Amendment 04 - Questions and Answers - FA252121B0004 - Utilities.pdf

PDF 152 KB Posted

Attached to
Construct Utilities Flight Control Road, Cape Canaveral SFS, FL Federal contract opportunity
Solicitation number
FA252121B0004
Issued by
Department of the Air Force Space Command

About this file

This document provides questions and answers regarding Solicitation FA252121B0004 to construct utilities on Flight Control Road at Cape Canaveral Space Force Station in Florida. The project scope involves installing new sanitary sewer, underground water, communication utilities and infrastructure with a period of performance not to exceed 180 days from notice to proceed. The work includes excavation for utility installation and water main construction. The solicitation is for a firm-fixed-price construction contract between $1 million to $5 million issued as a total small business set-aside. Offerors must meet small business criteria to be eligible for award, and all proposed costs and prices must remain valid until January 15, 2022. The federal agency is the Department of the Air Force Space Command.

View the file

Other files for this federal contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS & ANSWERS

Solicitation: FA252121B004 Project Number: DBEH 20-1515

Project Description: Construct Utilities Flight Control Road Cape Canaveral SFS, FL

Ref: Technical Specification: GENERAL. Referencing Q.22 and Q.23 below.

Q33. We understand a State of FL utility contractor would be acceptable but how about an out of state UG licensed contractor from AL or GA?

A22. Yes.

Ref: Technical Specification: Sheet C-503 Paragraph Notes #8 SOW/Technical

Specification/Drawings paragraph/page - Certifications/requirements

Q22. Sheet C-503 Note 8, BFP Assembly Notes, states that the potable water service shall be installed by a state licensed plumbing contractor. Please confirm that the site work including potable water may be installed by a company with a Licensed General Contractor or a Licensed

Underground Utilities Contractor with no additional requirement for a licensed plumber.

A22. A State of Florida licensed UG utility contractor will be acceptable.

Ref: Technical Specification: Sheet C-503 Paragraph Notes #8 SOW/Technical

Specification/Drawings paragraph/page Certifications/requirements

Q23. Sheet C-503 Note 8, BFP Assembly Notes, states that the fire services shall be installed by a state licensed fire sprinkler contractor. Please confirm that the site work including fire service, potable water and other utilities may be installed (in all areas to within 5 feet of a building) by a company with a Licensed General Contractor or Licensed Underground Utilities Contractor with no additional requirement for a licensed fire sprinkler contractor.

A23. A State of Florida licensed UG utility contractor will be acceptable.

**NOTE: Q.22 & Q.23 are re-listed in this document for reference purposes only.