STATEMENT OF WORK (SOW)
For
Fibers to Support Fam Camp, West and East Falcon
Keesler AFB MS
17 June 2019
Prepared By
38 ES/ENPW
4064 Hilltop Road Tinker AFB OK 73145-2713
Table of Contents Table of Contents
1.0 SCOPE
2.0 REQUIREMENTS
2.1 GENERAL REQUIREMENTS
2.1.1 Safety Requirements
2.1.1.1 Site Coordination
2.1.1.2 Confined Space
2.1.1.3 Accident/Incident Reporting and Investigation
2.1.1.4 Work Area (s)
2.1.1.5 Traffic Control
2.1.2 Security Requirements
2.1.2.1 Security Clearances
2.1.2.2 Operational Security (OPSEC)
2.1.3 Environmental Management
2.1.4 Permits
2.1.5 Integrated Product Team (IPT)
2.1.6 Quality Assurance
2.1.7 Contractor Personnel
2.1.7.1 Project Management
2.1.7.2 Site Point of Contact (POC)
2.1.7.3 Personnel Requirements
2.1.8 Warranty
2.1.9 Manuals and Practices
2.2 SPECIFIC REQUIREMENTS
2.2.1 Outside Plant Requirements
2.2.1.1 Existing Maintenance Holes
2.2.1.2 Measurements
2.2.1.3 Cable Racks and Cable Rack Supports
2.2.1.4 Labeling
2.2.1.4.1 Cable Tags
2.2.1.4.2 FODP Marking
2.2.1.4.3 New Ducts
2.2.1.5 FOC Terminations and Splicing
2.2.1.6 FOC Maintenance Loop
2.2.1.7 Outside Plant Installation
2.2.1.7.1 Conduit Systems and Inner-ducts Installation
2.2.1.7.1.1 Manhole/Handhole and Conduit System
2.2.1.7.1.2 Ductbank Infrastructure
2.2.1.7.1.3 Geo- textile Fabric Installation
2.2.1.7.1.4 Composition
2.2.1.7.1.5 Installation
2.2.1.7.1.6 Paved Surface Crossings
2.2.1.7.1.7 Conduit Protection
2.2.1.7.1.8 Bends and Sealing
2.2.1.7.1.9 NEMA 4X Enclosure & Pedestal
2.2.1.7.1.10 Entrance Conduits into Existing Maintenance holes
2.2.1.7.1.11 Pull Tape
2.2.1.7.1.12 Utility Separation
2.2.1.7.1.13 Spacers and Tracer Wire
2.2.1.7.1.14 Grounding and Bonding
2.2.1.7.2 Closure for Underground Optical Fiber Cables
2.2.1.7.3 Fiber Optic Distribution Panel (FODP)
2.2.1.7.4 Fiber Optic Cable Installation
2.2.1.7.4.1 Between HH-149J and CCTV Pedestal #1 NEMA Box
2.2.1.7.4.2 Between HH-149J and CCTV Pedestal #2 NEMA Box
2.2.1.7.4.3 Between HH-149E and CCTV Pedestal #3 NEMA Box
2.2.1.7.4.4 Between HH-149E and CCTV Pedestal #4 NEMA Box
2.2.1.8 Testing
2.2.1.8.1 Fiber Optic Cable Tests
2.2.1.8.1.1 Optical Attenuation
2.2.1.8.1.2 Distance
2.2.2 Site Restoration/Debris Removal
2.2.3 Service Outages
2.2.4 National Pollution Discharge Elimination System (NPDES)
2.2.5 Underground Utilities Markings
2.2.6 Identification/Marking
2.2.7 Installation Schedules
2.2.8 Weekly Status Reports
2.2.9 As-Built Drawings
2.2.10 Geospatial Deliverable
2.2.11 Installation Test Plan
2.2.12 Acceptance/Installation Test Report
2.2.13 Final Acceptance
2.2.14 Deliverable Summary
3.0 GENERAL INFORMATION
3.1 Period of Performance
3.2 Place of Performance
3.3 Hours of Operation
3.4 Holidays/Down Days
3.5 Base Support
3.6 Minimum Contractor Qualifications
4.0 APPENDICES
4.1 Appendix A. APPLICABLE STANDARDS
4.2 Appendix B. List of Acronyms
5.0 Sketches: Proposed Cable Routes
1.0 SCOPE.
This Statement of Work (SOW) defines the requirements for the Contractor to engineer, furnish, install, and test (EFI&T) new six (6) strands single mode (SM) fiber optic cable (FOC) from existing HH-149J to CCTV Pedestals 1&2, and from existing HH-149E to CCTV Pedestals 3&4; new hand holes, and conduit systems. Reference Sketches 1 & 2. The Contractor shall provide all equipment, tools, materials, supplies, transportation, labor, supervision, management, and other incidentals necessary to meet the requirements as stated in this SOW; no equipment, supplies, or material, will be provided by the government. All equipment, supplies, or materials installed as part of the Customer- Owned Outside Plant Telecommunications Infrastructure will be new and not refurbished, and must be rustproof and corrosion-resistant, due to the nature of the environment.
2.0 REQUIREMENTS.
2.1 GENERAL REQUIREMENTS.
2.1.1 Safety Requirements.
2.1.1.1 Site Coordination.
The Contractor shall meet with the base safety officer immediately upon arrival on site for review of the specific safety requirements prior to installation.
2.1.1.2 Confined Space.
The Contractors and Sub-contractors entering spaces on Keesler AFB (KAFB), MS are responsible for the safety of their personnel and for their own confined space program as outlined in local, state, federal (OSHA CFR 29 Part 1910-268) compliance standards. The Primary Contractor (Prime) is responsible for all sub- contractor confined space operations. The Contractor will notify the KAFB Fire Department on-duty dispatch controller twenty four (24) hours prior to entering any maintenance hole, if emergency services assistance is desired.
2.1.1.3 Accident/Incident Reporting and Investigation.
The Contractor shall record and report all available facts relating to each instance of injury to either Contractor or Government personnel to the Base Safety Office unless otherwise stated in the SOW.
