Entrada Way Culvert Slip-Out Bank Stabilization Project.pdf
PDF 43 MB Posted
- Solicitation number
- 13311
- Issued by
- San Mateo County, San Francisco City, California
About this file
This document comprises the Contract Documents and Specifications for the Entrada Way Culvert Slip-Out Bank Stabilization Project issued by the County of San Mateo, California Department of Public Works. The project involves stabilization and repair of the left bank failure along La Honda Creek upstream of Entrada Way, spanning approximately 600 feet. Work includes roadway and drainage improvements such as pavement removal, aggregate base compaction, asphalt concrete repaving, guardrail installation and removal, stormwater drainage structure and pipe installation, road embankment rock slope protection, concrete and steel soldier pile retaining wall construction with ground anchors, three engineered log structures with vegetated soil lifts, creek channel realignment of approximately 190 feet, clearing and grubbing, erosion control measures, temporary creek diversion systems, and revegetation and plant maintenance. Sealed bids were due July 23, 2026, at 2:00 p.m., with bid opening and public reading at that time. The contract award was anticipated for August 11, 2026, with Notice to Proceed issued one week thereafter. The contractor must begin work within ten calendar days of Notice to Proceed and complete the work within seventy working days, with an in-water work window restricted to June 15 through October 15. The engineer's estimate totals $2,249,400, comprising 65 line items across multiple divisions including general construction, earthwork and landscape, structures, drainage facilities, and traffic control devices.
The project is federally funded under FEMA-4683-DR-CA with California OES No. 081-00000 and is subject to prevailing wage requirements established by the California Department of Industrial Relations, with federal wage rates applicable where higher than state rates. Contractors and subcontractors must be registered with the Department of Industrial Relations and must not be on the debarred contractor list. A bidder's bond and separate performance and payment bonds, each equaling 100 percent of the contract price, are required. The contract includes mandatory compliance with the Equal Employment Opportunity Program for minority employment, federal non-discrimination requirements, Buy America requirements for steel and iron materials, California Labor Code provisions including certified payroll records submission, and various environmental compliance requirements including erosion control and water quality certifications. Liquidated damages are assessed at $4,800 per calendar day for delays beyond the specified working days, with additional task-specific damages of $500 per day for failure to comply with Best Management Practices or submit required payroll records. The project requires submission of a baseline schedule, construction work plan, and updated schedules throughout the contract period. Contractor must perform at least 50 percent of the original contract work with its own organization, and no subcontract may exceed specified thresholds without proper listing and compliance documentation.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TitleSht.E5103
Last Updated: June 26, 2026 F:\Users\design\C3D\E5103000_Entrada Way Slip-Out Project\12 Design\100% Final P&S\Spec Compilation\FINAL_SMC_Fed Specs_Front End_Section 1-9.docx
COUNTY OF SAN MATEO
STATE OF CALIFORNIA
CONTRACT DOCUMENTS
AND
SPECIFICATIONS
ENTRADA WAY CULVERT SLIP-OUT BANK STABILIZATION PROJECT
TOTAL PROJECT APPROXIMATELY 600 FEET IN LENGTH
WITH APPURTENANT WORK THERETO
IN SAN MATEO COUNTY
COUNTY PROJECT NO. 13311
PROJECT FILE NO. E5103
FEDERAL-AID PROJECT NO. FEMA-4683-DR-CA
CAL OES NO. 081-00000
KRZYSZTOF LISAJ
(R.C.E. No. 84003)
County Engineer
Department of Public Works San Mateo County
555 County Center, 5th Floor
Redwood City, California 94063-1665
APPROVED: June 26 , 2026
This page intentionally left blank
TableCon.E5103 i
TABLE OF CONTENTS
NOTICE TO CONTRACTORS
Bid Opening Date Engineer's Estimate General Bidder's Information
SPECIAL PROVISIONS
Section
1. Definitions
2. Bidding 2-1. Plans and Specifications 2-1.015. Federal Lobbying Restrictions 2-2 In-Use Off-Road Diesel-Fueled Vehicle Fleet Compliance Certification
3. Contract Award and Execution
4. Description of Work
5. Control of Work 5-1. Differing Site Conditions 5-2. Repair of Equipment 5-3. Cooperation 5-4. Permits and Licenses 5-5. Project Appearance 5-6. Preservation of Property 5-7. Air Pollution Control 5-8. Obstructions 5-9. Sound Control 5-10. Public Convenience 5-11. Disposal of Material Outside the Highway Right Of Way 5-12. Sanitary Sewer Monitoring and Reporting Requirements 5-13. Subcontracting
6. Control of Materials 6-1. Certificates of Compliance 6-2. Materials Testing
7. Legal Relations and Responsibility 7-0.10 Federal Forms, Posters and Data Required of Contractor During Construction 7-0.11 Required Listing of Proposed Subcontractors 7-0.12 Labor Nondiscrimination 7-0.13 Prevailing Wage 7-0.14 Buy America Requirements 7-0.15 Removal of Asbestos and Hazardous Substances 7-0.16 Subcontracting 7-0.17 Prompt Progress Payment to Subcontractors ii
