Performance Work Statement Roof Survey and Inspection
View the file
Other files
| File | Type | Posted |
|---|---|---|
| QUESTIONS_-_FA2860-15-R-0015.docx | DOCX document | |
| FA2860-15-R-0015.pdf | ||
| Wage_Determination_2005-2103.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement
For
Roof Survey and Inspection
11th CES/CEOES
Updated: 27 February 2015
1.0 DESCRIPTION OF SERVICES. The contractor shall furnish all personnel, labor, equipment, transportation, tools, materials, supplies, supervision, quality control, management and other items and services necessary to perform roof survey and inspection services & improvements, to include vegetative roof stewardship services, at Joint Base Andrews, Maryland (JBA) and its affiliated communication sites at Brandywine and Davidsonville, Maryland, in accordance with this Performance Work Statement
(PWS). The services provided shall act as a preventative maintenance measure toward the care of JBA facilities and shall allow for a more complete understanding of the roof system’s condition, which ultimately permits base personnel to better manage the entire roof system. Maintenance shall prevent:
structural damage; damage to interior components such as ceilings, walls, carpet, and equipment; mold growth and loss of personnel productivity. Additionally, regular maintenance shall prevent the need for costly full repair/replacement of the roof systems on JBA. The estimated quantities of work are listed in
Appendix A, titled Estimated Workload Data. The contractor shall provide roof survey and maintenance services & minor repairs to locations designated in Appendix A and comply with all local, state, and federal laws. All inspectors shall maintain roof inspector certification through the National Roof
Certification and Inspection Association (NRCIA) or equivalent certification.
1.1 Roof Inspection. An inspection checklist for each roof system type to be inspected during the course of the base wide survey shall be submitted by the roof contractor no later than 10 days after date of contract award for Contracting Officer Representative (COR) approval.
1.1.1 Visual Inspection. The roofing contractor shall perform a visual inspection in accordance with approved inspection checklist and verification of current roof system conditions of facilities listed in
Appendix A. Roof core cuts shall be made, on an as needed basis, to determine the roof system construction. Any roof core cuts shall be patched the same day the core is taken with appropriate materials to ensure a water tight seal.
1.1.2 Moisture Inspection. The contractor shall provide infrared thermography imaging to detect and identify potential problems related to moisture infiltration and to identify the possible source of infiltration. Fly over inspection will not be permitted on JBA. Contractor shall notify the COR of newly discovered areas of moisture infiltration when identified so that measures can be taken by the government to prevent further damage. All information shall be included in the roof report as well.
1.2 Roof Report. The roof report should include at a minimum:
1. Roof type with associated area in square feet.
2. Descriptions and photographs of all observed roof deficiencies.
3. Sloped metal roof systems shall be evaluated with recommendations as to what should be done to correct poor detailing and terminations where possible.
4. Roof plan drawings to include, but not limited to, basic layout with associated pitches, location of equipment and penetrations.
5. Recommendations and a brief scope of work with estimated budget shall be provided for all roof systems.
6. Report to be submitted in three (3) copies.
7. Shall be submitted within five (5) days of roof inspection.
All roofs shall be cataloged based on current roof conditions using the following color code system:
Green – remaining performance life of 7+ years.
Amber – remaining performance life of 4 to 7 years.
Red – roof systems with less than 3 years of life remaining.
1.3 Roof Data. All roof inspection data shall be contained in an online database system that can be easily accessed by JBA. The roof database shall be required to interface with the JBA GIS/GeoBase system
Version 10.0 or above. Data shall be inputted into system no later than five (5) working days after inspection.
1.4 Preventive Maintenance/Repair. Minor repair of flashings and metal edges along perimeters and units to include minor tears, splits and breaks in membrane flashing to be repaired with appropriate repair mastic and membrane. All accumulative repairs not to exceed 1000 sq ft, costs shall be included in Debris
Removal and Visual Inspection line item. Preventive Maintenance/Repair should include the following items:
Metal Edge Cleats and clips shall be re-secured, if necessary.
Coat all exposed reinforcing membrane with approved mastic.
Re-secure termination bars and counter flashing, as needed.
All pitch pans shall be refilled and topped off.
Check and re-secure drain bolts and clamping rings, as needed.
Check strip-in drain leads, coat with approved mastics, if needed.
When approved, a work order will be provided to the contractor for minor repairs.