The Contractor will secure the scene of any accident and wreckage until released by the accident investigative authority through the Base Point of Contact (POC). If the Government elects to conduct an investigation of the incident, the Contractor will cooperate fully and assist the Government personnel until the investigation is completed.
2.1.1.4 Work Area(s).
At day’s end, the Contractor shall remove all debris and surplus materials from the work place.
Safety barriers will be in place to protect unfinished work site at the end of the day. All open holes or trenches will be completely enclosed by flexible orange construction safety fencing, or other safety barriers, at the end of the work day. Under no circumstances will any equipment or materials be left unattended within the designated Keesler AFB MS. On work sites outside the base perimeter, the Contractor will coordinate with (and abide by the requirements of) the appropriate local, state, and federal agencies to ensure work areas are safe at day’s end.
2.1.1.5 Traffic Control.
In the event base vehicular traffic is to be disrupted by trenching or horizontal directional boring, the Contractor shall make appropriate notifications NLT 10 calendar days in advance to 81 CS/SCXP so that Base Security Forces and Emergency Services personnel can be informed of the planned disruptions.
2.1.2 Security Requirements.
The Contractor shall process and provide a Site Visit Request Letter to 81 CS/SCXP within 5 calendar days after contract award. This spreadsheet will identify the names (as shown on the driver’s license), driver’s license numbers and state of issue, and birth date of the personnel who will be performing work under this SOW, company name, address, phone number and contract number, start date and end date. This information is required to grant access to the base. If required by the base, the Contractor will provide identification badges for their employees. All Contractor personnel shall wear these badges while on duty on the Government site. The badges will identify the individual, company name, and be clearly and distinctly marked as Contractor and be in accordance with base regulations
2.1.2.1 Security Clearances.
Stated work and associated products will be performed at the UNCLASSIFIED level. However, some of this work will take place in secure areas where Contractor employees must be escorted at all times.
The Contractor must coordinate access to secure areas at least five (5) working days ahead of time. It is the Government's responsibility to provide escorts.
2.1.2.2 Operational Security (OPSEC).
Network infrastructure drawings (MHDS, MH/HH locations, fiber paths, etc.) are on the 81 CS Critical Information List and must be protected. The Contractor shall take appropriate measures to protect detailed information pertaining to the EFI&T effort, to include appropriate marking of documents as “For Official Use Only (FOUO),” and ensuring limited distribution of documents and schematics/drawings to only those individuals with a valid need to know. IAW AFI 10-701, OPSEC Considerations, the contractor shall develop an OPSEC plan to ensure the protection of FOUO data either furnished by the government or produced by the contractor. The contractor shall provide an OPSEC plan no later than 10 days prior to arrival on site.
2.1.3 Environmental Management.
The Contractor shall comply with the most stringent environmental federal, state, and local laws and regulations; and Air Force policies, instructions, and plans. The federal Government is not exempt from compliance with environmental regulations. The Contractor shall maintain an awareness of changing environmental regulatory requirements to avoid environmental deficiencies for activities on Keesler AFB MS. The Contractor shall ensure their Sub-contractors comply with these specifications.
2.1.4 Permits.
The Contractor shall complete and process all permits required to complete the installation prior to any trenching, or modifications to a facility, maintenance hole or hand hole; for example, the Base Civil Engineering Work Clearance Request, a digging permit, (AF Form 103) and Base Civil Engineer Work Request (AF Form 332). AF Form 103 and AF Form 332 and any other required permits (as determined by Base Civil Engineering (BCE) and/or 81 CS/SCXP, etc.) will be submitted at IAW local procedures. All utility markings, flags, etc. will be maintained by the contractor after the responsible work center/shop identifies/locates them. If a utility is severed or damaged due to neglect or if attributed to the fault of the contractor, then the contractor will repair and return the utility back to the same condition it was in prior to the damage. The form(s)/permits will be submitted within 10 calendar days after award.
2.1.5 Integrated Product Team (IPT).
The Contractor shall chair a weekly IPT meeting that includes Contractor representatives, the Cyberspace Integrator-Base (CSI-B), 81 CS/SCXP PM, and other base personnel as requested. The Contractor will provide an agenda and a worldwide “Meet Me” teleconference capability for the duration of the project. The purpose of the IPT meeting is to discuss project progress, problems being encountered, and other information necessary/beneficial to ensure success and timely completion of contract requirements. The Contractor will record meeting minutes and distribute to the attendees.
2.1.6 Quality Assurance.
The Contractor shall provide a Quality Control Plan for the life of the project. The Contractor’s quality assurance evaluator will assist the Government representative in performing random spot checks and system acceptance tests. The Contractor shall be responsible for identifying system and outside plant deficiencies and/or discrepancies throughout the life of the project. A weekly report (soft copy) will be submitted indicating progress/status and listing any deficiencies/discrepancies found and actions to correct them.
2.1.7 Contractor Personnel.
2.1.7.1 Project Management.
The Contractor shall provide a Project Manager (PM) and alternate(s) responsible for contract performance and continuity. The Contractor shall identify the Project Manager’s or alternate's range of authority to act for the Contractor relating to daily contract operation.
2.1.7.2 Site Point of Contact (POC).
The Contractor shall designate the Contractor's on-site team leader and alternate(s) as the Site POC for individual projects in their Site Visit Request Letter. The Site POC or alternate(s) will be on site during duty hours until project completion. The Site POC will be the interface for all work site communications with the Government, including quality, safety, and discrepancy matters.
2.1.7.3 Personnel Requirements.
The Project Manager, Site POC, and respective alternate(s) will be able to read, write, speak, and understand English.
2.1.8 Warranty.
The Contractor shall provide a one year warranty or manufacturer’s standard commercial warranty, whichever is longer. This warranty shall include a one year workmanship warranty. The warranty period shall start from the date of system and/or project acceptance. The Contractor shall provide written procedures and required information for warranty services at or prior to site acceptance.
2.1.9 Manuals and Practices.
The Contractor shall provide the latest version of operation, installation, and maintenance manuals and practices/users guide for each system installed as provided by the original manufacturer with all new equipment should be provided to 81 CS/SCXP PM.
