4_AF_66_Form_GLEN_181011.pdf

PDF 23 KB Posted

Attached to
Synopsis Federal contract opportunity
Solicitation number
FA2550-18-R-1011
Issued by
Department of the Air Force Space Command

About this file

AF Form 66

View the file

Other files for this federal contract opportunity

Other files attached to Synopsis, newest first.
File Type Posted
1_SOW_GLEN181011.pdf PDF
5_GLEN18_1011_Wage_Determination.pdf PDF
2_SAFB_Environmental.pdf PDF
0_SF1442_FA255018R1011.pdf PDF
3_Specifications.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Submittal Form AF-66

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY PROJECT ENGINEER

LI

N

E N

U M

BE

R

C

ER

TI

FI

C

AT

E O

F C

O M

PL

IA

N C

E

SH

O

P D

R

AW

IN

G

S

C O

LO

R

S

EL

EC

TI

O N

M

AN

U

FA

TU

R

U R

'S R

EC

O

M M

EN

D

AT

IO

N

C

AT

AL

O

G D

AT

A

O &M

R

EC

O M

M

EN

D

AT

IO

N

S

C

AL

C U

LA

TI

O N

S

W

AR

R

AN

TY

D R

AW

IN

G S

R

EP

O R

T

TE

ST

R

ES

U

LT

S

R

EQ

U

IR

ED

S

U

BM

IS

SI

O N

D

AT

E (C

AL

EN

D

AR

D

AY

S)

D

AT

E

TO

C O

N

TR

AC

TI

N G

D

AT

E

TO

C

IV

IL

E

N G

IN

EE

R

IN

G

R

ET

U R

N S

U

SP

EN

SE

D

AT

E

SU

BM

IT

TA

L N

U M

BE

R

S

AP

PR

O

VE

D

D

IS

AP

PR

O

VE

D

C O

N

TR

AC

TO

R S

U

BM

IT

TA

L

FI

N

AL

A

PP

R

O

VA

L

REMARKS

GENERAL

1 Project Specific MSDS Sheets 1 Within 4 weeks of NTP

2 Form-3064 Contract Progress Schedule 1 Within 8 weeks of NTP

3 Form-3065 Contract Progress Report 1 Weekly from

NPT

4 Health, Safety, and Environment Plan(s) 1 Within 4 weeks of NTP

5 Contractor's Quality Control Plan 1 Within 4 weeks of NTP

6 Operation and Storage Areas 1 Within 4 weeks of NTP

7 Utility Outages 1 4 weeks advance of

Pre-construction Meeting Minutes 1 Within 2 weeks of NTP

8 Submittal Log 1 Within 4 weeks of NTP

DESIGN

9 Shop Drawings 1 Within 8 weeks of NTP

ELECTRICAL

10 LED lighting fixtures 1 1 1 Within 8 weeks of NTP

11 Lighting Controls 1 1 1 Within 8 weeks of NTP

12 Occupancy Sensors 1 1 1 Within 8 weeks of NTP

13 Low Voltage Wires 1 1 1 Within 8 weeks of NTP

14 Connectors 1 1 1 Within 8 weeks of NTP

15 Terminals 1 1 1 Within 8 weeks of NTP

16 Circuit Breakers 1 1 1 Within 8 weeks of NTP

17 Conduits 1 1 1 Within 8 weeks of NTP

18 Panelboards 1 1 1 Within 8 weeks of NTP

19 Other Associated Hardware 1 1 1 Within 8 weeks of NTP

TO BE COMPLETED BY CONTRACT ADMINISTRATOR

PROJECT NUMBER PROJECT NAME SOLICITATION /CONTRACT NUMBER

GLEN 18-1011 Repair by Rpalcing Hallway lighting, B400

Project Submittal Form AF-66

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY PROJECT ENGINEER

LI

N

E N

U M

BE

R

C

ER

TI

FI

C

AT

E O

F C

O M

PL

IA

N C

E

SH

O

P D

R

AW

IN

G

S

C O

LO

R

S

EL

EC

TI

O N

M

AN

U

FA

TU

R

U R

'S R

EC

O

M M

EN

D

AT

IO

N

C

AT

AL

O

G D

AT

A

O &M

R

EC

O M

M

EN

D

AT

IO

N

S

C

AL

C U

LA

TI

O N

S

W

AR

R

AN

TY

D R

AW

IN

G S

R

EP

O R

T

TE

ST

R

ES

U

LT

S

R

EQ

U

IR

ED

S

U

BM

IS

SI

O N

D

AT

E (C

AL

EN

D

AR

D

AY

S)

D

AT

E

TO

C O

N

TR

AC

TI

N G

D

AT

E

TO

C

IV

IL

E

N G

IN

EE

R

IN

G

R

ET

U R

N S

U

SP

EN

SE

D

AT

E

SU

BM

IT

TA

L N

U M

BE

R

S

AP

PR

O

VE

D

D

IS

AP

PR

O

VE

D

C O

N

TR

AC

TO

R S

U

BM

IT

TA

L

FI

N

AL

A

PP

R

O

VA

L

REMARKS

TO BE COMPLETED BY CONTRACT ADMINISTRATOR

PROJECT NUMBER PROJECT NAME SOLICITATION /CONTRACT NUMBER

GLEN 18-1011 Repair by Rpalcing Hallway lighting, B400

CLOSEOUT

20 Manufacturer's Warranties 1 DUE AT

COMPLETION

21 O&M Maintainance data, manuals 1 DUE AT

COMPLETION

22 As Built Drawings 1 DUE AT

COMPLETION