F5A3CF1196AW01 SOO Cabinet Installation NAS JRB FW 8 Jul 20.docx
DOCX document 17 MB Posted
- Attached to
- FA667521R0021 - Network Cabinet Install
- Solicitation number
- FA667521R0021
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOO Cabinet Installation NAS JRB FW REV1 6 Aug 21.pdf | ||
| RFI Form.pdf | ||
| SCA_2015-5231.pdf | ||
| Solicitation - FA667521R0021.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF OBJECTIVES
Cabinet Installation in 7 Buildings NAS JRB Fort Worth, TX 15 July 2021
DESCRIPTION OF SERVICES
This Statement of Objectives (SOO) defines the requirement for Communications installation of cabinets and the removal of any existing outdated patch cable wiring (PW), racks, Abandon-In-Place (AIP) clean up at 8 comm rooms in 7 buildings at NAS JRB Fort Worth, TX. It also defines the requirement for the Contractor to test as well as provide the re-start support of the NIPRNet equipment in those buildings.
MINIMUM QUALIFICATIONS
All qualifications shall be submitted by the Contractor to the government for verification.
PROJECTS
3.1 Project Requirement
The Contractor shall provide all management, personnel, equipment, tools, transportation, supervision, and other incidentals necessary to install new cabinets, network equipment from the existing racks which includes network switches, power, grounding, and associated hardware in 8 comm rooms in 7 different buildings. The Contractor shall also install new green patch cables for the network equipment. The Contractor shall verify with 301 CS for any additional items that may be needed during the site walk-through. Engineering, installation and testing will be implemented by contract.
This project shall be performed as a turn-key project for the 301st Communications Squadron (CS).
For the following Comm rooms the government will discuss with contractor the best installation practice/location for cabinets during site survey.
1. Building #1235 , Comm Room #112: The Contractor shall verify with the 301 CS/SCOI for the location of the new cabinet and shall use best practice to install the new cabinet and relocate the equipment from the existing rack to the new cabinet. The Contractor shall provide required patch cables for all network equipment. Wherever possible, utilize existing cable trough, Arlington loop or J hook to secure PW to the structure and shall not block access to the space above the ceiling….
2. Building #1615 , Comm Room “Mec”: The Contractor shall verify with the 301 CS/SCOI for the location of the new cabinet and shall use best practice to install the new cabinet and relocate the equipment from the existing rack to the new cabinet. The Contractor shall provide required patch cables for all network equipment. Wherever possible, utilize existing cable trough, Arlington loop or J hook to secure PW to the structure and shall not block access to the space above the ceiling….
3. Building #1649 , Comm Room #105: The Contractor shall verify with the 301 CS/SCOI for the location of the new cabinet and shall use best practice to install the new cabinet and relocate the equipment from the existing rack to the new cabinet. The Contractor shall provide required patch cables for all network equipment. Wherever possible, utilize existing cable trough, Arlington loop or J hook to secure PW to the structure and shall not block access to the space above the ceiling….
4. Building #1650 , Comm Room “301 OSF Storage” : The Contractor shall verify with the 301 CS/SCOI for the location of the new cabinet and shall use best practice to install the new cabinet and relocate the equipment from the existing rack to the new cabinet. The Contractor shall provide required patch cables for all network equipment. Wherever possible, utilize existing cable trough, Arlington loop or J hook to secure PW to the structure and shall not block access to the space above the ceiling….
5. Building #1650 , Comm Room #123: The Contractor shall verify with the 301 CS/SCOI for the location of the new cabinet and shall use best practice to install the new cabinet and relocate the equipment from the existing rack to the new cabinet. The Contractor shall provide required patch cables for all network equipment. Wherever possible, utilize existing cable trough, Arlington loop or J hook to secure PW to the structure and shall not block access to the space above the ceiling….
6. Building #1655 , Comm Room #140: The Contractor shall verify with the 301 CS/SCOI for the location of the new cabinet and shall use best practice to install the new cabinet and relocate the equipment from the existing rack to the new cabinet. The Contractor shall provide required patch cables for all network equipment. Wherever possible, utilize existing cable trough, Arlington loop or J hook to secure PW to the structure and shall not block access to the space above the ceiling….
7. Building #1790 , Comm Room #: The Contractor shall verify with the 301 CS/SCOI for the location of the new cabinet and shall use best practice to install the new cabinet and relocate the equipment from the existing rack to the new cabinet. The Contractor shall provide required patch cables for all network equipment. Wherever possible, utilize existing cable trough, Arlington loop or J hook to secure PW to the structure and shall not block access to the space above the ceiling….
