Exhibit D _ PM Fee Proposal Form.xlsx
XLSX spreadsheet 16 KB Posted
- Attached to
- GSOU J-460-PM School of Optometry
- Solicitation number
- PE-47200-RFQ-2026-000000126
- Issued by
- Brooks County, Georgia
About this file
This is a Program Management Fee Proposal Form for Project No. J-460 School of Optometry at Georgia Southern University in Statesboro, Georgia. The project is valued at $13,300,000 and is divided into three phases: Phase I (Predesign), Phase II (Design & Preconstruction), and Phase III (Construction). The program management services will be delivered across these three project phases with specific resource allocations and time commitments for each phase.
The proposed fee totals $430,920, representing 3.24% of the total project cost. The fee structure includes staffing costs across five primary positions: Project Director (Joe Jones, $150/hour, $3,000 total fee), Project Manager (John Smith, $120/hour, $177,600 total fee), Assistant Project Manager (Ann White, $120/hour, $139,200 total fee), Administrative Assistant (Sam Black, $60/hour, $40,320 total fee), and Contract Compliance Specialist (Jane Green, $100/hour, $60,800 total fee). Phase I allocates $69,800 in fees, Phase II allocates $154,360, and Phase III allocates $206,760. The proposal also includes $10,000 in reimbursable expenses distributed across the three project phases ($2,000 for Phase I, $3,000 for Phase II, and $5,000 for Phase III).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit E _ Contractor Affidavit.docx | DOCX document | |
| Exhibit F _ Proposer_s Disclosure Statement.doc | DOC document | |
| Exhibit A _ RFQ Certification Form.docx | DOCX document | |
| Egnyte Upload Instructions.pdf | ||
| Exhibit B _ Certificate of Minority Form.docx | DOCX document | |
| J_460 GSOU School of Optometry PM RFQ_RFP_djh.pdf | ||
| Exhibit C _ Project Team Composition Form.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project No. PM Fee Proposal
| A. | Instituion Name | $13,300,000 | ||||||||||||
| Phase I - Predesign | Phase II - Design & Preconstruction | Phase III - Construction | Total | Fee % | ||||||||||
| Job Title | Name of Proposed Personnel | Rate/Hour | Hours/Week | Duration (Weeks) | Fee | Hours/Week | Duration (Weeks) | Fee | Hours/Week | Duration (Weeks) | Fee | Fee | ||
| Project Director | Joe Jones | $150.00 | 2 | 10 | $3,000.00 | 0 | 22 | $0.00 | 0 | 52 | $0.00 | $3,000.00 | 0.02% | |
| Project Manager | John Smith | $120.00 | 30 | 10 | $36,000.00 | 30 | 22 | $79,200.00 | 10 | 52 | $62,400.00 | $177,600.00 | 1.34% | |
| Asst. Project Manager | Ann White | $120.00 | 20 | 10 | $24,000.00 | 20 | 22 | $52,800.00 | 10 | 52 | $62,400.00 | $139,200.00 | 1.05% | |
| Administrative Assistant | Sam Black | $60.00 | 8 | 10 | $4,800.00 | 8 | 22 | $10,560.00 | 8 | 52 | $24,960.00 | $40,320.00 | 0.30% | |
| Contract Compliance Specialist | Jane Green | $100.00 | 0 | 10 | $0.00 | 4 | 22 | $8,800.00 | 10 | 52 | $52,000.00 | $60,800.00 | 0.46% | |
| Other | None | $0.00 | 0 | 10 | $0.00 | 0 | 22 | $0.00 | 2 | 52 | $0.00 | $0.00 | 0.00% | |
| Other | None | $0.00 | 0 | 10 | $0.00 | 0 | 22 | $0.00 | 3 | 52 | $0.00 | $0.00 | 0.00% | |
| Other | None | $0.00 | 0 | 10 | $0.00 | 0 | 22 | $0.00 | 8 | 52 | $0.00 | $0.00 | 0.00% | |
| Other | None | $0.00 | 0 | 10 | $0.00 | 0 | 22 | $0.00 | 2 | 52 | $0.00 | $0.00 | 0.00% | |
| Other | None | $0.00 | 0 | 10 | $0.00 | 0 | 22 | $0.00 | 3 | 52 | $0.00 | $0.00 | 0.00% | |
| Reimbursable Expenses | $0.00 | 0 | 10 | $2,000.00 | 0 | 22 | $3,000.00 | 0 | 52 | $5,000.00 | $10,000.00 | 0.08% | ||
| $69,800.00 | $154,360.00 | $206,760.00 | $430,920.00 | 3.24% |
&"Arial,Bold"&12J-460 School of Optometry - PROGRAM MANAGEMENT FEE
Sheet 1
Sheet 2
Sheet3
File details come from the government source that posted it. Updated .