RFI_3.docx
DOCX document 42 KB Posted
- Attached to
- Mobile Weapons Rack Storage System Federal contract opportunity
- Solicitation number
- F1C3475076A001
About this file
Most recent RFI. 27 May 2015
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFI__2.docx | DOCX document | |
| WR_picture-room-dimensions.pptx | PPTX presentation | |
| RFI__1.docx | DOCX document | |
| SOW_Weapons_Racks.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI for Weapons Storage System
1. Based on the ceiling height of 9' 10" double stacking the cabinets height won't be an issue. Would 50"H cabinets be acceptable?
a. Yes , As long as there is 18 inches clearance from the lowest point on the ceiling to the top of the storage system.
2. Any information available about how far the installation location is from the delivery dock? Is it ground level?
a. Both areas are in close to each other. Also, we do have loading docks available. It is ground level.
3. What about the debris removal? What is available and how far from installation location?
a. Boxes and small debris can be put into the dumpsters, otherwise they would have to be taken it to the AAFB landfield.
4. Logistically, if this all ships in one container will this be delivered to a base warehouse and then transported to the installation location by Andersen base logistics? Or do the vendors need to arrange delivery to the door which would include some storage cost at the port.
a. Vendors will arrange door to door delivery.
5. Are all the M9s in one cabinet? It appears they will be in the 61"H cabinet. Or what are they storing in the 61"H cabinet? IT appears all weapons are on UWR 3
6. Could you clarify the difference between the blue shaded carriages and the white carriages on the desired layout?
a. Blue is for possible future expansion (not a part of this solicitation). Please only quote for the white side.
7. What type of flooring is the mobile usint being installed on?
a. Cement floor.
NOTE: This procurement is for Spacesaver high-density mobile system or EQUAL. It does not have to be the exact item as long as it meets the requirement.