1.5 Work Orders. When approved and funded by the Government, a work order may be issued to the contractor for roof repairs identified during visual inspection that exceed the threshold in paragraph 1.4.
This work is not guaranteed to the contractor and will be solely determined by the Government. When approved, the contractor will charge the Government for man-hours and reimbursable materials on the appropriate CLINs IAW paragraph 4.11 and 4.11.1. More than one requirement may be included on a work order. The COR will establish a required completion date for each work order. The contractor shall inspect the job prior to close out to ensure all requirements were met. After completion, the contractor shall notify the COR to schedule an acceptance services inspection.
1.6 Vegetative Roof Systems. Contractor shall evaluate and provide a stewardship program to maintain health of living roof as well as establish a nondestructive inspection for the membrane beneath the living parts of the roof.
1.6.1 Stewardship Program. The Stewardship program shall include, but is not limited to providing:
Regular inspection of membrane, waterproofing, seals and flashings for leakages
Regular inspection and cleaning of drainage appurtenances
Plant inspection for disease or nutrient deficiency and replacement as necessary to maintain 80- to 90-percent coverage
Seasonal removal of weeds
Application of protection methods against pests
Application of slow-release fertilizer, depending on plant requirements
Provide supplemental growing medium on areas if needed
Irrigation, replanting, aeration, and replacing eroded media for all vegetative roofs as needed.
1.6.2 Inspection Frequency. All vegetative roofs need to be inspected quarterly (every 3-4 months) to insure no issues need to be addressed from 1.6.1.
1.6.3 Work Order. A work order shall be issued to the contractor by the COR for performance of services that are non-recurring or regularly scheduled (i.e. vegetative roof plant replacement, minor membrane repairs, flashing repair etc.). More than one requirement may be included on a work order.
When approved, the contractor will charge the government for man-hours and reimbursable materials on the appropriate CLINs. The COR will establish a required completion date for each work order. The contractor shall inspect the job prior to close out to ensure all requirements were met. After completion, the contractor shall notify the COR to schedule an acceptance services inspection.
1.6.4 Reimbursable Materials. Plant materials and media for vegetative roofs and materials used for work orders issued for roof repairs shall be reimbursed at 100% contractors cost by the government IAW paragraph 4.11. and 4.11.1. The contractor shall provide no less than, a one (1) year warranty from the nurseries or growers from which all new plant materials are purchased. The contractor shall be responsible for replacing any defective plant within appropriated period of such warranty. These warranties shall include labor cost for removal and replacement.
1.7 Warranty. Provide JBA with a one (1) year performance warranty on approximately 500,000 square feet of roof systems that are categorized as green or amber. The specific roof systems to be warranted shall be selected by Civil Engineering personnel from the attached roof inspection listing following the initial inspection. In the event that a roof leak occurs in a roof system covered under a performance warranty, the contractor shall respond within 48 hours to correct the roof leak. If the leak is an emergency, the contractor shall respond within four (4) hours, during normal operating hours after the call is placed. The contractor is responsible for all costs of the leak repair. Roof leaks caused by acts of God, owner abuse, unauthorized alterations or installation of roof top equipment/penetrations shall not be required to be covered under the performance warranty. COR must be notified if and when this determination is made. The sloped metal roof systems with poor detailing and terminations, as well as roof systems coded in the Red category shall not be required to be covered for the roof leaks.
1.8 Contractor Requirements
1.8.1 Debris Removal. Debris shall be removed in a timely manner but no later than the contractor’s daily departure. Debris shall be removed using the contractor supplied dumpsters/containers/trucks for hauling and disposal to the JBA designated location. Surrounding areas shall be clean and neat in appearance. The contractor shall be responsible for bringing refuse to the identified dumpsters. The
Contractor shall not dispose of flammable liquids, batteries, tires mineral spirits, oil, lubricants and other flammable or hazardous material in base dumpsters. The contractor shall be required to comply with all installation recycling programs.
1.8.2 Materials. Materials utilized during preventive maintenance shall be of such composition and quality so as to be compatible with the respective roof coating as well as colored to match, as close as possible to the existing roof material. Contractor shall submit two (2) copies no later than five (5) days prior to use, of the manufacturer’s technical data bulletins, material safety data sheets (MSDS) and safety instructions on each product proposed for use. Contractor shall submit the required U.L. rating certification for each product proposed for use no later than five (5) days prior to use.
