RFI RESPONSES 10 AUG 10.docx
DOCX document 22 KB Posted
- Attached to
- VAV Controls Replacement Federal contract opportunity
- Solicitation number
- FA3010-10-R-0011
About this file
RFIs as of 10 Aug 10
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA3010-10-R-0011 Amend 0001.pdf | ||
| First and Second Floor Drawings.pdf | ||
| FA3010-10-R-0011 Solicitation.pdf | ||
| Performance Questionnaire.doc | DOC document | |
| FINAL SPECIFICATION.pdf | ||
| Wage Det.doc | DOC document | |
| Past Performance Reference List Attach 4.rtf | RTF text file |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
10 August 2010 MAHG101031
RFI REPLY
MAHG 101031
Wolfe Hall Controls Replacement Building 4330
KEESLER AFB, MISSISSIPPI
1) Are there existing mechanical record drawings indicating:
- existing air distribution ductwork and vav boxes, location, sizes.
Reply: See the first and second floor, PDF (two) drawings indicating the ductwork for the zones the existing, twelve air handling units are currently serving. The VAV boxes were added after the building was originally constructed and we have not been able to located any mechanical plans indicating there location.
- mechanical rooms plans that would indicate air handling units piping.
Reply: none
- existing electrical drawings.
Reply: See PDF drawings.
- architectural drawings to include reflected ceiling plans and floor plan.
- Reply: See PDF drawings.
2) The area the contractor will have to work in for five weeks is the area which is served by each air handling unit (10,800 sqft) which is basically ten classrooms (1/12 of the building at a time). The owner will be responsible for locating the existing VAV box and moving/covering the furniture/electronic equipment. The contractor shall complete the VAV box replacement and the owner is responsible for restoring the furniture/electronic equipment in its initial location.
The building occupants are coordinating the sequence of the areas (zones) which will be down. The sequence will attempt to be kept as close to being adjacent to each other as possible but the contractor shall take into account having to move to areas throughout the building which are not adjacent to each other.
END