support outside of those listed hours (has own CLIN for passenger service after‐hours).
As part of the permit application process, the applicant is asked: “If you are applying on behalf of an airport for a permit to control birds in flight zones, indicate whether you are operating under an approved Wildlife Hazard Management Plan.”
Does Keesler AFB currently have an approved
Wildlife Hazard Management Plan?
Reference PWS Section 6, General
Information. At the end of this paragraph it states that “The SP shall obtain a Federal Fish and Wildlife depredation permit annually.”
Yes, Keesler operates under the approved 81TRW 91‐212
(Keesler AFB BASH Plan).
The list contains 2 Garrett Super Scanner Metal
Detectors however one is identified as inop. Will this be replaced by the Government so as not to leave the contractor without a working backup?
Reference Attachment 1 Government
Furnished Equipment.
Contractor has not requested a replacement hand‐held scanner; however, the Government will provide a replacement when requested. Currenlty, passenger service has a hand‐held scanner and a walk through scanner; 2 operational scanners available
We see a Bird‐X Megablaster Pro and shotgun clearing barrel in the GFE list however, we do not see any of the BASH equipment that aligns with the BASH equipment training found in Appendix
H. Is this additional the responsibility of the contractor?
Reference Attachment 1 Government
Furnished Equipment and H‐1. Training, Certification, and/or Licensing.
Contractor provides all other BASH equipment not listed on the GFE. See question # 15 for contractor specific required purchases
The first sentence of the paragraph states “See
Appendix E, Historical Workload Data, for historical data in relation to collateral tasks.”
Appendix E is nothing more than a building layout with no workload. Please clarify.
Reference PWS Appendix D – Collateral
Tasks(Duties) and Appendix E – Work Area
Layout.
This sentence has been removed from the PWS with
Amendment 0002, as it was mistakenly included.
There is no workload for either Airfield
Management, On Call Support and Passenger
Processing. Please provide current workload. Reference PWS dated 25 July 2022.
Airfield Management is always scheduled to provide on‐ call support when the airfield is closed
(weekends/holidays). On‐call is built into the monthly schedule and sent to Command Post for after‐hour notification purposes. Passenger service is not placed on‐ call and notified in advance if after‐hours support is required
Collective Bargaining Agreement. We believe that the version incorporated was absent an addendum that dealt with base closure pay.
Please confirm that the CBA provided includes all attachments and/or addendum.
The Collective Bargaining Agreement provided included all attachments/addendum in the Government's possession.
Do contractors need to submit a hard copy proposal? Is a hard copy proposal required?
Proposal shall be submitted via email, hard copy is not required.
Can contractors email proposals to the contacts listed in Para (b)? Yes.
Is a technical volume required? I reviewed and only see “compliance with solicitation requirements”.
Technical volume is not required, contractor should submit price per CLIN structure.