2.2 SPECIFIC REQUIREMENTS.
The Contractor shall provide all equipment, tools, materials, supplies, transportation, labor, supervision, management, and other incidentals necessary to meet the requirements as stated in this SOW. The Contractor shall comply with the current TIA (Telecommunications Industry Association) telecommunication installation and testing commercial standard and base installation standards. All equipment, supplies, and materials provided will be new and not refurbished.
2.2.1 Outside Plant Requirements.
2.2.1.1 Existing Maintenance Holes.
The Contractor shall design and install Customer-Owned Outside Plant Telecommunications Infrastructure in accordance with TIA-758-B. The cable installation will be coordinated with the 81 CS/SCXP so that any impact on the building users is properly coordinated. The sequence of installation is at the Contractor’s discretion. See Sketches – Drawings, for reference and estimated distances of existing and proposed infrastructure and cable routes. This is only a proposed solution.
The Contractor is free to make any recommendations pertaining to the accomplishment of this requirement in their proposal.
2.2.1.2 Measurements.
Any distances provided in this SOW are approximations and should NOT be used for ordering materials (cable, innerduct, etc.) or determining duct lengths. The contractor shall field verify measurements.
2.2.1.3 Cable Racks and Cable Rack Supports.
Cable racks will be installed in handhole and maintenance holes as required. Splices will not be supported by the cables that enter each end of the splice case. The splices will be supported by cable hooks under the splice case. Telecommunications industry standard cable hooks of the appropriate length will be provided to support cables and splice cases. The cable hooks will be secured using cable rack locking clips. All cables will be supported using racking clips, cable racks, and cable hooks.
2.2.1.4 Labeling.
The Contractor shall label all equipment and cables they install in accordance with (IAW) TIA-606-B and as directed by 81 CS/SCXP.
2.2.1.4.1 Cable Tags.
All tags will be permanently labeled, easily visible and corrosion resistant. Install cable tags in all maintenance holes/hand holes, cable vaults, pull boxes and building entrance terminal locations.
When cables pass through a MH/HH, put a tag on the cable, approximately 2 feet from each duct entrance, or on each side of the splice case, if one exists. If there is a slack loop in the cable in the MH/HH, put a tag on the loop. Information on the tag will conform to the system used by local maintenance personnel to identify cables.
Example (fiber): FO 4309 – Building fiber is being installed for
4705-4309 – ITN / Building number
1-12 SM or MM – Number and type
2.2.1.4.2 FODP Marking.
FODP will be stenciled/marked with black ink or paint or adhesive backed decals in letters and numbers. If the manufacturer has not identified the sequence in which ports on FODPs (pigtail modules) are counted, the Contractor will provide designation labels/strips to identify the sequence in which they are counted. Each splice tray will be marked to identify the fiber count contained in the splice tray. The marking will identify the FODP by number (building number), cable number, and count.
FODP: For example: FODP-241
FO 241-100, 1-12
FO 241-101, 13-24
FO 241-102, 25
2.2.1.4.3 New Ducts.
New ducts will be permanently labeled on the wall of each building/maintenance hole (MH)/handhole (HH) indicating the connecting building/maintenance hole/handhole at the other end of the duct (for example, “To MH-306H”). The same information will appear on the Contractor’s completed as-built-drawings.
2.2.1.5 FOC Terminations and Splicing.
Fiber optic cable termination will be SC connectors, with no splicing (Home Run installation), and no jumpers. The US color code will be used when terminating the fiber optic cables. The Contractor will determine whether or not there is some practical reason for an intermediate splice in the cable at some MH/HH between the cable end points, and consist of fusion splices in a high quality re-enterable splice case. A coil of 25 feet of cable will be provided on each cable entering or leaving a splice case in a MH or HH.
2.2.1.6 FOC Maintenance Loop.
Minimum of 25 feet of fiber optic cable at every MH/HH location, starting/ending in the first maintenance hole outside each end building (i.e. the first maintenance hole outside of each building will contain a 25 foot maintenance loop). All maintenance loops installed within maintenance holes must be supported by two cable hooks. Cable hooks are to be positioned so the highest one supports the underside of the top of the coil and the bottom hook supports the underside of the bottom of the coil. The maintenance loop will have a cable tag. The same information will appear on the Contractor’s completed as-built-drawings.
2.2.1.7 Outside Plant Installation.
The Contractor shall design and install Customer-Owned Outside Plant Telecommunications Infrastructure IAW TIA-758. Each cable installation and cut-over will be coordinated with the 81 CS/SCXP. The sequence of installation is at the Contractor’s discretion. See Attachment 1 for reference and estimated distances of existing and proposed cables routes.
2.2.1.7.1 Conduit Systems and Inner-ducts Installation.
The Contractor shall install the following:
2.2.1.7.1.1 Manhole/Handhole and Conduit System.
Install four (4) 4’W x 4’L x 4’H (interior dimensions) handholes (to be designated as New HH-149- J1, New HH-149-J2, New HH-149-H1, and New HH-149-F1 for the purposes of this requirement.
The handhole will be precast with an AASHTO (American Association of State Highway and Transportation Official) wheel load rating of H-20 or European equivalent; with predrilled duct entry holes [sealed with knockouts configured for splayed entry in the end walls)] with duct terminators to accept 4-inch I.D. schedule 40 conduit; manufacturer installed wall inserts for attaching cable rack hardware; equipped with cable racks, sump, pulling-in irons, and a ground rod on the outside of MH/HH. The cover will be round and imprinted with “Communication”). Note: It is understood that some handholes are precast with bonding ribbon or some similar connection to the handhole rebar and therefore do not require a ground rod. This method of grounding in lieu of a ground rod is satisfactory just as long as the impedance to ground is at the acceptable level. See Sketch.
2.2.1.7.1.2 Ductbank Infrastructure.
Install 4” & 2” duct banks IAW the following Table:
From Maintenance
Hole
To Maintenance
Hole
Quantity Size (inches)
Approx.