8. Building #3356 , Comm Room “Mec”: The Contractor shall verify with the 301 CS/SCOI for the location of the new cabinet and shall use best practice to install the new cabinet and relocate the equipment from the existing rack to the new cabinet. The Contractor shall provide required patch cables for all network equipment. Wherever possible, utilize existing cable trough, Arlington loop or J hook to secure PW to the structure and shall not block access to the space above the ceiling….
3.2 Engineering
The Contractor shall ensure the relocation and installation of new cabinets and existing NIPRNet premise wiring will not impact the critical missions of all 8 buildings.
3.3 Technical Exchange Meeting (TEM)
The Contractor shall conduct a TEM to review project and/or technical issues. The TEM provides a forum for the Government and Contractor to exchange information about the current project status, installation schedules, and known or expected problems. These meetings shall be coordinated with the 301 CONF/PK Contract Administrator and 301 CS/SCX. A written agenda shall be provided to the 301 CS/SCX at least 48 hours prior to the meeting. The Contractor will maintain minutes of the TEM and relative follow-on activities and distribute them to the Contract Administrator, attendees and other lead project member not in attendance. Meeting locations shall be determined by the 301 CS/SCX and provided to the Contractor after source selection.
3.4 Contractor Furnished (CF) Materials
All the materials, cable patch panels, patch panels for the project shall be purchased by the Contractor. Contractor shall provide a list of material and any other materials needed for the installation. Any unused materials will remain in the custody of the 301 CS. Contractor will provide all equipment and personnel required for the installation.
3.5 Installation
All cabinets and cables will be installed IAW applicable standards specified in Section 6. Cable wire management must be provided where applicable to provide a neat and orderly installation. All cables will be fanned and formed using either Velcro or nylon tie-wraps. The Contractor shall clean up all installation and construction related dust and debris from the work site daily.
Specific details will be reviewed during a walk through with 301 CS and 301 BCE personnel. Any significant changes will need to be coordinated with 301 CS and 301 BCE and personnel. Contractor will coordinate with 301 CS and 301 BCE personnel to locate any permanent infrastructure required to support project.
3.5.1 Removal of Existing Cable & Equipment
All existing outdated NIPRNet patch cables, patch panels, racks and associated equipment will be removed and disposed of by the Contractor after the new cabinets have been installed, tested, and users are able to utilize the new infrastructure.
3.5.2 Equipment Racks/Cabinets
New equipment cabinets required will be provided by the government.
3.5.4 Connectivity to Network Equipment
All required green UTP patch cables from the network equipment to the new Category 6 patch panels shall be provided by the contractor.
3.5.5 Pre-Installation Survey (PIS)
Prior to arrival, the Contractor shall ensure any required Government support is complete, and verify site conditions (IAW FAR 52.236-3, and FAR 52.236-7, as applicable). The Contractor shall immediately notify the Contracting Officer (CO) of any pre-installation survey discrepancies.
3.5.6 Testing
The Contractor shall furnish all test equipment and personnel required to conduct testing. During any testing phase, the Government reserves the right to perform any of the Contractor performed inspections and tests to assure results conform to prescribed requirements. The Contractor shall record all inspections and tests as they are accomplished and make all test sheets/results available to the 301 CS Quality Assurance Evaluator (QAE) for review as tests are completed. The Contractor shall notify the 301 CS/SCX representative at least three working days prior to any testing and shall make available all testing standards and criteria used to accomplish testing. All testing will be IAW accepted industry standards for the type of test being conducted. The Contractor shall provide test reports to the Government within 10 days of completing the testing. The Contractor is required to locate/repair any testing irregularities if caused by the installation. Cable testing will be IAW RUS Bulletin 1753F-201. The Contractor shall accomplish the following tests:
3.5.6.1 In-progress Testing
In-progress tests shall be conducted on a continual basis to ensure equipment and material are being properly installed and configured to meet the project requirements during implementation.
3.5.6.2 Post-implementation Testing
Upon completion of installation, post-implementation tests shall be accomplished to ensure the entire system is properly configured, the requirements of the project have been met, results of cable tests confirm rating of cable, and the system is ready to cutover.
3.5.7 Acceptance Criteria
Acceptance of the installation will be dependent upon all installed cable testing at levels deemed acceptable under the Contractor-submitted and Government-approved Test Plan.