What would the government like for contractors to submit to meet the requirements of Para (a) (1)
Compliance with solicitation requirements?
Contractor will submit a proposal that meets the requirements setforth by 52.212‐1 & 52.212‐2 to comply with Para (a)(1).
1449, Page 53 of 54
Amendment 0001, Page 2 of 4 Para. (b)
Date (Contractor Pay Periods)
AM
Actual
Hrs Worked
(outside of published afld hrs)
Pax Svc Actual
Hrs Worked
(outside of published afld hrs)
Remarks
AM
FY19 Hrs
Added Hrs Per
CONS,
appvd
22Aug19
Remarks FY19 started 1Oct18 44.4
1 - 5 Jan 19 0.0 0.0 Pay period started 23Dec18 0.0 6 - 26 Jan 19 2.5 0.0 2.5 JAN 6.7
27 Jan - 9 Feb 19 4.2 0.0 4.2 hrs in Jan 4.2 FEB 4.3 10 - 23 Feb 19 4.3 2.5 4.3 MAR 10.1
24 Feb - 9 Mar 19 6.8 0.0 6.8 hrs in Mar 6.8 APR 8.8 10 - 23 Mar 19 3.3 0.0 3.3 MAY 30.2
24 Mar - 6 Apr 19 2.0 0.0 2 hrs in Apr 2.0 JUN 2.3 7 - 20 Apr 19 3.8 0.0 3.8 JUL 17.7
21 Apr - 4 May 19 12.5 1.8 3 hrs in Apr; 9.5 hrs in May 12.5 AUG 26.8 5 - 25 May 19 18.4 0.0 18.4 SEP 101.2
26 May - 8 Jun 19 3.3 0.0 2.3 hrs in May, 1 hr in Jun 3.3 OCT 7.8 9 - 22 Jun 19 0.3 0.0 0.3 NOV 1.8
23 Jun - 6 Jul 19 1.8 0.0 1 hr in Jun, 0.8 hr in Jul 1.8 DEC 1.8 7 - 20 Jul 19 12.6 0.0 12.6 2019 219.5 ANNUAL TOTAL
21 Jul - 3 Aug 19 4.3 0.0 4.3 hrs in Jul 4.3 4 - 24 Aug 19 3.3 0.0 3.3
25 Aug - 7 Sep 19 67.3 4.0
23.5 hrs in Aug, 43.8 hrs in Sep
67.3
8 - 21 Sep 19 47.4 0.0 47.4 22 Sep - 31 Sep 19 10.0 0.0 Pay period ends 5Oct19 10.0 100 Current/At end of FY19
Total Hrs End of FY19 252.5
FY20
Hrs
Started over at 250 on 1Oct19
1 - 5 Oct 19 1.9 0 Start of FY20 1.9 6 - 19 Oct 19 4.5 0 4.5
20 Oct -2 Nov 19 1.4 1.5 1.4 hrs in Oct 1.4 3 - 23 Nov 19 1.8 0 1.8
24 Nov - 7 Dec 19 0.0 0 0.0 8 - 21 Dec 19 1.8 2.5 1.8
22 Dec - 31 Dec 19 0.0 0 See 2020 spreadsheet for payroll ending 4Jan20
0.0
ANNUAL
TOTALS
219.5 12.3 11.4 Carry over to 2020
By Month
After Hours
Support Reported on MAR
AVBL BALANCE
(out of 250 hrs +
CONS added hrs) 97.5
FY20 started 1Oct19 238.6
AM
Actual
Hrs Worked
(outside of published afld hrs)
Pax Svc Actual
Hrs Worked
(outside of published afld hrs)
Remarks
AM
FY20 Hrs
Added Hrs Per
CONS,
appvd 2Sep20
Remarks
FY20 started 1Oct19 11.4 1 - 4 Jan 20 0.0 0.0 Pay period started 22Dec19 0.0
5 Jan 20 - 18 Jan 20 0.0 0.0 0.0 JAN 0.0
19 Jan - 8 Feb 20 3.3 6.5 3.3 hrs in Feb 3.3 FEB 8.8
9-22 Feb 20 2.5 0.0 2.5 MAR 2
23 Feb - 7 Mar 20 3.0 0.0 3 hrs in Feb 3.0 APR 0
8 - 21 Mar 20 2.0 0.0 2.0 MAY 41.6
22 Mar - 4 Apr 20 0.0 0.0 0.0 JUN 25.3
5-18 Apr 20 0.0 0.0 0.0 JUL 22.5
19 Apr - 9 May 20 0.0 0.0 0.0 AUG 78.8
10 - 23 May 20 39.9 0.0 39.9 SEP 66.5 *Originally marked as 66.6
24 May - 6 Jun 20 23.5 0.0
1.7 hrs in May, 21.8 hrs in Jun
23.5 OCT 39.9
7 - 20 Jun 20 3.5 0.0 3.5 NOV 62
21 Jun - 4 Jul 20 3.0 1.7 3 hrs in Jul 3.0 DEC 6.8
5 - 18 Jul 20 9.0 0.0 9.0 2020 354.2 ANNUAL TOTAL 19 Jul - 8 Aug 20 43.6 0.0 10.5 hrs in Jul; 33.1 hrs in Aug 43.6
9 - 22 Aug 20 23.1 0.0 23.1
23 Aug - 5 Sep 20 38.7 1.6 22.6 hrs in Aug; 16.1 hrs in Sep 38.7
6 - 19 Sep 20 28.4 0.0 28.4
20 Sep - 30 Sep 20 22.0 0.0 Pay period ends 3 Oct 20 22.0 100 Current/At end of FY20 (corrected from 115.1)
Total Hrs End of FY20 256.9
FY21
Hrs
Started over at 250 on 1Oct20
1-3 Oct 20 2.5 0 Start of FY21 2.5 4-17 Oct 20 20.6 0 20.6
18 Oct - 7 Nov 20 33.6 0 16.8 hrs in Oct; 16.8 hrs in Nov 33.6
8 - 21 Nov 20 45.2 0 45.2 22 Nov - 5 Dec 20 0.0 0 0.0