Distance
(Feet)
Figure Comment
Existing HH- 149J
New HH-149- J1
2 4 730 Sketch 1 Coordinate with base CE for method of crossing paved surface
New HH-149- J1
New HH-149- J2
2 4 600 Sketch 1 Coordinate with base CE for method of crossing paved surface.
New HH-149- J2
CCTV Pedestal #1 NEMA Box
1 4 700 Sketch 1 Coordinate with base CE for method of crossing paved surface.
Existing HH- 149J
CCTV Pedestal #2 NEMA Box
1 4 270 Sketch 1 Coordinate with base CE for method of crossing paved surface.
Existing HH- 149H
New HH-149- H1
2 4 700 Sketch 2 Coordinate with base CE for method of crossing paved surface.
New HH-149- H1
CCTV Pedestal #3 NEMA Box
1 4 670 Sketch 2 Coordinate with base CE for method of crossing paved surface.
Existing HH- 149F
New HH-149- F1
2 4 700 Sketch 2 Coordinate with base CE for method of crossing paved surface.
New HH-149- F1
CCTV Pedestal #4 NEMA Box
1 4 450 Sketch 2 Coordinate with base CE for method of crossing paved surface.
2.2.1.7.1.3 Geo- textile Fabric Installation.
Geo-textile fabrics IAW the following Table:
From Maintenance
Hole
To Maintenance
Hole
Quantity Approx.
Distance
(Feet)
Figure Comment
Existing HH- 149J
New HH-149- J1
One (1) 3”x 3 cell 730 Sketch 1 (Will be detectable type) in one of the new 4” PVC conduit.
New HH-149- J1
New HH-149- J2
One (1) 3”x 3 cell 600 Sketch 1 (Will be detectable type) in one of the new 4” PVC conduit.
New HH-149- J2
CCTV
Pedestal #1 NEMA Box
One (1) 3”x 3 cell 700 Sketch 1 (Will be detectable type) in of the new 2” PVC conduit.
Existing HH- 149J
CCTV
Pedestal #2 NEMA Box
One (1) 3”x 3 cell 270 Sketch 1 (Will be detectable type) in of the new 2” PVC conduit.
Existing HH- 149H
New HH-149- H1
One (1) 3”x 3 cell 700 Sketch 2 (Will be detectable type) in one of the new 4” PVC conduit.
New HH-149- H1
CCTV
Pedestal #3 NEMA Box
One (1) 3”x 3 cell 670 Sketch 2 (Will be detectable type) in of the new 2” PVC conduit.
Existing HH- 149F
New HH-149- F1
One (1) 3”x 3 cell 700 Sketch 2 (Will be detectable type) in one of the new 4” PVC conduit.
New HH-149- F1
CCTV
Pedestal #4 NEMA Box
One (1) 3”x 3 cell 450 Sketch 2 (Will be detectable type) in of the new 2” PVC conduit.
2.2.1.7.1.4 Composition.
The ducts will be 4-inch inside diameter (I.D.) round or metric equivalent. The ducts will be made of EPC-40 Polyvinyl Chloride (PVC) (Schedule 40) IAW NEMA TC-2. For unique/site specific situations, the ducts will be made of EPC-80-PVC (Schedule 80) IAW NEMA TC-2. Schedule 80 PVC will be limited to risers, all above ground conduit, and under the roadway/parking pavement.
High density polyethylene (HDPE) SDR 13.5 will be used when directional boring is used. The ducts will be appropriately labeled indicating the composition material. Ducts will have a sleeve or bell-end type coupling and will be watertight when assembled. In addition, the Contractor will adhere to any additional Keesler AFB/site specific requirements.
2.2.1.7.1.5 Installation.
Installation of underground conduits/ducts will be IAW RUS Bulletin 1751F-643 and RUS Bulletin 1753F-151. Ducts installed beneath roads, sidewalks, parking areas, other paved surfaces or areas to be paved, etc. will be installed a minimum of 36" below grade. In a MH with knockouts, ducts will start at the bottom knockout, allowing for upward expansion in the MH. All ducts not installed under roads, sidewalks, parking areas, or areas to be paved, etc. will have a minimum of 36 inches ground cover, where possible. The Contractor will provide other protective measures, concrete cap, etc., in those areas where the minimum ground cover cannot be achieved. Grading of ducts will be accomplished IAW RUS Bulletin 1751F-643. All conduits will be continuous between MH/HHs (i.e., no breaks or separations in the conduit runs between MH/HHs).
2.2.1.7.1.6 Paved Surface Crossings.
The Contractor shall be responsible for any required trenching and/or boring necessary to lay the duct system. The Contractor is also responsible for backfilling ditch lines and compaction of fill materials with appropriate compaction tools. Backfill material shall be clean and free from all organic material, clay, marl, or unstable materials, debris, lumps, or broken paving. NO rocks or stones larger than 3 inches in diameter shall be allowed in backfill. Material for backfill may be material resulting from excavation, if it meets the above requirements. Unless specified otherwise, Directional Drilling shall be used for all paved surface crossings (see Table “Directional Drilling:
PVC Duct-banks” for details). Directional drilling shall be used for sidewalks, parking lot driveways, road crossings, taxiways, runways, etc.
2.2.1.7.1.7 Conduit Protection.
The Contactor shall install the appropriate physical protection required [(concrete encasement, steel tube (casing)] for buried PVC conduits or HDPE rsanderolled pipe, consistent with commonly accepted telecommunications industry practices relative to the task and to the environment in which they are installed and the loads (H-5, H-10, H-20, railroads, flight line, etc.) to which they are expected to be exposed. Type of protection may be dependent upon the specific application and will be IAW applicable federal, state or local (Keesler AFB MS Civil Engineering construction requirements) procedures. However, at a minimum, nonmetallic conduits will be encased in concrete of minimum 3000 lb. /in2 compressive strength where vehicular traffic is above the pathway. The encasement will be concrete of a wet type mix and will be placed in such a manner as to ensure the concrete completely surrounds all conduits and no air voids are trapped in the mix.
