FA283515-R-0061 Statement of Work Rev. 1
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_Windows_Bldg_1614_w_signature.pdf | ||
| Davis_Bacon_8_21_15.pdf | ||
| FA2835-15-R-0061_Solicitation_Released.pdf | ||
| General_Construction_Statement_of_Work.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
For General Construction Location Building: Multiple Buildings on Base By: Roland Hartz WORK ORDER NUMBERS: 65808, 65703, 65744, 65828, 65887, 65977, and 65478 Rev. 1 DATED: 21 July 2015
1. GENERAL INFORMATION:
This project is intended to do general construction on multiple buildings on in accordance with all applicable National, Air Force, State and local building codes and regulations. This work will consist of supplying/furnishing all labor, materials, tools, equipment, shop drawings, and expenses necessary to accomplish the work described below in compliance with the Commonwealth of Massachusetts Building Code and Massachusetts General Law requirements, state and federal codes, base standards and manufacturer’s instructions. When there is a conflict between nationally recognized codes and local codes, the most stringent shall apply.
2. SCOPE: General construction on multiple buildings ( Contractor to Field Verify all Measurements)
2. A (Base Bid) Work Order 65808 Building 1614 Replace Broken Windows in Multiple Locations (total of 6 windows)
· Phase 1 1AO183(approximate size 68”x 68”) Far Corner & 1CO135 (approximate size 68”x 68”)
· Phase 2 1IO129(approximate size 68”x 68”), 2IO121(approximate size 68”x 68”),2IO401 (approximate size 68”x 68”) and Arcade Hallway (approximate size 68”x 68”)
· Existing windows are ¼ bronze annealed, ¼ low E
2. B (Option 1) Work Order 65703 Building 1722 Install New Doors
· Door sizes are 3’0” x 7’0”
· Remove existing doors and frames facing Robbins Street
· Install new frames, doors and hardware (Door handle to have inter changeable core)
· One door metal with steel frame, right hand swing, one store front bronze tone with full window left hand swing
· Seal doors and frames per manufactures recommendations
· Paint solid door to match existing in building ( 1 primer and 2 finish coats)
· Red lines are required
2. C (Option 2) Work Order 65744 Building 1201 Replace 2 Exterior Doors (by bathroom and dumpster)
· Remove existing frame and door by bathroom left hand swing
· Remove existing door and frame by overhead door and dumpster right hand swing
· Modify opening to fit a 3’-0” x 7’-0” door (including exterior siding and trim)
· Both door sizes to be 3’-0’ x 7’-0”
· Move exit sign up above new opening
· Install new door frames
· Install new doors (door to have 24” x 24” lite installed in them)
· Seal doors and frames per manufactures recommendations
· Install new heavy duty door closers
· Install new crash bars with night latch and pull with interchangeable core
· Install new thresholds
· Paint doors to match existing at building ( 1 primer 2 finish coats)
· Red lines are required
2. D (Option3) Work Order 65828 Building 1725 Redesign Cell for Booking Room
· Remove toilet, sink, toilet paper dispenser, mirror, and paper towel dispenser from walls
· Cap off all plumbing in walls
· Cover plumbing in walls with access panels
· Install 2’ x 4’ fluorescent light fixture on ceiling
· Provide conduit and box on back wall for data
· Install two (2) receptacles
· Replace cell door with new wood door paint to match existing
· Install door handle with interchangeable core
· Red lines are required
2. E (Option4) Work Order 65887 Building 1412 Rooms 608/610 Remove Mold
· Prior to the start of work coordinate work schedule with Civil Engineering
· Disconnect remove and properly dispose of two (in each room) below window fan coil units (HVAC & Elec.). Disconnect and save pipe enclosures for re-use
· Remove and dispose of all pipe insulation from demising walls to FCU’s
· Replace ball valves – two for each FCU – no shut down allowed
· Furnish and install four (4) (two left hand and two right hand) new Fan Coil Units: Airtherm SETF, 120 volt and check for proper function - HVAC and Electric test for proper operation Provide three (3) copies of O & M manuals
· Install new pipe insulation with PVC elbows where removed
· Reinstall pipe enclosures
· Remove all curtains, trim and other items from exterior wall for re-use
· Remove existing wall paper on exterior wall in living room/ kitchen and bedroom Take care not to damage wall paper on side walls
· Remove existing drywall from exterior wall
· Install new foam insulation
· Install new drywall
· Finish smooth
· Flat tape at corners and ceiling keep compound off of wall paper
· Prime and paint new gypsum (color TBD) make an accent wall
· Re-install all items taken off of wall
· Conduct final clean-up of area
2. F (Option 5) Work Order 65977 Building 1642 Install Garage Door with Man Door
· Install new metal overhead garage door with 36” man door
· Existing opening is approximately 12’ x 13’
· Install electric opener with all safety devises
· Check door for proper operation
· Any welding will require burn permit
· Red lines are required
· Provide three (3) copies of O & M manuals
2. G (Option 6) Work Order 65478 Building 1827 Install Electric Door Opener
· Install electric door opener sized to door on Cookson roll up door 12’ x 12’
· Install all controls and safety devised needed
· All wiring to be in conduit
· Check for proper operation
· Red lines are required
· Provide three (3) copies of O & M manuals
3. 2. H (Option7)Work Order 65799 Building 1721 Install vestibule approximate size 8’ x 8’ x 8’ with 3’0” x 7’ 0” door (with all require hardware) and roof Porta King Building Systems or Equal prefabricated
· Remove two small bushes
· Remove exterior lights (save to be moved and re used)
· Cut asphalt approximately 25 lf
· Remove asphalt dispose of properly
· Excavate for slab to put structure on prepare in accordance with manufactures instructions
· Pour slab 9’ x 9’ x 6”
· Install new aluminum vestibule with glazing door to line up with existing walk way
· Attached to building and seal per manufactures recommendations
· Install new light fixture inside of vestibule
· Re install saved fixture to outside of vestibule
· Install matting inside vestibule
· Pave from existing walkway to base of new vestibule
· Repair any landscaping disturbed during construction
· Dig Safe permit is required
· Redline are required
4. GENERAL REQUIREMENTS:
Work includes, but is not limited to the following:
a. Provide resolutions of any technical problems that arise during the construction.
b. Should any change in scope be required, it must be coordinated with the Project POC and approved as a change order prior to performing the change in work.
c. Provide updates to Project POC. Any construction issues, changes to schedule, or schedule slippages with justification must be reported at the periodic updates.
d. Provide warranty letter for each work order
e. Period of Performance shall be 180 days after contract award
5. ADMINISTRATION:
Points of Contact (POC):
Lead: Roland Hartz Phone Number. (781) 225-2951 Alternate POC: William Neice Phone Number. (781) 225-6157