DELIVERABLES
All deliverables are subject to Government acceptance and approval. They shall meet professional standards and the requirements set forth in this SOO. All deliverables shall be produced using recommended software tools/versions as accepted by the Government. The Contractor shall submit the following deliverables to the contracting officer and administrator.
As-Built Drawings (A001) The contractor shall provide updated drawings in Visio and pdf formats. These drawings shall depict the entire pathway and details of the installation, including but not limited to: labeling, cables, As-Built Rack Elevation, Inside Cable Plant drawings, patch panel locations, labeling, and drop locations.
Project and Work Schedule (A002):
The contractor shall provide a complete milestone schedule that denotes major activities to include time-phased start and completion dates for this project and sub-projects associated with the installation. Also, the schedule shall detail the weekly activities of each person on site.
Status Report (A003):
The contractor shall provide a weekly status report that shall include a minimum of the current progress towards overall project completion, any obstacles to implementation encountered, and any damage to the working environment caused by the installation. Report shall be provided in electronic format (Soft Copy).
Test Plan (A005):
The contractor shall provide a detailed test plan for each site in accordance with the Original Equipment Manufacturer’s installation manuals and practices. Test plan shall include a functional test of network connectivity (printed listing of test results) for each of the installed components.
Test Report (A006):
The contractor shall test and provide a test report for each site in accordance with the contractor developed test plan. For locations selected by the Communications Squadron or COR, the contractor shall retest and revalidate the test report under observance of a Government Representative.
GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES
5.1 Floor Plans
The government shall provide pictures of current network cabinets in all buildings identified in this SOO (See Attachment).
GENERAL INFORMATION
Applicable Documents The Contractor shall comply with all laws, codes, regulations, and statutes applicable to performance of this contract, including but not limited to those specified in the tables below. The following tables provide locations where some documents may be obtained. It is the Contractor's responsibility to obtain and adhere to all applicable standards.
6.2 Federal Government
The Contractor shall comply with all applicable federal standards, laws, codes, regulations, and statutes applicable to performance of this contract.
6.3 Privacy Act
Work on this project may require that Contractor personnel have access to Privacy Information. Contractor personnel, any Contractor representative, or any subcontractor shall adhere to the Privacy Act, Title 5 of the U.S. Code, Section 552a and applicable agency rules and regulations.
6.4 State, Local and Site-Specific Regulations
The Contractor shall comply with all applicable state, local, and site-specific codes, regulations, and statutes applicable to performance of this contract.
6.5 Commercial Standards and Manuals
The Contractor shall comply with the following commercial standards where applicable in the performance of this contract. It is the Contractor's responsibility to identify and obtain applicable standards and best commercial practice documentation. Should a conflict arise between this SOO and any commercial standard referenced, the Contractor shall make the government aware of the conflict. The government shall determine which standard applies and the Contractor shall implement this standard.
ANSI/TIA/EIA standards shall be a secondary set of governing standards for all telecommunications cabling plant designs, testing and installations. The primary ANSI/TIA/EIA standards applicable to this infrastructure program are 568-B, Commercial Building Telecommunications Cabling Standard, and 569-B, Commercial Building Standard for Telecommunications Pathways and Spaces. These standards establish the minimum requirements for telecommunications cabling within an office environment. They recommend topology and maximum performance distance for various topologies. They establish media parameters, which determine network performance distance for various topologies. They specify connector and pin assignments to ensure inter-connectivity. Moreover, they establish the useful life of telecommunications cabling systems as being a minimum of ten years. Designers and installation teams are responsible for adhering to these accepted industry standards. More stringent standards can be adopted, however, care must be exercised to ensure the more stringent characteristics are followed for the complete horizontal cabling system including connecting hardware, patch cords, equipment cords, work areas cords, and cross-connect wiring. These documents may be obtained through Global Engineering Documents, 1-800-854-7179.
