Attachment 03 DDC System Requirements
View the file
Other files for this federal contract opportunity
Show all 35
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DDC System Requirements: 19 August 2011
1. Provide building level supervisory controllers based on Eglin’s existing Niagara AX Framework Rev 3.5 or later. The building level supervisory controllers shall include point-2-point (P2P), Secure Socket Layer SSL, Web server and embedded WorkBench (WB). The building level supervisory controllers shall contain all building logic and graphics.
2. All graphics and points shall be duplicated in the existing Niagara AX Framework ENS (Enterprise Network Server) using existing workbench software located in building 696 which shall serve as the Web Server for the system. All trended points shall be transferred via P2P to the server for history trending of points.
3. One- laptop with the latest operating system, cpu, and technology as it relates to laptops, software and hardware for upload, download, commissioning, and trouble shooting of all control devices shall be unconditionally provided to the government with all necessary licensing.
4. The system shall allow CE technicians to connect to all controllers with all available software in all modes available from the manufacturer from Bldg 696 via the local area network (LAN) to program, backup, download, configure and perform all functions necessary to maintain the system as if onsite and direct connected to the device.
5. All hardware and software administrator level passwords shall be provided to the government to access all levels of all controllers including the new Niagara Framework controllers. The password shall allow complete access to everything the manufacture has access to.
6. Contractor shall provide systems engineering training to 5 DDC personnel on Eglin AFB for 5 full days (course length). The training will produce 5 factory certified technicians.
7. All field controllers shall use Bacnet mstp protocol.
8. Provide a Lan drop within three foot of each building level supervisory controller and provide a patch cable between the Lan drop and the building level supervisory controller.
Graphics shall be in the existing ENS (Enterprise Network Server) located in building 696 which shall serve as the Web Server for the system.
Include date and time on all graphic screens.
Main Map Graphic- This screen will have a list and link to all of the buildings on the entire Eglin complex.
Building Graphic- This screen will have a 3d graphic of the front of the building and a building number. The following links are required on this page: Back to Main Map, floor plans, alarms, reports, schedules, history, and user service.
Floor Plan Graphic The floor plan will be 3D with color coded zones, room numbers, and as- built sensor and equipment locations.
The following points are required on this page: room temp, room humidity, occupancy status The following links are required on this page: back to building graphic, all equipment (Click on sensor or equipment shown on the floor plan and the link will go to the corresponding equipment).
Typical Equipment Graphic Include a header with equipment type and number, room numbers and area served.
Include all points on the equipment graphic.
The following points will be animated: fans, dampers, coils, pumps, boilers.
All set points will have the capability of being changed from the graphic.
The following links are required on this page: back to floor, provide a hidden link over each point to show an hourly 3 day trend, provide a hidden link over each point to override all outputs. Provide a link to a spread sheet with manufacture and part numbers and warranty dates for all parts on the equipment graphic.
Communication Bus Graphic Include an as-built wiring diagram of the communication bus between all controllers.