1.8.3 Power Outages. Power outages and limited utility interruptions shall be permitted in accordance with a previously arranged schedule. The contractor is responsible for notifying and coordinating all outages with the COR, who will coordinate with the Base Civil Engineer at least five (5) working days in advance of the intended outage.
1.8.4 Quality Control Report. The contractor shall produce a Quality Control Report no later than five
(5) days after inspection citing: date of roof inspection, representative’s name, outcomes, maintenance performed and recommendations for additional preventive measures derived from inspection results.
Contractor shall share any performance mechanisms/reports with the Government to ensure industry standards are met.
1.8.5 Work Stoppages. From time to time there will be work stoppages due to scheduled and unscheduled mission requirements (events). During times of work stoppage the roof inspection/maintenance work schedule shall be altered to work in other areas until the event is complete at which time roof inspection/maintenance work will be scheduled and accomplished.
2.0 SERVICES SUMMARY
Performance
Objectives
PWS Reference Performance Thresholds
Roof inspections of approved facilities.
1.1.1
1.6.2
Not to exceed one (1) customer complaint or one
(1) defect per month of inspection items included in approved checklist.
Core cuts patched same day.
Housekeeping conducted during inspections
1.8.1 Debris disposed of no later
than the contractor’s daily departure.
Provide stewardship program
1.6.1 Not to exceed one (1)
customer complaint or one
(1) defect per month of maintenance performed on specified items.
Preventive maintenance conducted during inspections
1.4 Not to exceed one (1)
customer complaint or one
(1) defect per month of preventative maintenance performed on specified items.
Submittal of reports and repair estimate
1.2
1.3
Reports include 95% of specified information and
3.0 GOVERNMENT FURNISHED PROPERTY
3.1 Government Furnished Property. None
3.2 Medical Services. Ambulance/ emergency medical services are available at JBA medical clinic. The contractor’s employee shall be billed directly and it is their responsibility to secure payment from their medical insurance.
3.3 Security Forces/Fire Protection. The Government will provide security police and fire protection to the extent necessary to ensure a safe and secure installation. In return for these services, the contractor shall adhere to security and fire directives, instruction and policies on JBA. The security forces law enforcement desk is located at building 1845 and the fire services are located at building 1287 & 3464.
4.0 GENERAL INFORMATION
4.1 Quality Control. The contractor shall submit a Quality Control Plan (QCP) within ten (10) days of contract award, outlining procedures to identify, prevent and ensure non-recurrence of defective services in accordance with the performance work statement, applicable standards and codes. As a minimum, the contractor shall develop quality control procedures that address the areas identified in 2.0 Services
Summary.
4.2. Quality Assurance. The Government will periodically evaluate the contractor’s performance by appointing a representative(s) to monitor performance. The Government representative will evaluate the contractor’s performance through intermittent on-site inspections of the contractor’s quality control program and receipt of complaints from base personnel. The Government may inspect each task as completed or increase the number of quality control inspections if deemed appropriate because of repeated failures discovered during quality control inspections or repeated customer complaints.
Likewise, the Government may decrease the number of quality control inspections if performance dictates. The Government will also receive and investigate complaints from various customers located on the installation. The contractor shall be responsible for initially validating customer complaints. However, the Government representative shall make final determination of the validity of customer complaint(s) in cases of disagreement with customer(s).
4.3 Work Schedule. The contractor shall establish a monthly work schedule to describe in detail all the efforts to accomplish required services identified in PWS and Appendix A throughout the month. Once the work schedule is received, at this time, if changes need to be made to reduce conflicts with the
Government operations, special events, or other occurrences, the contractor shall meet with the
1.8.4 submitted within five (5) days of roof inspection in three (3) copies.
Warranty of selected roof systems
1.7 Two (2) customer
complaints per month.
During emergencies covered under warranty shall respond within four
(4) hours, during normal operating hours after the call is placed.
Work Orders 1.5, 1.6.3 100% inspection 0 defects
Government and revise the schedule as necessary. The CO’s representative can request changes to the monthly work schedule so spacing of services is distributed to meet the needs of the Government. The contractor shall not be allowed to deviate from this schedule without prior approval from the COR.