6 - 19 Dec 20 5.8 0 5.8
20 - 31 Dec 20 1.0 0 See 2021 spreadsheet for payroll ending 2Jan21
1.0
ANNUAL
TOTALS
354.2 9.8 108.7 Carry over to 2021
By Month
After Hours
Support Reported on MAR
AVBL BALANCE
(out of 250 hrs +
CONS added hrs) 93.1
FY21 started 1Oct20 141.3
AM
Actual
Hrs Worked
(outside of published afld hrs)
Pax Svc Actual
Hrs Worked
(outside of published afld hrs)
Remarks
AM
FY21 Hrs
Added Hrs Per
CONS,
appvd
21Jul21
Remarks
FY21 started 1Oct20 108.7 1 - 2 Jan 21 0.0 0.0 Pay period started 20Dec20 0.0
3 - 16 Jan 21 1.5 0.0 1.5 JAN 10.8
17 Jan - 6 Feb 21 10.8 0.0 9.3 hrs in Jan; 1.5 hrs in Feb 10.8 FEB 13.3
7 - 20 Feb 21 11.8 1.3 11.8 MAR 0
21 Feb - 6 Mar 21 0.0 0.0 0.0 APR 0
7 - 20 Mar 21 0.0 0.0 0.0 MAY 10.3
21 Mar - 3 Apr 21 0.0 0.0 0.0 JUN 5.6
4 - 17 Apr 21 0.0 0.0 0.0 JUL 38.7
18 Apr - 8 May 21 1.0 0.0 1 hr in May 1.0 AUG 56.2
9 - 22 May 21 5.0 0.0 5.0 SEP 22.3
23 May - 5 Jun 21 4.3 0.0 4.3 hrs in May 4.3 OCT 22.6 FY21 HOURS 6 - 19 Jun 21 4.1 0.0 4.1 NOV 0.5
20 Jun - 3 Jul 21 8.2 0.0 1.5 hrs in Jun; 6.7 in Jul 8.2 DEC 2.8
4 - 24 Jul 21 26.2 0.0 26.2 2021 183.1 ANNUAL TOTAL 25 Jul - 7 Aug 21 8.5 0.0 5.8 hrs in Jul; 2.7 hrs in Aug 8.5
8 - 21 Aug 21 43.6 0.0 43.6 22 Aug - 4 Sep 21 9.9 0.0 9.9 hrs in Aug 9.9
5 - 18 Sep 21 20.0 0.0 20.0 19 - 30 Sep 21 2.3 0.0 Pay period ends 2 Oct 21 2.3 100 Current/At end of FY21
Total Hrs End of FY21 265.9
FY22
Hrs
Started over at 250 on 1Oct21
1 - 2 Oct 21 0.0 0 Start of FY22 0.0 3 - 16 Oct 21 9.0 0 9.0
17 Oct - 6 Nov 21 13.6 0 13.6 hrs in Oct 13.6 7 - 20 Nov 21 0.5 0 0.5
21 Nov - 4 Dec 21 0.0 0 0.0 5 - 18 Dec 21 1.5 0 1.5
19 - 31 Dec 21 1.3 0 See 2022 spreadsheet for payroll ending 8Jan 22
1.3
ANNUAL
TOTALS
183.1 1.3 25.9 Carry over to 2022
By Month
After Hours
Support Reported on MAR
AVBL BALANCE
(out of 250 hrs +
CONS dd d h )84.1
FY22 started 1Oct21 224.1
AM
Actual
Hrs Worked
(outside of published afld hrs)
Pax Svc Actual Hrs
Worked (outside of published afld hrs)
Remarks
AM
FY22 Hrs
Added Hrs Per
CONS,
appvd
DATE
Remarks
FY22 started 1Oct21 25.9 1-8 Jan 22 0.0 0 Pay period started 19Dec21 0.0
9 - 22 Jan 22 7.8 0 7.8 JAN 11.4 Corrected on 6Jun22 from 12.7
23 Jan - 5 Feb 22 4.6 0 3.6 hrs in Jan; 1 hr in Feb 4.6 FEB 1.8
6 - 19 Feb 22 0.8 0 0.8 MAR 3.3
20 Feb - 5 Mar 22 0 0 0 APR 2
6 - 19 Mar 22 2 0 2 MAY 23.1 Reported 22.1; added addt'l 1 hr to June report to recoup
20 Mar - 9 Apr 22 1.3 0 1.3 hrs in Mar 1.3 JUN 30.2
10 - 23 Apr 22 0 0 0 JUL 6.8
24 Apr - 7 May 22 13.6 2 2 hrs in Apr, 11.6 in May for AM; 2 hrs in May for Pax Svc 13.6 AUG
8 - 21 May 22 0 0 0 SEP
22 May - 4 Jun 22 25.8 0 11.5 hrs in May, 14.3 hrs in Jun 25.8 OCT FY22 HOURS
5 - 18 Jun 22 11 0 11.0 NOV 19 Jun - 9 Jul 22 6.7 0 4.9 hrs in Jun; 1.8 hrs in Jul 6.7 DEC
10 - 23 Jul 22 1.2 0 1.2 2022 78.6 ANNUAL TOTAL 24 Jul- 6 Aug 22 3.8 0 3.8 hrs in Jul 3.8
7 - 20 Aug 22 0.0 21 Aug - 3 Sep 22 0.0
4 - 17 Sep 22 0.0 18 - 30 Sep 22 0.0 0 Current/At end of FY22
Total Hrs End of FY22 104.5
FY23
Hrs
Start over at 250 on 1Oct22
1 - 8 Oct 22 Start of FY23 0 9 - 22 Oct 22 0
23 Oct - 5 Nov 22 0 6 - 19 Nov 22 0
20 Nov - 3 Dec 22 0 4 - 17 Dec 22 0
18 - 31 Dec 22 0
ANNUAL
TOTALS
78.6 2 0 Carry over to 2023
By Month
After Hours
Support Reported on MAR
AVBL BALANCE
(out of 250 hrs +
CONS dd d h )145.5
FY23 started 1Oct22 250