2.2.1.7.1.8 Bends and Sealing.
All bends between MHs will be a minimum of ten times (10X) the diameter of the duct size (i.e., 4 inch duct = 40 inches) with the sum of bends in all directions not exceeding a total of 90 degrees where practical. Coordinate with 81 CS/SCXP if runs have bends that total more than 90 degrees is required. Ducts will have bell ends and enter a maintenance hole perpendicular to the surface of the wall through which it is entering. All ducts/inner ducts entering maintenance holes must be sealed.
Universal duct plugs or removable putty sealants may be used. Upon completion of conduit sections, a test mandrel ¼” (6.4mm) smaller than the inside diameter of the conduit will be pulled through two diagonally opposite ducts to ensure proper alignment. In addition, all ducts will be cleared of loose materials such as concrete, mud, dirt, stones, etc.
2.2.1.7.1.9 NEMA 4X Enclosure & Pedestal.
The Contractor shall install four (4) each NEMA 4X enclosures and a pedestals. The Contractor shall determine the size of the enclosure based on FODP size to be accommodated and conduit coming into the enclosure, etc. The enclosure door will have a locking mechanism capable of accepting a padlock to be provided by the 81 CS/SCXP. Reference Sketches 1 & 2.
2.2.1.7.1.10 Entrance Conduits into Existing Maintenance holes.
When new entrance conduits/ducts or sleeves are required, the Contractor will bore and install the necessary holes and install the ducts or sleeves, if a knockout does not exist. Contractor bored holes will be fitted with duct terminators to accept 4-inch I.D., schedule 40 (or schedule 80) conduit.
Penetration will not be in such a location through the wall as to block use of existing ducts in the maintenance hole. New ducts will be a minimum of 18 inches from either the maintenance hole floor or ceiling, if practical. The minimum bending radius for entry conduit/ducts will be no less than 10 times the inside diameter of the conduit. Ducts and openings around ducts will be sealed to prevent moisture from entering the maintenance holes. All duct entrances will be flush/beveled or use terminator cap with the MH/HH interior wall surface.
2.2.1.7.1.11 Pull Tape.
All newly installed ducts left vacant will be provided with a pull tape with a waterproof, corrosion resistant, pre-lubricated flat woven polyester pull tape with sequential footage markings, (1250 lb.
pulling strength) for future cable installations. The pull tape will extend into the maintenance holes/handholes and be secured to a cable rack or pulling iron, etc.
2.2.1.7.1.12 Utility Separation.
When communications ducts cross either power duct or buried power cable, maintain a minimum separation of 3 inches of concrete or 12 inches of well-tamped earth between the two or 12 inches of well tamped earth when parallel; for pipes (e.g., gas, water, oil) maintain 6 inches when crossing or 12 inches when parallel.
2.2.1.7.1.13 Spacers and Tracer Wire.
Along the length of the duct run, if the ducts are installed by trenching, spacers will be placed at five
(5) foot intervals and cable warning tape will be buried one (1) foot below the surface and will follow the duct route. The tape will be a minimum of three inches wide and orange in color with the appropriate warning message. All new tracer wire installed for this project needs to have a wire nut and label installed at all wire ends, and those wire ends secured but not connected to grounds. The tracer wire will be exposed; free from the conduit and capped (insulated). The tracer will be secured and routed to the maintenance hole or handhole neck to a point where maintenance personnel may access the wire without having to enter the maintenance hole/handhole, and tagged with a label so indicating it as a “Duct Tracer Wire to xxx - Do Not Remove (where xxx is the other end of the wire).” Tracer wires will not be connected to any grounding system. Tracer wire will be pulled back from building entrances until it is underground to prevent lightning damage.
2.2.1.7.1.14 Grounding and Bonding.
In the Equipment room/Mechanical room and NEMA enclosures in which the optical fiber cable is to be terminated, there is either a telecommunications main grounding busbar (TMGB) or a telecommunications grounding busbar (TGB); if grounding busbar doesn’t exist in the equipment room/mechanical room, then the Contractor will provide it and bonded to earth ground. The optical fiber cable shield (armor) will be connected to the busbar using hardware and a grounding conductor (No. 6 AWG green insulated wire) suitable for the application. The grounding conductor will be tagged with a nonmetallic tag as close as practicable to the point of termination in a readable position.
The information on the tag will contain the following information “If this connector or wire is loose or must be removed, please call Base Communications Office” or some similar wording. Although it is not anticipated that any splicing will be required in a maintenance hole, should there be some practical reason that a splice be made, the cable shield (armor) will be bonded and continuous throughout the cable length. In addition, the splice case will be bonded to the maintenance hole bonding ribbon, if it exists.
2.2.1.7.2 Closure for Underground Optical Fiber Cables.
The closure will be sealed and suitable for enclosing a splice organizer in a protective housing. The splice organizer will consist of splice trays and protective sleeves, shield bond connectors, and ancillary hardware necessary to house fiber optic splices. The splice organizer will house a minimum of 36, and 48 fiber optic fusion splices in a neat and orderly fashion. The splice organizer will provide individual support for each splice. The organizer will allow for one meter of fiber to be stored without kinks, twists, or micro-bends. The organizer will be suitable for reentry, for future maintenance or modification, without damage to the fiber or splices. The closure will be high quality re-enterable splice case or equivalent for making a straight, butt, or branch splice and will protect the splice and maintain cable shield electrical continuity in a manhole, or handhole environment and suitable for pressure testing. The number of cable ports in and out of the closure, along with any necessary washers or any plugs for unused ports, will be suitable for the particular application.
2.2.1.7.3 Fiber Optic Distribution Panel (FODP).
The Contractor shall install one (1) 12 port FODP in CCTV Pedestal #1 NEMA Box, one (1) 12 port FODP in CCTV Pedestal #2 NEMA Box, one (1) 12 port FODP in CCTV Pedestal #3 NEMA Box, and one (1) 12 port FODP in CCTV Pedestal #4 NEMA Box.