4.4 Hours of Operation. Hours of operation are from 7:30 AM to 4:30 PM Monday thru Friday.
4.5 Federal Holidays. The following is a list of Federal Holidays observed by this installation:
New Year’s Day Labor Day Inauguration Day
Martin Luther King’s Birthday Columbus Day President’s Day
Veterans Day Memorial Day Thanksgiving Day
Independence Day Christmas Day
4.6 Security Requirements. All contractor employees shall carry contractor photo identification at all times. Contractor employees shall comply with any base security measures implemented at all times. This includes but is not limited to vehicle and goods searches and identification checks during times of increased security. All personnel employed by the contractor in performance of this contract, or any representative of the contractor entering the government installation, shall abide by all security regulations of the installation. The contractor should anticipate delays in getting commercial vehicles on base and allow time for commercial vehicles to reach their destination by driving designated routes at posted speed limits throughout the base. Procedures for commercial vehicle access to the base are subject to change without prior notice.
4.6.1 Contract Employees. The contractor shall be responsible for the action of any of their sub-contractors and their employees who are working on JBA. The contractor and sub-contractor, if hiring
U.S. citizen(s), shall ensure that they are in possession of a valid State driver’s license or State issued
Identification Card and birth certificate. If the employee/hiree is not a U.S. citizen, the contactor and/or subcontractor may hire non U.S. citizens if they are in possession of Green Card, Social Security Card, Resident Card, Work Visa and State issued Identification Card. If driving on base a State driver’s license and insurance is required.
4.6.2 Federal Criminal History Background Check. The contractor and all employees of the contractor requiring unescorted access to JBA controlled areas, to include all areas within the pathfinder fence, will be required to successfully undergo a Federal Criminal History Background Check and be fingerprinted.
The contractor shall be responsible for all costs associated with fingerprinting and the Federal Criminal
History Background Check. The authorization number is 00625G, and should be entered in the ORI space on the back of the blue card. For updated information on obtaining federal background checks visit the
MD Department of Public Safety and Correctional Services website at:
http://www.dpscs.state.md.us/publicservs/bgchecks.shtml or call the number below.
CJIS – Central Repository
6776 Reisterstown Road, Suite 102
Baltimore, MD 21215
Or
CJIS – Central Repository
P.O. Box 32708
Pikesville, MD 21282-2708 http://www.dpscs.state.md.us/publicservs/bgchecks.shtml
Contact CJIS at 410-764-4501 or toll free at 1-888-795-0011 if you have questions about the procedure or the associated fees.
4.6.3 Weapons. Weapons of any sort are not authorized on JBA, this includes guns, knives, swords, numb chucks, brass knuckles, or any other weapon that has a sole purpose to injure or maim.
Combination tools such as Leatherman and small pocket knives with folding blades less than four inches are authorized if used in the performance of duty. Those found in violation of this directive are subject to apprehension, criminal charges and debarment from the installation.
4.6.4 Illegal Controlled Substance: The U.S. Federal Government is the most vocal opponent of the drug industry and it has set the de facto international standards regarding the legality and illegality of different drugs. Illegal controlled substance and narcotics are not authorized on JBA what so ever, controlled substances may not be transported on the installation via vehicle or on an individual person, i.e., marijuana/Cannabis, cocaine, crack cocaine, LSD, Methamphetamine (Meth), Heroin, Anabolic steroids, Psilocybin mushrooms, are some of forbidden substances ( this list is not all inclusive).
Prescription medications are authorized for the person the medication is issued to; however the medication must not be expired and the label must clearly indicate the name of the person the medication is issued to. Otherwise the prescription medication may be deemed illegal by the law enforcement officials. Those found in violation of this directive are subject to apprehension, criminal charges and debarment from the installation.
4.6.5 Base Access. Identification cards and vehicle registrations shall be obtained from the Visitor
Control Center (building 1832) located at the main gate entrance of JBA. Owners must present valid drivers' licenses, current registration, proof of insurance, and any other information deemed necessary to obtain a vehicle pass. While on the premises of JBA or any of its affiliate sites, Contractor personnel shall represent themselves as non-government employees by conspicuously displaying badges at all times.
Lost vehicle and entry passes shall be reported immediately to Security Police, and the COR.
4.6.6 Physical Security. The contractor shall be responsible for safeguarding all government property provided for contractor’s use. At the end of each shift, all government facilities, equipment, and materials shall be secured. The contractor shall be responsible for providing and placing all barricades and safety devices during any activities and comply with all Occupational Safety and Health Standards (OSHA).
