Attch_23_Task_Order_0001_Statement_of_Objectives.docx

DOCX document 956 KB Posted

Attached to
Simplified Acquisition of Base Engineering Requirements (SABER) Federal contract opportunity
Solicitation number
FA2823-15-R-4002
Issued by
Department of the Air Force Materiel Command Test Center

About this file

Attachment 23 Task Order 0001 Statement of Objectives

View the file

Other files for this federal contract opportunity

Other files attached to Simplified Acquisition of Base Engineering Requirements (SABER), newest first.
File Type Posted
FA2823-15-R-4002-0005.pdf PDF
FA2823-15-R-4002-0004.pdf PDF
Attch_27_Floor_Plan_Bldg_107.pdf PDF
FA2823-15-R-4002-0003.pdf PDF
Site_Visit_KTR_Sign_In_Sheet.pdf PDF
Attach_28_-_MFR_for_Questions_and_Answers.docx DOCX document
FA2823-15-R-4002-0002.pdf PDF
MFR_for_SABER_Solicitation_Questions_(2).docx DOCX document
Attch_01_Eglin_SABER_Specifications.pdf PDF
Attch_05_Eglin_Architectural_Compatibility_Plan.pdf PDF
Attch_02_Industrial_Safety_and_Health_Requirements.docx DOCX document
Attch_10_Wage_Rate_FL140081.pdf PDF
Attch_15_Wage_Rate_FL140229.pdf PDF
Attch_11_Wage_Rate_FL140029.pdf PDF
Attch_19_Wage_Rate_FL140094.pdf PDF
Attch_24_Contract_Bonds_Checklist.pdf PDF
Attch_16_Wage_Rate_FL140194.pdf PDF
Attch_14_Wage_Rate_FL140222.pdf PDF
Attch_20_Past_Performance_Project_References.doc DOC document
FA2823-15-R-4002.doc.pdf PDF
Attch_12_Wage_Rate_FL140036.pdf PDF
Attch_06_Eglin_AFB_Access_Affidavit.pdf PDF
Attch_26_Daily_Report_to_Inspector.pdf PDF
Attch_18_Wage_Rate_FL140126.pdf PDF
Attch_21_Past_Performance_Questionnaire.doc DOC document
Attch_08_Wage_Rate_FL140052.pdf PDF
Attch_04_Cable_Installation_Specifications.pdf PDF
Attch_07_Base_Access_Memorandum.doc DOC document
Attch_13_Wage_Rate_FL140070.pdf PDF
Attch_17_Wage_Rate_FL140119.pdf PDF
Attch_25_Site_Visit_Map.pdf PDF
Attch_09_Wage_Rate_FL140197.pdf PDF
Attch_22_Financial_Responsibility_Questionnaire.doc DOC document
Attch_03_DDC_System_Requirements.docx DOCX document
FA2823-15-R-4002-0001.pdf PDF
Show all 35

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

HEADQUARTERS 96TH TEST WING (AFMC)

EGLIN AIR FORCE BASE FLORIDA

5 Dec 14

STATEMENT OF OBJECTIVES (SOO)

Contract #:FA2823-10-D-0001
Project #:FTFA14-1101
Project Title:Repair Cabinets Bldg 107

SUMMARY OF WORK

1. PURPOSE OF SECTION: The purpose of this section is to provide the Contractor with a Statement of Objectives (SOO) for the above mentioned project. This document does not replace any of the provisions or requirements of the Simplified Acquisition of Base Engineering Requirements (SABER) contract to include SABER Statement of Work and specifications. The provisions of this section apply to this delivery order only, and the Contractor shall ensure that they, their personnel and subcontractors completely understand these provisions before developing the detailed statement of work and commencing work on this delivery order. The Contractor shall seek clarification from the Contracting Officer (CO) if there is any question on the applicability of a provision. These provisions are for the purpose of general information only and are not intended to completely describe the regulations and restrictions that apply on Eglin AFB. The Contractor’s proposal shall be submitted to the CO in accordance with paragraph 3.3.2. Contractor’s Statement of Work (SOW) package. “Design responsibility rests with the contractor. Government reviews, coordination, testing, comments, and observation at any stage of contract performance shall not be construed as actual or constructive notice to the Government of design and/or workmanship defects.”

2. PROJECT SCOPE: The project is located at Bldg 107. The Contractor shall be required to furnish all materials, equipment, plant, labor and personnel necessary to design, manage, and accomplish this task order in accordance with the contract requirements. A complete and usable facility must be furnished upon completion of task order. The Contractor is expected to maintain, at all times, good and accepted construction and safety standards.

A. The Contractor shall replace restroom lavatory base cabinets, faucets and shower floor tile.

3. PRINCIPAL FEATURES: Principal features of work are as follows:

A. ARCHITECTURAL/PLUMBING:

1. Disconnect and demo five existing lavatory faucets; carefully remove existing cultured marble sink countertop (approx 10 LF) and store on site for later reinstallation; demo five (5) existing 24” wide wood base cabinets.

2. Supply and install five (5) new manufactured wood casework vanity base cabinets (approximately 24”w x 18”d x 30”h). Cabinets shall be quality constructed of oak, traditional style, two panel door doors, toe kick, solid wood frame, particleboard side panels, dark finish (Java Oak or similar), with associated hardware (brushed nickel knobs and concealed hinges). Cabinets shall be similar in style to Insignia Ridgefield Java Oak Traditional cabinets and correctly sized to properly fit in area of removed cabinets. Submit cabinet data sheet or sketch, material sample, and color chart for selection and approval prior to ordering. Install vinyl base around perimeter of new cabinets and caulk adjacent to wall tile.

3. Reinstall existing sink countertop, caulk to backsplash, and reconnect sink drains.

4. Install five new single lever, energy-efficient Delta (or approved equal) lavatory faucets with popup stoppers; reconnect to existing water supply shut-off valves with braided supply lines.

5. Replace existing ceramic tile floors in three (3) showers, two (2) shower curb tile and bottom two rows of 4” wall tile in the three showers. Approximate shower dimensions are 33” x 46” with a 4-1/2” curb for two showers, and handicap shower is approximately 60” x 62”. New ceramic floor, wall and curb tile (price group 1) shall be 4”x4”. Properly slope floor tile to floor drains. Wall tile shall match existing. Submit tile samples for color selection and approval.

6. Repair damaged ceramic wall/base tile adjacent to vanity base cabinet and shower openings as required (not to exceed 10 LF); match tile with existing tile/base.

B. FIRE PROTECTION:

1. Ensure Design and Installation meet all requirements of UFC 3-600-01 and all applicable NFPA standards.

4. SPECIAL INSTRUCTIONS:

General:

a. The Contracting Officer is the only person who can obligate the government, direct the contractor or make changes to a delivery/task order.

b. The Contractor shall perform all investigative and design services necessary to complete this project by all appropriate codes.

c. In the absence of required material submittals/drawings showing the description of item or items to be installed, at a minimum, the description of the item or items installed shall be that of the negotiated proposal.

5. REQUIRED DRAWINGS as marked:

(X) A.Cover Sheet with title and approval block
(X) B.Floor Plan with finish schedule
(X) C.Cabinet elevation and details

6. RECOMMENDED PERFORMANCE PERIOD: 90 calendar days

//signed//
DAVID FRASIER, Civ
SABER Project Manager

Attachment:

a) Existing site condition photos

EXISTING LAVATORY CABINETS

EXISTING HANDICAP SHOWER (60” X 62”)

EXISTING REGULAR SHOWER - 2 EACH (33” X 46”)