2.2.1.7.4 Fiber Optic Cable Installation.
The Contractor shall install single mode (SM), loose buffer tube, water blocked, outside plant (OSP) cable suitable for underground applications. The intent is to install the cable in one continuous length, to the extent that it is practical. The cable will meet RUS 7 CFR 1755.900 criteria; will comply with industry standards with regard to manufacturers’ cable marking, jacket, rip cords, water blocking, fiber color coding, jacketing materials, etc. In addition, the fibers will comply with industry standards with regard to mode field diameter, core cladding concentricity, attenuation, and dispersion characteristics at 1310 nm and 1550nm. The cable will be installed along the recommended paths in the paragraphs below:
2.2.1.7.4.1 Between HH-149J and CCTV Pedestal #1 NEMA Box
The Contractor shall install approximately 2150’ of new 6 strand SM FOC from HH-149J to CCTV Pedestal #1 NEMA Box via new HH-149-J1, and new HH-149-J2. Splice the 6 strand SM FOC at the existing HH-149J to the existing 12 strand SM FOC which terminate in B2801, and terminate new six (6) strands FOC in new 12 port FODP in the CCTV Pedestal #1 NEMA Box. Reference Sketch 1.
2.2.1.7.4.2 Between HH-149J and CCTV Pedestal #2 NEMA Box
The Contractor shall install approximately 325’ of new 6 strand SM FOC from HH-149J to CCTV Pedestal #2 NEMA Box. Splice the 6 strand SM FOC at the existing HH-149J to the existing 12 strand SM FOC which terminate in B2801, and terminate new six 6 strand FOC in new 12 port FODP in the CCTV Pedestal #2 NEMA Box. Reference Sketch 1.
2.2.1.7.4.3 Between HH-149E and CCTV Pedestal #3 NEMA Box
The Contractor shall install approximately 3425’ of new 6 strands SM FOC from HH-149E to CCTV Pedestal #3 NEMA Box via HH-149F, HH-149G, HH-149H, and new HH-149-H1. Splice new 6 strands SM FOC at the existing HH-149E to the existing 12 strands SM FOC which terminate in B2801, and terminate new six (6) strands FOC in new 12 port FODP in the CCTV Pedestal #3 NEMA Box. Reference Sketch 2.
2.2.1.7.4.4 Between HH-149E and CCTV Pedestal #4 NEMA Box
The Contractor shall install approximately 1850’ of new 6 strand SM FOC from HH-149E to CCTV Pedestal #4 NEMA Box via HH-149F and new HH-149-F1. Splice new 6 strand SM FOC at the existing HH-149E to the existing 12 strand SM FOC which terminate in B2801, and terminate new six 6 strand FOC in new 12 port FODP in the CCTV Pedestal #4 NEMA Box. Reference Sketch 2.
2.2.1.8 Testing.
The Contractor shall furnish all test equipment and personnel required to conduct testing. The Contractor shall record all inspections and tests as they are accomplished and make all test sheets/results available for 81 CS/SCXP representative as tests are completed. The Contractor shall notify the 81 CS/SCXP at least 5 calendar days prior to any testing. All testing will be IAW accepted telecommunications industry standards for the type of test being conducted. The Contractor shall provide test reports to the government within 10 calendar days of completing the testing. Contractor is required to locate/repair any testing irregularities if caused by the installation.
Any splicer’s errors detected will be corrected in the splice in which they were made. It is assumed that the cable is delivered fault free from the manufacturer. No cable faults or splicer’s errors are allowed in the new cable. Contractor is required to locate and repair cable faults or splicer’s errors if caused by the installation.
2.2.1.8.1 Fiber Optic Cable Tests.
All strands of all fiber optic cables will be tested IAW TIA 526-7 Measurement of Optical Power Loss of Installed Single-mode Fiber Cable Plant, or equivalent. As a minimum, the following tests will be performed. Both Optical Time Domain Reflectometer (OTDR) and Optical Power Meter tests will be used for all end-to-end circuits. Between FODPs, bi-directional testing at 1310 nm and 1550 nm is required. For incomplete circuits that end in manholes, only 1 way OTDR testing is required.
NOTE: Testing of the Fiber Optic Cables on the reel will be provided to the 81 CS/SCXP prior to installation.
2.2.1.8.1.1 Optical Attenuation.
End to end attenuation tests will be conducted on all fiber optic cable strands. Tests will be accomplished to ensure the installed cable is within the specified parameters
2.2.1.8.1.2 Distance.
Test to determine the installed cable length between optical patch panels. All strands of all fiber optic cables will be tested.
2.2.2 Site Restoration/Debris Removal.
The Contractor shall restore all disturbed grounds to the “as found” condition or better after installation. Base grounds restoration requirements will be complied with. Common use areas will be restored to their original condition. The Contractor will be responsible for disposing of all residues from this project off base and in accordance with Federal, state and base environmental laws and regulations. All residue produced by directional drilling operations (i.e., slurry) will be disposed of off base on the same day the residue is produced, at an appropriate disposal facility at the contractor’s expense, IAW federal, state, local and Keesler AFB MS environmental laws and regulations. Under no circumstances will the contractor stage or store boring residue in slurry ponds or other containment areas on Keesler AFB MS.
2.2.3 Service Outages.
The Contractor shall be responsible for preventing any unscheduled (i.e. cutting or disabling any in-service cables or equipment.), Contractor-caused, interruptions of communications capabilities that are properly identified. The Contractor will coordinate planned outages with the site POC at least 10 calendar days in advance of the outage if the implementation necessitates disruption of service, (e.g., communications, electrical, or other utilities).
2.2.4 National Pollution Discharge Elimination System (NPDES).
If required by Base Civil Engineer (BCE), the Contractor shall obtain approvals for NPDES at State and/or Federal level [in some locations this may be called the Storm Water Pollution Prevention Plan (SWPPP)]. The storm water/environmental plan is the sole responsibility of the Contractor. Base Civil Engineering/CEV will review and advise to ensure minimum standards and storm water controls/BMPs are in place to ensure compliance; this is a compulsory item in the SOW and contract.
The Contractor will implement storm water controls/BMPs to ensure sediment, as a result of storm water runoff, does not enter storm drainage channels and/or inlets.
The Contractor shall conduct an initial meeting within 10 days of the Contractor site survey with the base environmental office to identify NPDES preparations and/or the storm water/environmental plan.
