Attachment 13 - Q and A_8 March 2022.pdf

PDF 394 KB Posted

Attached to
FOC Installation, ITB1101 to ITB6901 Federal contract opportunity
Solicitation number
FA301022R0010
Issued by
Department of the Air Force Air Education and Training Command

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers

8 March 2022

Question 1: The solicitation documents seem to infer that the proposed route for installation is not necessarily mandatory; Does the fiber have to be installed in the proposed route?

Answer 1: The proposed route is the best expected path based on known infrastructure. Proposals should be submitted based on the proposed path as identified in the solicitation documents.

Any deviations to the proposed routing shall be handled after contract award if it is discovered that differing site conditions exist. Any identified boring, ducting, and max-cell installation included in the solicitation documents MUST be accomplished/provided as part of the resultant contract regardless of any fiber installation route deviations.

Question 2: Is there a recommended manufacturer or part number for the Fiber Optic Distribution

Panels (FODP) required by the solicitation documents?

Answer 2: No specific requirement exists for the FODP’s as long as they are 36 port, new (not refurbished), can be mounted in the existing racks, and meet all necessary/applicable specifications as included in the solicitation documents.