4.6.7 Retrieving Identification Media. The contractor shall retrieve all identification media, including vehicle passes from employees who depart for any reason before the contract expires; e.g., terminated for cause, retirement, etc. and return them to issuing COR or 11 Security Forces Squadron Visitor Control
Center personnel before final payment will be made.
4.7 Performance of Services during Crisis Declared By the National Command Authority or
Overseas Combatant Commander. In the event the contractor is unable to perform his daily operations due to peacetime emergency and/or wartime contingency disturbances, etc., neither the Government nor the contractor shall take action for non-compliance with contract requirements.
4.8 Safety. Contractor shall comply with all applicable OSHA and AFOSH standards.
4.9 Hazardous Material Identification. Material Safety Data Sheets (MSDS) are required as specified in the latest version of Federal Standard No. 313 (including revisions adopted during the term of the contract) for any other material designated by a government technical representative as potentially hazardous and requiring safety controls. MSDSs shall be submitted by the contractor at the pre-performance conference, and as necessary throughout the life of the contract. Failure to provide MSDSs or certificates when requested could result in unsatisfactory performance ratings and possible termination of the contract. Appendix A shows the proposed procedures for contractors requiring the use of radioactive material (RAM) and Radiation Generating Equipment of JBA.
4.10 Notification of Environmental Spills. If the contractor spills or releases any substance listed in 40
CFR 302, Designation, reportable Quantities, and Notification into the environment, the contractor shall immediately report the incident to the COR, and be familiar with and follow the most current “Base Spill
Plan” (a copy will be provided at the pre-performance conference). The contractor shall be held liable for the spill or release of substances. The contractor is responsible for advising his employees of all
Environmental and Hazardous Materials Handling and is also required to have and maintain Material
Safety Data Sheets (MSDS) on all materials that are required by state and federal laws and/or regulations, reference AFI 91-301 and OSHA requirements.
4.11 Contractor Purchased Items. The contractor shall be responsible for the acquisition of all materials and supplies to perform work under this contract and will be reimbursed by the Government for allowable costs. The contractor shall obtain and provide three (3) current market prices for each item submitted for
Government reimbursement over $2,500. However, the contractor shall obtain approval from the COR prior to purchasing any single item or combination of items. Additionally, the contractor shall comply with the Competition in Contracting Act by seeking competitive pricing for all items. Evidence of compliance must be made available to the Government upon request. The contractor is authorized to use available government sources of supply (e.g., GSA) for making such acquisitions.