The Contractor shall review the NPDES requirements applicable to the base; develop a plan to comply with the NPDES; obtain approval of the NPDES plan from all appropriate government agencies; and comply with any other applicable state requirements for construction.
The Contractor shall implement, monitor and manage the NPDES Plan.
2.2.5 Underground Utilities Markings.
The Contractor shall coordinate with base agencies to ensure markings are placed over existing base infrastructure prior to digging or directional drilling and will take precautions to protect existing infrastructure. Contractor will be responsible for costs associated with repair of any damages caused during installation when the infrastructure is clearly marked. The AF Form 103 (digging permit) will be submitted through Civil Engineering 45 calendar days in advance of digging activities. Contractor is responsible for maintaining all markings.
2.2.6 Identification/Marking.
The Contractor shall clearly mark all Contractor-Furnished Property and Equipment (CFP/CFE) with their company's name. The Contractor will place an easily read, very visible, sign (minimum 8.5" x 11") on large containers, construction equipment, or un-manned rental vehicles while on the Government installation indicating the company name and both the Contractor and Site POC's names and local telephone numbers.
2.2.7 Installation Schedules.
The Contractor shall provide a complete milestone schedule that denotes project activities to include time-phased start and completion dates for the project and sub-projects associated with the installation of the components and system.
2.2.8 Weekly Status Reports.
The Contractor shall prepare a Weekly Status Report and distribute to IPT members. The purpose of the report is to inform IPT members of project progress, problems being encountered, and other topics necessary/beneficial to ensure success and timely completion of the contract requirements.
The Status Report and meeting agenda may be combined as long as the resulting report contains all the required elements and contains sufficient detail to serve as project record.
2.2.9 As-Built Drawings.
The government will supply existing system drawings, and the Contractor shall provide updated drawings in Visio for building and rack elevation; Visio and .pdf for OSP. These drawings will depict the entire pathway and details of the installation, including but not limited to: labeling, cables, innerducts and maintenance holes/handholes, conduits, maintenance loops, distances, bores, trenches, building entrances. Detailed butterfly drawings will also be required. If the existing cable diagram or butterfly drawings are not available; the contractor will create the missing cable diagram/ butterfly drawings as well as, add the components used in this project. The Contractor will record/deliver geospatial data of new outside plant distribution system.
2.2.10 Geospatial Deliverable.
The Contractor shall record geospatial data and provide as-built documentation (shape files) of all new installed MH system components (including metadata) compatible with the Cyberspace Infrastructure Planning System (CIPS) Visualization Component (CVC) drawing system. Data points will be recorded at the center of each manhole/handhole lid and at intervals not to exceed 25 feet along cable routes. Sufficient data points will be recorded to capture any change in direction along the route. All GPS coordinates will have +/- 3 feet accuracy for all readings. The government is responsible for providing the Contractor with a copy of the installation’s most current GeoBase Common Installation Picture (CIP), and current CVC drawings of the areas of interest. The government will review the shape files in CVC and transcribe the information to the CVC system.
Shape files will be delivered upon project completion
2.2.11 Installation Test Plan.
The Contractor shall provide a test plan as to how the system will be pre-tested, in-progress-tested, post-tested and cut-over plan to demonstrate to the Government that the system is fully operational and meets or exceeds the specified requirements and that the system is fully ready to be placed into service. The Contractor will test the system to demonstrate its proper performance to the Government quality assurance representative. These tests will be accomplished prior to the system being placed into service.
2.2.12 Acceptance/Installation Test Report.
The Contractor shall provide an installation test report of the results of the testing accomplished under the installation test plan. The Test Report(s) will be provided to the Government no later than 10 calendar days after test(s) have been completed.
2.2.13 Final Acceptance.
The Contractor shall schedule a final project walk-through with the Base POC. This should be scheduled 10 calendar days prior to acceptance.
2.2.14 Deliverable Summary.
All deliverables are subject to Government acceptance and approval. They will meet professional standards and the requirements set forth in this Task Order. All deliverables will be produced using recommended software tools/versions as accepted by the Government.
3.0 GENERAL INFORMATION.
3.1 Period of Performance.
The period of performance for the project will be determined based on the proposed schedule and actual contract award date not to exceed 120 days.
3.2 Place of Performance.
The place of performance is Keesler AFB MS.
3.3 Hours of Operation.
The Contractor will routinely work during normal duty hours, 0700-1700 Hrs. of the site. However, mission requirements may necessitate approximately 15% of the work outside normal hours (nights and/or weekends), especially if existing service must be interrupted. Any site work requested by the Contractor to be performed outside of normal duty hours will be coordinated with the Base POC at least 10 calendar days in advance.
3.4 Holidays/Down Days.
The Contractor will not perform under this contract on federal holidays or site-unique down-days unless expressly authorized by the Contracting Officer and coordinated with the base POC.
3.5 Base Support.
The Contractor shall identify any base support requirements (for example, laydown and storage areas) necessary to complete this project in their proposal. The contractor will return all government furnished lay-down and storage areas to their original condition upon completion of the project
3.6 Minimum Contractor Qualifications
All work will be performed by an experienced Telecommunications Contractor. The Contractor will have a minimum of 3 years of experience in Telecommunications Systems installations.