| NUMBER |
| TITLE |
| WEBSITE OR LOCATION |
| BICSI |
| Building Industry Consulting Service International, Inc (BICSI) |
| http://www.bicsi.org/ |
| NFPA 70 (2002) |
| National Fire Protection Association (NFPA), National Electric Code (NEC) |
| http://www.nfpa.org/ |
| ANSI |
| American National Standards Institute (ANSI) and Internet Standards Resources |
| http://www.ansi.org/ |
| EIA/TIA |
| Engineering: EIA/TIA Standards |
See Commodity Specific Appendices and Individual Task Orders http://www.eia.org/ http://www.tiaonline.org/
| TIA/EIA-526-7 (Feb 2002) |
| Measurement of Optical Power Loss of Installed Single-Mode Fiber Cable Plant – OFSTP-7 |
| http://www.eia.org/ |
http://www.tiaonline.org/
| TIA/EIA-526-14 (Aug 1998) |
| Optical Power Loss Measurement of Installed |
Multimode Fiber Cable Plant – OFSTP-14 http://www.eia.org/ http://www.tiaonline.org/
| TIA/EIA-568-B.1 (Mar 2004) |
| Commercial Building Telecommunications Cabling Standard Part 1: General Requirements |
| http://www.eia.org/ |
http://www.tiaonline.org/
| TIA/EIA-568-B.2 (Dec 2003) |
| Commercial Building Telecommunications Cabling |
Standard Part 2: Balanced Twisted-Pair Cabling Components http://www.eia.org/ http://www.tiaonline.org/
| TIA/EIA-568-B.3 (Apr 2002) |
| Commercial Building Telecommunications Cabling Standard Part 3: Optical Fiber Cabling Components Standard |
| http://www.eia.org/ |
http://www.tiaonline.org/
| TIA/EIA-569-A (Dec 2001) |
| Commercial Building Standards for Telecommunications Pathways and Spaces |
| http://www.eia.org/ |
http://www.tiaonline.org/
| TIA/EIA-570 (Apr 2004) |
| Residential Telecommunications Cabling Standard |
| http://www.eia.org/ |
http://www.tiaonline.org/
| TIA/EIA-598 (Dec 2001) |
| Optical Fiber Cable Color Coding |
| http://www.eia.org/ |
http://www.tiaonline.org/
| TIA/EIA-606 (May 2002) |
| Administration Standard for the Telecommunications Infrastructure of Commercial Buildings |
| http://www.eia.org/ |
http://www.tiaonline.org/
| TIA/EIA-607 (Oct 2002) |
| Commercial Building Grounding and Bonding Requirements for Telecommunications |
| http://www.eia.org/ |
http://www.tiaonline.org/
| TIA/EIA-758 (Apr 1999) |
| Customer-Owned Outside Plant Telecommunications Cabling Standard |
| http://www.eia.org/ |
http://www.tiaonline.org/
| EIA-310 (Sep 1992) |
| Racks, Panels and Associated Equipment |
| http://www.eia.org/ |
http://www.tiaonline.org/
| EIA SP-2840-A (Mar 1994) |
| Commercial Building Telecommunications Cabling Standard |
| http://www.eia.org/ |
http://www.tiaonline.org/
| ICEA S-80-576 (2002) |
| Telecommunications Wire and Cable for Wiring of Premises |
| Insulated Cable Engineer Association, Inc., P.O. Box P, South Yarmouth MA 02664; Telephone (508) 394-4424 |
| ICEA S-83-596 (2001) |
| Fiber Optic Premises Distribution Cable |
| Insulated Cable Engineer Association, Inc., P.O. Box P, South Yarmouth MA 02664; Telephone (508) 394-4424 |
| GR-409 (Jun 1994) |
| Generic Requirements for Premises Fiber Optic Cable |
| http://telecom-info.telcordia.com/site-cgi/ido/index.html |
| GR-20 (Jul 1998) |
| Generic Requirements for Optical Fiber and Optical Fiber Cable |
| http://telecom-info.telcordia.com/site-cgi/ido/index.html |
| NEMA TC 2 (2003) |
| Electrical Polyvinyl Chloride (PVC) Tubing and Conduit |
| http://www.nema.org/index_nema.cfm/1260/ |
| NEMA TC 6&8 (2003) |
| PVC Plastic Utilities Duct for Underground Installations |
| http://www.nema.org/index_nema.cfm/1260/ |
| NEMA TC 9 (2004) |
| Fittings for PVC Plastic Utilities Duct for Underground Installation |
| http://www.nema.org/index_nema.cfm/1260/ |
| MIL-F-15733 |
| Military Specifications for Filters, Radio Frequency Interference |
| http://www.dscc.dla.mil/Downloads/MilSpec/Docs/MIL-PRF-15733/prf15733.pdf |
| MIL-STD-220 |
| RFI Filters, Methods Testing |
| http://www.dscc.dla.mil/Downloads/MilSpec/Docs/MIL-STD-220/std220.pdf |
| MIL-HDBK-419 |
| Grounding, Bonding, and Shielding for Electronic Equipments and Facilities |
| http://www.uscg.mil/hq/tcpet/tpf/etsms/Mil-STDs/MILHDBK419.pdf |
| NACSEM 5204 |
| (C) Shielded Enclosures (U) |
| NSA 65-6 |
6.6 Contractor Personnel
6.6.1 Program Manager
The Contractor shall provide a Program Manager (PM) and alternate(s) responsible for contract performance and continuity. The Contractor shall identify in writing to the 301 CONF Contracting Officer the Program Manager or alternate's range of authority to act for the Contractor relating to daily contract operation.
