Form 66 Submittal Log
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA255017R10020001.pdf | ||
| GLEN_03-1026_Pre-Proposal_RFI_Responses.docx | DOCX document | |
| Attachment_7_Design_Guide_Version_March_2016.pdf | ||
| FA255017R1002.pdf | ||
| Attachment_6_Wage_Determination_CO170018.pdf | ||
| Attachment_1_GLEN_03-1026_SOW.docx | DOCX document | |
| Attachment_5_GLEN_03-1026_Bid_Schedule.xlsx | XLSX spreadsheet | |
| Attachment_3_GLEN_03-1026_Project_Drawings.pdf | ||
| Attachment_2_GLEN_03-1026_Specifications.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| SCHEDULE OF MATERIAL SUBMITTALS (Paving IDIQ) | PROJECT NO. | PROJECT NAME | SOLICITATION /CONTRACT NUMBER | |||||||||||||||||||
| GLEN 03-1026 | Maintain Pavement Base Wide Areas | BUILDING 210, 220, 500 AND 440/442 PARKING LOTS | ||||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | |||||||||||||||||||||
| LINE NUMBER | Note: 3 copies required per submittal. Government will retain all submittals. | CERTIFICATE OF COMPLIANCE | SHOP DRAWINGS | COLOR SELECTION | MANUFATURUR'S RECOMMENDATION | CATALOG DATA | O&M RECOMMENDATIONS | CALCULATIONS | WARRANTY | DRAWINGS | REPORT | TEST RESULTS | REQUIRED SUBMISSION DATE | DATE TO CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | APPROVED | DISAPPROVED | CONTRACTOR SUBMITTAL | FINAL APPROVAL | REMARKS |
| GENERAL | ||||||||||||||||||||||
| 1 | Approved Form 103, BCE Work Clearance Request | X | Prior to commencment of work | With Map Accureately Showing Work Area | ||||||||||||||||||
| 2 | Project Specific MSDS Sheets | X | NTP + 5 days | Prior to Mobilization | ||||||||||||||||||
| 3 | Form-3064 Contract Progress Schedule | X | Bid Submittal | |||||||||||||||||||
| 4 | Form-3065 Contract Progress Report | X | Each Draw | |||||||||||||||||||
| 5 | Health, Safety, and Environment Plan(s) | 1 | NTP + 5 days | |||||||||||||||||||
| 6 | Traffic Control Plans - For Each Phase of Construction | 1 | 1 | NTP + 10 days | ||||||||||||||||||
| 7 | Contractor's QA/QC Plan | 1 | NTP + 5 days | |||||||||||||||||||
| 8 | Business Telephone and Directory | 1 | NTP + 5 days | |||||||||||||||||||
| 9 | Site Visit Meeting Minutes | 1 | NTP + 5 days | |||||||||||||||||||
| 10 | Construction Schedule | 1 | NTP + 5 days and weekly updates | |||||||||||||||||||
| 11 | Salvageable Material | 1 | NTP + 5 days | |||||||||||||||||||
| 12 | Mothly Solid Waste Reporting | 1 | Monthly Reports | |||||||||||||||||||
| 13 | Hydrant Connection request | 1 | 10 days prior to any work | |||||||||||||||||||
| 14 | Utility Outage Request | 1 | 10 days prior to the proposed outage | |||||||||||||||||||
| 15 | Traffic Change Request | 1 | 10 days prior to commencing with construction activites | |||||||||||||||||||
| 16 | Confined Space Permit | 1 | 5 days prior to work in a confined space | |||||||||||||||||||
| CIVIL | ||||||||||||||||||||||
| 17 | Current Backflow Preventer Inspection Cert. | 1 | 1 | 10 days prior to any work | ||||||||||||||||||
| 18 | Joint layout Plan | 10 days prior to any work | ||||||||||||||||||||
| 19 | Select Fill Sieve Analysis | 1 | 1 | NTP+5 days | ||||||||||||||||||
| 20 | Select Fill Chem. Analysis (Where Applicable) | 1 | 1 | NTP+5 days | ||||||||||||||||||
| 21 | Soil Compaction Test Results | 1 | 1 | Within 3 days after test results are made available | ||||||||||||||||||
| 22 | Concrete Mix Design per ACI | 1 | 1 | NTP+5 days | Including Break History | |||||||||||||||||
| 23 | Slurry Seal Mix Design | 1 | 1 | NTP+5 days | ||||||||||||||||||
| 24 | Concrete Batch Tickets, Each Truck | 1 | 1 | Following day | ||||||||||||||||||
| 25 | Concrete 7 and 28 Day ACI Compressive Strength Test Results | 1 | 1 | Within 3 days after test results are made available | ||||||||||||||||||
| 26 | Product Data - Expansion Joint Sealant | 1 | 1 | NTP+5 days | ||||||||||||||||||
| 27 | Concrete Aggregate Sieve Analysis | 1 | 1 | NTP+5 days | ||||||||||||||||||
| 28 | Concrete Curing Compounds, Admixtures, Joint Sealants, Expansion Joints, and Asphalt Crack Sealant Materials | 1 | 1 | NTP+5 days | ||||||||||||||||||
| 29 | Sampling and Testing, Aggregate Base - Sieve Results, Field Density Tests | 1 | 1 | Within 3 days after test results are made available | ||||||||||||||||||
| 30 | Asphalt Mix Design | 1 | NTP+5 days | |||||||||||||||||||
| 31 | Asphalt Test Reports - Aggregates | 1 | 1 | Within 3 days after test results are made available | ||||||||||||||||||
| 32 | Asphalt Cement Binder Certificates | 1 | 1 | NTP+5 days | ||||||||||||||||||
| 33 | Product Data - Prime Coat and Tack Coat Emulsion | 1 | 1 | NTP+5 days | ||||||||||||||||||
| 34 | Cast Iron Truncated Domes | 1 | 1 | NTP+5 days | ||||||||||||||||||
| 35 | Product Data - Paint for Pavement Markings and Glass Beads | 1 | 1 | NTP+5 days | ||||||||||||||||||
| 36 | Product Data - Thermoplastic Compound | 1 | 1 | NTP+5 days | ||||||||||||||||||
| 37 | Equipment - List of proposed Equipment for paint and markings. | 1 | 1 | 1 | NTP+5 days | |||||||||||||||||
| 38 | Equipment - Asphalt Milling Equipment to be used. | 1 | 1 | 1 | NTP+5 days | |||||||||||||||||
| 39 | Product Data - Instalation of Asphalt Sealant Material | 1 | 1 | NTP+5 days | ||||||||||||||||||
| 40 | Samples - Asphalt Crack Sealant Material | 1 | 1 | NTP+5 days | ||||||||||||||||||
| CLOSEOUT | ||||||||||||||||||||||
| 41 | O&M Maintainance data, manuals and Manufacturer's Warranties | 1 | Install + 4 days | |||||||||||||||||||
| 42 | Factory and Field Test Certificates, Logs and Test Results | 1 | 1 | Before Acceptance | ||||||||||||||||||
| 43 | As Built Submittal per AEC Standards on CD | 3 | Final + 7 days |