4.11.1 Reimbursable Items. The contractor shall submit a reimbursable list of items to be preapproved by the COR/CO, with pricing and description. The contractor shall provide the COR with the original receipt for materials within five (5) days of purchase. The bill should be itemized and include the cost, date of purchase, vendors name and location. The contractor shall invoice for reimbursable materials and supplies (e.g. vegetative roof plants, slow-release fertilizer and growing medium etc), with the exception of fuels (petroleum based products) or items used for vehicle maintenance. Office supplies and parts are not reimbursable. Crains, lifts, latters and scaffolding are not reimbursable.
Additionally, the contractor must identify the following:
(1) Manufacturer or brand name of item
(2) Unit of issue
(3) Actual cost to contractor
(4) How item was used
Appendix A
Estimated Workload Data
292 Buildings, estimated 4,616,858 square feet of roof
Facility Roof Area
Quantity Unit of Measure
Brandywine 3,500 SQ FT
Davidsonville 1 22,340 SQ FT
656 1,300 SQ FT
819 560 SQ FT
1046 3,250 SQ FT
1051 45,000 SQ FT
1054 6,940 SQ FT
1076 3,200 SQ FT
1190 5,911 SQ FT
1191 10,490 SQ FT
1201 3,962 SQ FT
1202 7,600 SQ FT
1205 2,400 SQ FT
1206 2,263 SQ FT
1207 8,000 SQ FT
1208 4,020 SQ FT
1216 894 SQ FT
1217 12,900 SQ FT
1220 20,000 SQ FT
1223 10,400 SQ FT
1225 45,000 SQ FT
1228 43,700 SQ FT
1229 7,983 SQ FT
1234 11,800 SQ FT
1235 11,713 SQ FT
1236 9,542 SQ FT
1237 4,200 SQ FT
1238 650 SQ FT
1240 5,600 SQ FT
1241 190 SQ FT
1245 22,700 SQ FT
1279 89,000 SQ FT
1280 76,672 SQ FT
1281 4,500 SQ FT
1285 3,941 SQ FT
1287 17,926 SQ FT
1288 32,300 SQ FT
1290 2,200 SQ FT
1345 13,840 SQ FT
1349 9,100 SQ FT
1350 6,143 SQ FT
1351 3,523 SQ FT
1353 9,500 SQ FT
1358 7,400 SQ FT
1359 44,420 SQ FT
1380 63,300 SQ FT
1398 3,630 SQ FT
1413 22,000 SQ FT
1414 17,500 SQ FT
1417 7,156 SQ FT
1419 9,835 SQ FT
1420 5,054 SQ FT
1442 19,900 SQ FT
1443 300 SQ FT
1444 27,677 SQ FT
1445 26,595 SQ FT
1523 4,800 SQ FT
1526 240 SQ FT
1530 4,100 SQ FT
1531 2,900 SQ FT
1539 19,400 SQ FT
1558 75,500 SQ FT
1560 9,800 SQ FT
1565 600 SQ FT
1568 11,166 SQ FT
1600 31,200 SQ FT
1605 1,500 SQ FT
1618 19,200 SQ FT
1624 18,200 SQ FT
1628 18,000 SQ FT
1631 15,300 SQ FT
1642 15,400 SQ FT
1657 14,200 SQ FT
1658 30,430 SQ FT
1668 4,400 SQ FT
1673 9,000 SQ FT
1674 15,951 SQ FT
1676 15,394 SQ FT
1677 7,229 SQ FT
1682 5,908 SQ FT
1683 43,000 SQ FT
1684 122,483 SQ FT
1685 4,000 SQ FT
1690 17,500 SQ FT
1691 15,000 SQ FT
1692 11,000 SQ FT
1706 1,500 SQ FT
1708 6,150 SQ FT
1711 15,962 SQ FT
1713 2,365 SQ FT
1714 54,757 SQ FT
1731 2,300 SQ FT
1734 74,783 SQ FT
1735 8,649 SQ FT
1754 74,783 SQ FT
1771 1,060 SQ FT
1773 215 SQ FT
1778 8,200 SQ FT
1781 2,316 SQ FT
1783 15,282 SQ FT
1791 22,599 SQ FT
1794 74,783 SQ FT
1800 53,000 SQ FT
1805 20,700 SQ FT
1810 4,300 SQ FT
1811 114,000 SQ FT
1839 224 SQ FT
1841 170 SQ FT
1845 14,623 SQ FT
1864 398 SQ FT
1870 7,088 SQ FT
1889 44,048 SQ FT
1900 33,360 SQ FT
1911 8,100 SQ FT
1914 91,411 SQ FT
1915 23,000 SQ FT
1919 860 SQ FT
1931 11,201 SQ FT
1932 28,688 SQ FT
1933 10,413 SQ FT
1934 2,400 SQ FT
1937 7,150 SQ FT
1969 1,252 SQ FT