6.6.2 Site Point of Contact (POC)
The Contractor shall designate the Contractor's on-site team leader and alternate(s) as the Site POC for this project in their Site Visit Request Letter. The Site POC or alternate(s) shall be on site during duty hours until project completion. The Site POC shall be the interface for all work site communications with the Government through the 301 CONF Contracting Officer, including quality, safety, and discrepancy matters.
6.6.3 General Personnel Requirements
The Site Visit Request Letter shall be submitted to the Contracting Officer not later than one week prior to base visit.
6.7 Security
Contractor must coordinate with appropriate base personnel and comply with all required security measures for gaining entry and working in all buildings identified in this SOO. The Contractor may require government escorts with proper building entry authorization and identification while in all buildings identified in this SOO. Some areas in those buildings may require prior coordination through base personnel in specified work areas before entering and work can be accomplished.
6.7.1 Key Control/Combinations
The Contractor shall establish and implement methods of assuring control and safeguard of all Government keys or lock combinations issued to the Contractor. GOVERNMENT KEYS SHALL NOT BE DUPLICATED. See FAR 52.245-2(e) (2).
6.7.2 Notification
The Contractor shall immediately notify the site security police and the Contracting Officer of any occurrences of lost or duplicated keys or compromise of combinations. In the event of a compromise, the Contractor may be required to provide appropriate consideration.
6.8 General Information
6.8.1 Period of Performance.
The period of performance for the project shall be no more than 60 days from the notice to proceed.
6.8.2 Place of Performance.
The place of performance is NAS JRB Fort Worth, TX.
6.8.3 Hours of Operation.
The Contractor shall routinely work during normal duty hours from 7:00AM – 4:00PM CST of the site. However, mission requirements may necessitate work outside normal hours (nights and/or weekends), especially if existing service must be interrupted. Any site work requested by the Contractor to be performed outside of normal duty hours shall be coordinated with and approved by the 301 CONF Contracting Officer at least 10 calendar days in advance.
6.8.4 Holidays/Down Days.
The Contractor shall not perform under this contract on federal holidays or site-unique down-days unless expressly authorized by the Contracting Officer and coordinated with the 301 CS/SCXP Project Manager.
6.8.5 Base Support.
The Contractor shall identify any base support requirements (for example, laydown and storage areas, access to base water/fire hydrants, etc.) necessary to complete this project in their proposal. The Contractor shall return all government furnished lay-down and storage areas to their original condition upon completion of the project.
6.9 Safety
The Contractor shall be responsible for complying with all local, state and federal safety guidelines.
6.9.1 Accident/Incident Reporting and Investigation
The Contractor shall record and report all available facts relating to each instance of accidental damage to Government property or injury to either Contractor or Government personnel to the Base Safety Office. The Contractor shall secure the scene of any accident and wreckage until released by the accident investigative authority through the Contracting Officer. If the Government elects to conduct an investigation of the incident, the Contractor shall cooperate fully and assist the Government personnel until the investigation is completed.
6.9.2 Subcontractor Safety
The Contractor shall be responsible for ensuring subcontractors satisfy the safety and health requirements set forth in Occupational and Safety Health Administration (OSHA) standards, any local procedures, and other provisions of this contract.
6.10 Hazardous Materials, Environmental and Other Local Requirements The Contractor shall meet with appropriate local environmental, and civil engineering offices prior to the commencement of work.
6.11 Potential Problems
The Contractor shall verify with 301 CS and 301 BCE for any potential problems with the projected work in areas that may contain asbestos, hazardous materials, and hazardous wastes and local procedures to be followed in the event such problems are encountered. The Contractor shall stop work and notify the 301 CS/SCX or other appropriate personnel when encountering such problems.
6.12 Disposal/Reporting
The Contractor shall comply with local procedures concerning the use, disposal, or reporting of hazardous materials.
