Attachment_4_GLEN_03-1026_Form_66_Submittal_Log.xlsx

XLSX spreadsheet 21 KB Posted

Attached to
Maintain Pavement Base-wide Federal contract opportunity
Solicitation number
FA255017R1002
Issued by
Department of the Air Force Space Command

About this file

Form 66 Submittal Log

View the file

Other files for this federal contract opportunity

Other files attached to Maintain Pavement Base-wide, newest first.
File Type Posted
FA255017R10020001.pdf PDF
GLEN_03-1026_Pre-Proposal_RFI_Responses.docx DOCX document
Attachment_7_Design_Guide_Version_March_2016.pdf PDF
FA255017R1002.pdf PDF
Attachment_6_Wage_Determination_CO170018.pdf PDF
Attachment_1_GLEN_03-1026_SOW.docx DOCX document
Attachment_5_GLEN_03-1026_Bid_Schedule.xlsx XLSX spreadsheet
Attachment_3_GLEN_03-1026_Project_Drawings.pdf PDF
Attachment_2_GLEN_03-1026_Specifications.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

SCHEDULE OF MATERIAL SUBMITTALS (Paving IDIQ)PROJECT NO.PROJECT NAMESOLICITATION /CONTRACT NUMBER
GLEN 03-1026Maintain Pavement Base Wide AreasBUILDING 210, 220, 500 AND 440/442 PARKING LOTS
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
LINE NUMBERNote: 3 copies required per submittal. Government will retain all submittals.CERTIFICATE OF COMPLIANCESHOP DRAWINGSCOLOR SELECTIONMANUFATURUR'S RECOMMENDATIONCATALOG DATAO&M RECOMMENDATIONSCALCULATIONSWARRANTYDRAWINGSREPORTTEST RESULTSREQUIRED SUBMISSION DATEDATE TO CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSAPPROVEDDISAPPROVEDCONTRACTOR SUBMITTALFINAL APPROVALREMARKS
GENERAL
1Approved Form 103, BCE Work Clearance RequestXPrior to commencment of workWith Map Accureately Showing Work Area
2Project Specific MSDS SheetsXNTP + 5 daysPrior to Mobilization
3Form-3064 Contract Progress ScheduleXBid Submittal
4Form-3065 Contract Progress ReportXEach Draw
5Health, Safety, and Environment Plan(s)1NTP + 5 days
6Traffic Control Plans - For Each Phase of Construction11NTP + 10 days
7Contractor's QA/QC Plan1NTP + 5 days
8Business Telephone and Directory1NTP + 5 days
9Site Visit Meeting Minutes1NTP + 5 days
10Construction Schedule1NTP + 5 days and weekly updates
11Salvageable Material1NTP + 5 days
12Mothly Solid Waste Reporting1Monthly Reports
13Hydrant Connection request110 days prior to any work
14Utility Outage Request110 days prior to the proposed outage
15Traffic Change Request110 days prior to commencing with construction activites
16Confined Space Permit15 days prior to work in a confined space
CIVIL
17Current Backflow Preventer Inspection Cert.1110 days prior to any work
18Joint layout Plan10 days prior to any work
19Select Fill Sieve Analysis11NTP+5 days
20Select Fill Chem. Analysis (Where Applicable)11NTP+5 days
21Soil Compaction Test Results11Within 3 days after test results are made available
22Concrete Mix Design per ACI11NTP+5 daysIncluding Break History
23Slurry Seal Mix Design11NTP+5 days
24Concrete Batch Tickets, Each Truck11Following day
25Concrete 7 and 28 Day ACI Compressive Strength Test Results11Within 3 days after test results are made available
26Product Data - Expansion Joint Sealant11NTP+5 days
27Concrete Aggregate Sieve Analysis11NTP+5 days
28Concrete Curing Compounds, Admixtures, Joint Sealants, Expansion Joints, and Asphalt Crack Sealant Materials11NTP+5 days
29Sampling and Testing, Aggregate Base - Sieve Results, Field Density Tests11Within 3 days after test results are made available
30Asphalt Mix Design1NTP+5 days
31Asphalt Test Reports - Aggregates11Within 3 days after test results are made available
32Asphalt Cement Binder Certificates11NTP+5 days
33Product Data - Prime Coat and Tack Coat Emulsion11NTP+5 days
34Cast Iron Truncated Domes11NTP+5 days
35Product Data - Paint for Pavement Markings and Glass Beads11NTP+5 days
36Product Data - Thermoplastic Compound11NTP+5 days
37Equipment - List of proposed Equipment for paint and markings.111NTP+5 days
38Equipment - Asphalt Milling Equipment to be used.111NTP+5 days
39Product Data - Instalation of Asphalt Sealant Material11NTP+5 days
40Samples - Asphalt Crack Sealant Material11NTP+5 days
CLOSEOUT
41O&M Maintainance data, manuals and Manufacturer's Warranties1Install + 4 days
42Factory and Field Test Certificates, Logs and Test Results11Before Acceptance
43As Built Submittal per AEC Standards on CD3Final + 7 days

Sheet2

Sheet3

File details come from the government source that posted it. Updated .