1988 334 SQ FT
2267 255 SQ FT
2487 8,113 SQ FT
2488 4,100 SQ FT
2489 39,400 SQ FT
2490 900 SQ FT
2492 1,000 SQ FT
2493 8,100 SQ FT
2495 13,000 SQ FT
2496 1,100 SQ FT
2497 3,150 SQ FT
2498 2,600 SQ FT
3001 12,700 SQ FT
3002 11,600 SQ FT
3004 13,100 SQ FT
3007 1,100 SQ FT
3014 1,938 SQ FT
3029 19,400 SQ FT
3030 8,300 SQ FT
3031 12,400 SQ FT
3032 5,600 SQ FT
3033 2,350 SQ FT
3034 2,100 SQ FT
3040 1,250 SQ FT
3041 4,100 SQ FT
3045 3,540 SQ FT
3046 5,200 SQ FT
3056 14,016 SQ FT
3066 125,000 SQ FT
3067 1,115 SQ FT
3068 514 SQ FT
3069 3,500 SQ FT
3070 4,000 SQ FT
3077 6,100 SQ FT
3086 89,100 SQ FT
3091 900 SQ FT
3092 1,519 SQ FT
3093 901 SQ FT
3094 2,300 SQ FT
3096 3,900 SQ FT
3106 4,100 SQ FT
3108 300 SQ FT
3109 13,100 SQ FT
3119 45,000 SQ FT
3121 6,700 SQ FT
3148 92,700 SQ FT
3149 6,000 SQ FT
3158 40,800 SQ FT
3160 850 SQ FT
3167 250 SQ FT
3188 119,000 SQ FT
3198 11,800 SQ FT
3212 27,400 SQ FT
3213 7,400 SQ FT
3214 4,200 SQ FT
3215 2,400 SQ FT
3216 400 SQ FT
3217 7,700 SQ FT
3218 2,200 SQ FT
3222 14,200 SQ FT
3227 7,200 SQ FT
3236 13,200 SQ FT
3252 28,500 SQ FT
3257 3,286 SQ FT
3282 25,000 SQ FT
3283 2,200 SQ FT
3285 2,400 SQ FT
3296 9,794 SQ FT
3304 2,400 SQ FT
3305 2,400 SQ FT
3307 3,100 SQ FT
3320 39,809 SQ FT
3342 1,678 SQ FT
3350 4,400 SQ FT
3351 2,400 SQ FT
3355 9,000 SQ FT
3356 2,900 SQ FT
3382 2,300 SQ FT
3410 320 SQ FT
3411 2,373 SQ FT
3415 7,200 SQ FT
3416 8,750 SQ FT
3417 9,794 SQ FT
3418 1,600 SQ FT
3422 15,247 SQ FT
3423 1,764 SQ FT
3424 12,304 SQ FT
3434 500 SQ FT
3440 1,200 SQ FT
3441 5,000 SQ FT
3442 1,920 SQ FT
3444 4,000 SQ FT
3445 9,680 SQ FT
3446 9,605 SQ FT
3447 3,200 SQ FT
3448 8,459 SQ FT
3449 14,164 SQ FT
3451 452 SQ FT
3458 529 SQ FT
3461 1,500 SQ FT
3464 10,788 SQ FT
3465 18,808 SQ FT
3466 5,400 SQ FT
3487 2,619 SQ FT
3500 51,300 SQ FT
3531 11,889 SQ FT
3537 7,960 SQ FT
3541 9,200 SQ FT
3547 5,000 SQ FT
3603 650 SQ FT
3605 640 SQ FT
3608 21,634 SQ FT
3613 8,600 SQ FT
3616 727 SQ FT
3617 8,500 SQ FT
3623 12,500 SQ FT
3629 23,223 SQ FT
3635 87,000 SQ FT
3639 5,200 SQ FT
3640 58,388 SQ FT
3642 1,220 SQ FT
3681 435 SQ FT
3705 16,562 SQ FT
3710 14,100 SQ FT
3715 2,624 SQ FT
3725 19,748 SQ FT
3743 6,500 SQ FT
3744 16,500 SQ FT
3745 1,658 SQ FT
3755 32,000 SQ FT
3756 4,000 SQ FT
3757 12,985 SQ FT
3758 2,300 SQ FT
3763 7,700 SQ FT
3765 11,000 SQ FT
3766 9,400 SQ FT
3767 2,000 SQ FT
3807 2,400 SQ FT
4442 16,978 SQ FT
4549 1,100 SQ FT
4575 22,223 SQ FT
4598 1,300 SQ FT
4693 720 SQ FT
4694 3,600 SQ FT
4700 30,391 SQ FT
4715 132 SQ FT
4779 380 SQ FT
4781 360 SQ FT
4783 26,500 SQ FT
4797 6,251 SQ FT
4798 9,679 SQ FT
4882 4,073 SQ FT
4883 1,500 SQ FT
4885 4,000 SQ FT
4886 1,800 SQ FT
4919 768 SQ FT
4923 3,200 SQ FT
4924 3,700 SQ FT
5013 1,567 SQ FT
5014 2,850 SQ FT
5015 2,400 SQ FT
5016 214,000 SQ FT
5019 1,500 SQ FT
5023 4,300 SQ FT
5026 37,000 SQ FT
5030 2,500 SQ FT
5032 162,750 SQ FT
1500* 89,613 SQ FT
3501* 52,631 SQ FT
Estimated Total 4,616,858 SQ FT
* Roofs with vegetative areas
Vegetative Roof
Facility Number
Building
Name SQ FT
Building 3501
ANGRC
HQ Vegetative Area
Vegetative:
26,800
Building 1500 AFDW HQ Vegetative Area
Vegetative:
50,898
Estimated Vegetative total 77,698