4.0 APPENDICES.
4.1 Appendix A. APPLICABLE STANDARDS.
AFI 91-203 – Air Force Consolidated Occupational Safety Instruction OSHA CFR 29 Part 1910-268 – Telecommunications TIA-606-B - Administration Standard for Telecommunications Infrastructure TIA-568-C.0 - Generic Telecommunications Cabling for Customer Premises TIA-568-C.1 - Commercial Building Telecommunications Cabling Standard TIA-568-C.2 - Balanced Twisted-Pair Telecommunications Cabling and Components Standard TIA-568-C.3 - Optical Fiber Cabling Components Standard TIA 942 - Telecommunications Infrastructure Standard for Data Centers TIA-607-B - Commercial Building Grounding (Earthing) and Bonding Requirements for Telecommunications TIA-526-7- Measurement of Optical Power Loss of Installed Single-mode Fiber Cable Plant TIA-526-14-B Optical Power Loss Measurement of Installed Multimode Fiber Cable Plant TIA-569-C - Commercial Building Standard for Telecommunications Pathways and Spaces TIA-570-C –Residential Telecommunications Infrastructure Standard TIA-598-C - Optical Fiber Cable Color Coding TIA-758-B Customer-owned Outside Plant Telecommunication Infrastructure Standard RUS Bulletin 1735F-401, Standards for Splicing Copper and Fiber Cable RUS Bulletin 1751F-643 - Underground Plant Design RUS Bulletin 1751F-801 – Electrical Protection Fundamentals RUS Bulletin 1753F-151 (515b) - Specifications and Drawings for Underground Cable Installation RUS Bulletin 1753F-201 (PC-4) – RUS Standard for Acceptance Tests and Measurements of Telecommunications Plant RUS Bulletin 1753F-207 (PE-87) – REA Specification for Terminating Cables NFPA 70 - National Electric Code
4.2 Appendix B. List of Acronyms
AASHTO American Association of State Highway and Transportation Officials AFM Airfield Management (BaseOPS) Approx. Approximately ATC Air Traffic Control Tower ATCALS Air Traffic Control and Landing Systems BCE Base Civil Engineering CDRL Contract Deliverable
CFE Contractor-Furnished Equipment CFP Contractor-Furnished Property CIP Common Installation Picture CIPS Cyberspace Infrastructure Planning System CMA Controlled Movement Area CMHDS Communications Maintenance Hole Duct System CO Contracting Officer Comm. Communications CS Communications Squadron CSI-B Cyberspace Integrator-Base CVC CIPS Visualization Component ECMRA Contractor Manpower Reporting Application EFI&T Engineer, Furnish, Install and Test FOC Fiber Optic Cable FODP Fiber Optic Distribution Panels FOUO For Official Use Only FY Fiscal Year HDPE High Density Polyethylene HH Hand Hole IAW In Accordance With ID Inside Diameter ILS Instrument Landing System IPT Integrated Process Team LMR Land Mobile Radio MH Maintenance Hole MHDS Maintenance Hole Duct System NLT No Later Than NPDES National Pollution Discharge Elimination System OEM Original Equipment Manufacturer OPSEC Operational Security OSHA Occupational Safety & Health Administration OSP Outside Plant OSS Operations Support Squadron OTDR Optical Time Domain Reflectometer PDF Portable Document Format PM Project Manager POC Point Of Contact Prime Prime Contractor PSI Pounds per Square Inch PVC Polyvinyl Chloride QAE Quality Assurance Evaluator QCM Quality Control Manager Qty Quantity RUS Rural Utilities Service Bulletin SCOW Supply Chain Operations Wing SCXP Scheduler Planner SE System Engineer
SM Single Mode SOW Statement of Work Sub Sub-Contractor SWPPP Storm Water Pollution Prevention Plan TIA Telecommunications Industry Association TMGB Telecommunication Main Ground Bus-Bar TRD Technical Requirements Document
5.0 Sketches: Proposed Cable Routes
Sketch 1: PROPOSED 6SM FOC FROM HH-149J TO CCTV PEDESTAL 1 AND CCTV PEDESTAL 2
HH-149J
New HH- 149-J1
700’ 730’
New HH- 149-J2
600’
1) Install new handholes and duct system from existing HH-149J to CCTV Pedestal 1.
2) Install duct system from existing HH-149J to CCTV Pedestal 2.
3) Install 6 SM FOC from HH-149J to proposed NEMA Boxes at CCTV pedestal 1 and CCTV pedestal 2.
4) At HH-149J splice the two new 6 SM FOCs to existing 12 SM FOC which terminate in B2801.
CCTV
Pedestal
#1 NEMA
Box
270’
Not To Scale
Existing Maintenance/Handhole
Existing Conduits
Proposed 2-4” conduit with innerduct
Proposed Handhole
Splice
Proposed 1-4” conduit with innerduct
CCTV Pedestal
CCTV
Pedestal
#2 NEMA
Box
Sketch 2: PROPOSED 6SM FOC FROM HH-149E TO CCTV PEDESTAL 3 AND CCTV PESDETAL 4
HH-
149E
HH-
149F
HH-
149G
HH-
149H
New HH- 149-H1
670’
700’
700’
600’
400’
900’’
New HH- 149-F1
1) Install new handhole and duct system from existing HH-149H to CCTV Pedestal 3.
2) Install new handhole and duct system from existing HH-149F to CCTV Pedestal 4.
3) Install 6 SM FOC from HH-149J to proposed NEMA Boxes at CCTV pedestal 3 and CCTV pedestal 4.
4) At HH-149E splice the two new 6 SM FOCs to existing 12 SM FOC which terminate in B2801.
450’
Not To Scale
Existing Maintenance/Handhole
Existing Conduits
Proposed 2-4” conduit with innerduct
Proposed Handhole
Splice
Proposed 1-4” conduit with innerduct
CCTV Pedestal
CCTV
Pedestal
#3 NEMA
Box
CCTV
Pedestal
#4 NEMA
Box
| Table of Contents |
| 1.0 SCOPE. |
| 2.0 REQUIREMENTS. |
| 2.1 GENERAL REQUIREMENTS. |
| 2.1.1 Safety Requirements. |
| 2.1.1.1 Site Coordination. |
| 2.1.1.2 Confined Space. |
| 2.1.1.3 Accident/Incident Reporting and Investigation. |
| 2.1.1.4 Work Area(s). |
| 2.1.1.5 Traffic Control. |
| 2.1.2 Security Requirements. |
| 2.1.2.1 Security Clearances. |
| 2.1.2.2 Operational Security (OPSEC). |
| 2.1.3 Environmental Management. |
| 2.1.4 Permits. |
| 2.1.5 Integrated Product Team (IPT). |
| 2.1.6 Quality Assurance. |
| 2.1.7 Contractor Personnel. |
| 2.1.7.1 Project Management. |
| 2.1.7.2 Site Point of Contact (POC). |
| 2.1.7.3 Personnel Requirements. |
| 2.1.8 Warranty. |