6.12.1 Hazardous Material Identification
The Contractor shall submit Material Safety Data Sheets (MSDS) IAW FAR Clause 52.457-3 for any hazardous materials (paints, solvents, cleaners, encapsulating compound, etc.) to be used in performance of the contract. The Contractor shall file the MSDS(s) with the Base Environmental Management Office prior to using hazardous material.
6.12.2 Environmental Assessment
The Contractor shall ensure that any required environmental assessments have been accomplished and that any problems identified have been resolved before beginning work. The Contractor shall immediately notify the Contracting Officer if an environmental assessment has not been accomplished.
6.13 Identification / Marking
The Contractor shall clearly mark all Contractor Furnished Property (CFP) with their company's name, contract number, and project number. The Contractor shall place an easily read, very visible, sign (minimum 8.5" x 11") on large containers, construction equipment, or un-manned rental vehicles while on the Government installation indicating the company name; contract/task order number; project title; and both the Contractor and Site POC's names and local telephone numbers.
6.14 Construction Equipment
The Contractor shall provide construction equipment (e.g., backhoes, trenchers, loaders, etc) required to support implementation. The Contractor shall be responsible for transportation of construction equipment to/from the work site, as well as their security.
6.15 Transportation and Storage of Material/Equipment
The Contractor shall transport and store all CFM and CFE required for completion of the contract requirements.
6.16 Commodity-Specific Material/Equipment Requirements
6.16.1 Metallic Inside Cable
Inside cable and wiring shall be Underwriters Laboratories (UL) listed and provided IAW Insulated Cable Engineer Association (ICEA) S-80-576 and NFPA 70. Riser cable shall be UL type CMR rated. Cables placed in air plenums shall be UL type CMP rated. No cable or wire shall be sized smaller than 24 AWG. All cable will be TIA/EIA Category 6 rated, and installed IAW TIA/EIA-568-B. All installed cable shall be plenum rated.
6.16.2 Fiber Optic Cable
Where required, Underwriters Laboratories (UL) Listing as Optical Fiber Conductive (OFC) or Optical Fiber Nonconductive (OFN) shall be the minimum requirement for cable used in building distribution. UL Listing as Optical Fiber Conductive Riser (OFCR) or Optical Fiber Nonconductive Riser (OFNR) shall be the minimum requirement for vertical runs and distribution cable installed in building risers. UL listing as Optical Fiber Conductive Plenum (OFCP) or Optical Fiber Nonconductive Plenum (OFNP) shall be the minimum requirement for cables installed in air plenums, ducts, and other air handling spaces. Fiber optic cables intended primarily for use within a facility from the serving building optical distribution center to the work area outlet shall contain individually jacketed, tight-tube buffered optical fibers for use in cross-connect/interconnect applications, intra-building backbone and horizontal wiring. All fiber optic cable used indoors shall comply with REA PE-90 paragraphs 2 through 6, except for loose tube requirements, and Telcordia GR-409. The Contractor shall provide fiber optic cables suitable for specific environments and applications. All optical fiber cable shall be terminated on Fiber Optic Distribution Panels (FODP). Intra-building backbone and horizontal fiber optic cable will not be spliced. All runs will be continuous between FODPs.
6.16.3 Fiber Optic Distribution Panel (FODP)
Where required, the FODP shall consist of a splice organizer, connector sleeves and other miscellaneous hardware. The FODP shall terminate indoor single mode cable. The FODP shall allow easily accessible patching and distribution. The splice organizer shall provide protection for both the splices and the fiber. In addition, the splice organizer shall be equipped with a tray to store excess fiber (minimum 4 meter length) in a neat and orderly manner without kinks or twists. The FODP shall be provided in wall and rack mount versions of 19 or 23-inch widths; as required for rack/cabinet size. The FODP shall have access from top or bottom and be able to interconnect when multiple FODP are placed together in the same termination point. Connectors and connector sleeves used with the FODP. Designation labels/strips shall be provided to identify fiber.
6.16.4 Fiber Optic Connector
Where required, the Contractor shall provide SC compatible connectors. The connectors shall have less than 1 decibel (dB) loss per mated coupling. The connector loss shall not exceed 2.0 dB after 500 disconnect/reconnect cycles. Unused optical connectors shall be equipped with protective covers. The connectors shall be installed on inside building cables and equipment inter-connect cables.
6.16.5 Equipment Cabinets
The Government will furnish all required cabinets..
6.16.6 Indoor Conduit System
Where required, an indoor conduit system shall be provided. The conduit system shall be comprised of conduit, pull boxes, bends, cable guards, and couplers, along with installation hardware. Non-metallic material shall be used for those secure areas specified.
6.16.7 Outlets
Where required, all outlets shall be Federal Communication Commission (FCC) approved. Each indoor jack shall be an 8-position, 8-wire modular jack (universal service ordering code (USOC) type), and shall be Federal Communication Commission (FCC) approved. Both flush and surface mounted wall receptacles shall be provided as required. Flush mounted types shall be suitable for mounting in outlet boxes. Surface mounted types shall be suitable for mounting on walls and baseboards and shall not protrude more than one inch from the surface.
6.17 Site Specific Coordination
6.17.1 In-brief
The Contractor shall conduct an in-brief with the Contract Administrator and other site personnel before the start of site survey or implementation. The in-brief shall provide project overview and the project schedule (e.g. arrange for required escorts; QAP schedule; etc.).
6.17.2 Out-brief
The Contractor shall conduct an out-brief with the Contract Administrator and other site personnel at the conclusion of the site survey and implementation. The site survey out-brief shall inform the Government of survey results, including, all projected required major material, end-item system equipment, and all construction support requirements related to the project. The implementation out-brief shall inform the customer of implementation results and necessary maintenance issues. At the conclusion of the out-brief, the Contractor shall provide the site POC a written synopsis of the project which includes major issues or action items. The synopsis shall include a list of attendees. A copy of this synopsis shall be forwarded to the CO within 2 workdays of the out-brief.
6.17.3 Service Outages
The Contractor shall be responsible for preventing any unscheduled Contractor-caused interruptions of service. The Contractor shall coordinate planned outages with the site POC and QAP at least five workdays in advance of the outage if the implementation necessitates disruption of service, (e.g., communications, electrical, or other utilities).
6.17.4 Base POC List
| POC |
| NAME |
| ORG/FAS |
| COMM |
| Project Manager |
| Derek Faucett |
| 301CS/SCXP |
| 817-782-6498 |
| derek.faucett.3@us.af.mil |
Contractor POC
QAP
| 301 CS/SCX |
| Timothy Grimes |
| 301CS/SCX |
| 817-782-6507 |
| timothy.grimes.2@us.af.mil |
| CSI-B |
| Hoan Nguyen |
| 38ES/ENPO |
| 405-734-7625 |
| hoan.nguyen@us.af.mil |
Contracting Officer
Contract Administrator
301 CONF/PK
817-782-xxxx
7 LABELING
The Contractor shall provide an effective labeling and numbering scheme to ensure administration tasks are simplified, to include, moves, adds and changes can be carried out with little guesswork, unused capacity can be easily identified and failed components can easily and quickly be identified during troubleshooting and repair activities. Naming scheme shall be coordinated with the 301 CS/SCX and telecommunications outlets (duplex, quadplex, or triplex) shall be labeled as follows.
| 7.1 | Telecommunications Outlet Labeling | |
| 7.1.1 | Two Position UTP Wall Plate |
ROOM Actual room number from the facility drawings at time of design.
| TR | Actual TR or Equipment Room where the end of the wall plate cables terminate. In existing facilities with no Telecom Room (TR) numbers the TR room identifier shall be floor number, room number where room number starts with the letter A with additional TR labeled B, C etc. | |
| RACK # | Actual Rack number that contains the patch panel where the cable terminates. | |
| PATCH PANEL # | Actual patch panel number. | |
| PORT #’s | Actual port numbers in the patch panel |
The bottom position of the UTP wall plate shall be marked with the Room Number that the wall plate is installed. This information is reflected in the site cable plan.
Top Position Example:
110-1-1-1, 2
TR 110
Rack # 1 Patch Panel # 1 Port #’s 1,2 (On the patch panel)
Bottom Position Example:
32 = Room Number (Actual room # from the cable plan and facility drawings at time of design)
Top Position Example: (no comm. room identifier) 1A-1-1-1, 2 = TR 1A, Rack # 1, Patch Panel # 1, Port #’s 1,2 (On the patch panel)
Figure 1: Two-Position Wall Plate Numbering Scheme
| 7.1.2 | Four Position UTP Wall Plate | |
| ROOM | Actual room number from the facility drawings at time of design | |
| TR | Actual TR or Equipment Room where the end of the wall plate cables terminate. In existing facilities with no Telecom Room (TR) numbers the TR room identifier shall be floor number, room number where room number starts with the letter A with additional TR labeled B,C etc. | |
| RACK # | Actual Rack number that contains the patch panel where the cable terminates. | |
| PATCH PANEL # | Actual patch panel number. | |
| PORT #’s | Actual port numbers in the patch panel |
The bottom position of the UTP wall plate shall be marked with the Room Number that the wall plate is installed. This information is reflected in the site cable plan.
Top Position Example:
110-1-1-1, 2, 3, 4
TR 110
Rack # 1 Patch Panel # 1 Port #’s 1,2,3,4 (On the patch panel)
Bottom Position Example:
32 = Room Number (Actual room # from the cable plan and facility drawings at time of design)
Top Position Example: (no comm. room identifier) 1A-1-1-1, 2, 3, 4 = TR 1A, Rack # 1, Patch Panel # 1, Port #’s 1,2,3,4 (On the patch panel)
Figure 2: Four-Position Wall Plate Numbering Scheme
7.2 Fiber Patch Panel Labeling
For fiber patch panels where the fiber originates in another building it shall be labeled using the following format. Building number, strand count, type of fiber, and fiber end point building # or ITN #.
For example: B 1130 01-36 SM to ITN 1109 B1130 = The building # the patch panel is in and fiber is terminated.
01-36 = The number of fiber strands terminated SM = Type of fiber (Single mode) ITN 1109 = Other end where the fiber is terminated.
For fiber patch panels such as cable ties between comm. rooms in the building where the fiber originates in another room shall be labeled using the following format. Room number, strand count, type of fiber, and fiber end point in what room.
For example: Tie Rm 130 01-12 MM to Rm 220 Rm 130 = The room # the patch panel is in and fiber is terminated.
01-12 = The number of fiber strands terminated MM = Type of fiber (Multimode fiber) Rm 120 = Other end where the fiber is terminated.
7.3 High Density Patch Panel Labeling
Example: 1A4 1 – Floor A – Patch Panel in alpha order/per rack 4 – Port #4 as shown by picture above
7.4 Cables
All cables will be labeled using color labels on both ends with encoded identifiers per ANSI/TIA/EI
8.0 ATTACHMENTS: Pictures
image1.emf oleObject1.bin 110-1-1-1,2
A
B
| TR | 110 | |
| RACK | 1 | |
| PATCH PANEL | 1 | |
| PORT #s | 1,2 |
DATA OUTLETS (Color Coded. Site Specific Colors may be used in lieu of standard colors)
A - Outlet - White B - Outlet - Blue
ROOM NUMBER (Actual room number from site cable plan and facility drawings at time of network infrastructure site cable plan development.)
Example of a Single Dual Data Outlet Located in room 32 and terminating in TR 110, Rack # 1, Patch Panel # 1 and starting in port # 1 of the patch panel.
110-1-1-3,4
A
B
| TR | 110 | ||
| RACK | 1 | ||
| PATCH PANEL | 1 | ||
| STARTING PORT # | 3,4 |
DATA OUTLETS (Color Coded. Site Specific Colors may be used in lieu of standard colors)
A - Outlet - White B - Outlet - Blue
ROOM NUMBER (Actual room number from site cable plan and facility drawings at time of network infrastructure site cable plan development.)
Example of a Second Dual Data Outlet Located in room 32 and terminating in TR 110, Rack # 1, Patch Panel # 1 and starting in port # 3 of the patch panel.
image2.png image3.png image4.emf
Cabinet Install Pictures.pptx Building 1235 Comm Room 112
Building 1615 Comm Room “Mec”
Building 1648 Comm Room 1014
Building 1649 Comm Room 105
Building 1650 Comm Room “301 OSF Storage”
Building 1650 Comm Room 123
Building 1655 Comm Room 140
Building 3356 Comm Room “Mec” image1.jpeg image2.jpeg image3.jpeg image4.jpeg image5.jpeg image6.jpeg image7.jpeg image8.jpeg image9.jpeg image10.jpeg image11.jpeg image12.jpeg image13.jpeg image14.jpeg image15.jpeg image16.jpeg image17.jpeg image18.jpeg image19.jpeg image20.jpeg image21.jpeg image22.jpeg image23.jpeg image24.jpeg image25.jpeg image26.jpeg image27.jpeg image28.jpeg image29.jpeg image30.jpeg image31.jpeg image32.jpeg image33.jpeg image34.jpeg