TABLE OF CONTENTS (Continued)
SPECIAL PROVISIONS (Continued)
Section 7-0.18 Prompt Payment of Funds Withheld to Subcontractors 7-0.19 Partnering 7-0.20 Procurement of Recovered Materials 7-1. Equal Employment Opportunity Program for Minority Employment 7-1.1. Definitions 7-1.2. Certifications of Compliance and Intent 7-1.3. Equal Employment Opportunity Program 7-1.4. Equal Employment Opportunity Program Evaluation 7-1.5. Inclusion of EEOP and Certificates 7-1.6. Compliance of Contractor 7-1.7. Compliance of Subcontractor 7-1.8. Penalties for Non-Compliance 7-1.9. Waiver of Compliance 7-1.10. Employee Benefits 7-1.11. Non-Discrimination 7-2. Prevailing Wages 7-2.1. Payroll Records 7-2.2. Contractor Employee Jury Service 7-3. Highway Construction Equipment 7-4. Public Safety 7-5. Excavation Safety 7-6 Public Convenience
8. Progress of Work and Time of Completion 8-1. Time of Completion 8-2. Liquidated Damages 8-3. Progress Schedule 8-4. Construction Work Plan
9. Measurement and Payment 9-1. Force Account Work 9-2. Payments to Contractor 9-3. Payments Withheld from Contractor 9-4. Stop Notices 9-5. Construction Claims iii
DIVISION II GENERAL CONSTRUCTION
10. Develop and Apply Water
11. Mobilization
12. Maintaining Traffic
13. Water Pollution Control
14. Construction Waste Management
15. Existing Facilities
DIVISION III GRADING EARTHWORK AND LANDSCAPE
17. Clearing and Grubbing
19. Earthwork
20. Landscape
21. Erosion and Sediment Control
22. Finishing Roadway
DIVISION IV SUBBASES AND BASES
26. Aggregate Base (Class 2)
DIVISION V SURFACINGS AND PAVEMENTS
39. Asphalt Concrete (Type A HMA)
DIVISION VI STRUCTURES
46. Ground Anchors and Soil Nails
49. Piling
51. Concrete Structures
52. Reinforcement
53. Shotcrete
57. Wood and Plastic Lumber Structures
59. Structural Steel Coatings
DIVISION VII DRAINAGE FACILITIES
64. Plastic Pipe
DIVISION VIII MISCELLANEOUS CONSTRUCTION
72. Rock Slope Protection
80. Chain Link Fence
DIVISION IX TRAFFIC CONTROL DEVICES
83. Metal Beam Guard Railing 83-2. Cable Railing iv
DIVISION XI MATERIALS
89. Aggregate
90. Portland Cement Concrete
96. Geosynthetics
98. Wood Materials for Engineered Log Structures
DIVISION XIII COUNTY MISCELLANEOUS
100. Construction Survey and Staking
101. Soldier Pile Retaining Wall
109. Restoration of Paved Surfaces
110. Connector Pipe Screen
Note: Gaps in Section numbering, above, indicate that the Section is either blank or does not apply.
v
FEDERAL REQUIREMENTS for FEDERAL-AID CONSTRUCTION PROJECTS FR-1 Federal Forms, Posters and Data Required of Contractor During Construction FR-2 Federal Wage Rates FR-3 Federal-Aid Construction Projects Forms:
o FHWA-1391 – Federal-Aid Highway Construction Contractor’s Annual EEO Report
FR-4 Required Federal-Aid Contract Language:
o LAPM Exhibit 12-G – includes FHWA Form-1273 o Appendix E, Title VI Assurances in Contracts – US DOT Order
1050.2A
APPENDIX A
County of San Mateo Waste Management Plan Form Waste Management Daily Transport Report
APPENDIX B
Sanitary Sewer Monitoring and Reporting Requirements:
State Water Resources Control Board Order No. WQ 2013-0058-EXEC
APPENDIX C
Sample “Payment Bond” Form Sample “Performance Bond” Form
APPENDIX D
Daily Personnel and Equipment Log
APPENDIX E
Construction Claims:
Public Contract Code Section 9204 and 20104 et seq.
APPENDIX F
County of San Mateo Memo B-33 for Senate Bill 1383 Compost, Mulch, and Renewable Natural Gas Procurement Reporting
APPENDIX G
Quality Assurance Program July, 2025 (QAP) vi
APPENDIX H
Regulatory Environmental Documents
United States Army Corps of Engineers –Nationwide Permit 13 Authorization – File Number SPN-2017-00048 (Pending)
US Fish and Wildlife Service (USFWS) Biological Opinion
National Marine Fisheries Service (NMFS) Biological Opinion
San Francisco Bay Regional Water Quality Control Board – 401 Water Quality Certification CIWQS Place ID No. TBD (Pending)
California Department of Fish and Wildlife – Streambed Alteration Agreement Notification No. EPIMS-SMO-61382-R3 (Pending)
CEQA IS/ND (State Clearinghouse Number 2025120514)
Best Management Practices
County of San Mateo Routine Maintenance Program Manual Table 9-1, 9- 2 and 9-3
San Mateo Countywide Water Pollution Prevention Program Construction Best Management Practices
APPENDIX I
Pre-Construction Handout Packet for Federal-Aid Contracts vii
PROPOSAL
Contractor’s Check-Off List Name and Address of Bidder Contractor Declaration Statement Bid Schedules Bidder's Bond Signature of Bidder Subcontractors San Mateo County Equal Employment Opportunity Program Equal Benefits Compliance Ordinance No. 04026 (Title 2, Chapter 2.84, San Mateo County Ordinance Code) Equal Benefits Compliance Declaration Form Contractor Employee Jury Service Ordinance No. 04269 (Title 2, Chapter 2.85, San Mateo County Ordinance Code) Contractor Employee Jury Service Compliance Declaration Form Non-Collusion Declaration Form Equal Employment Opportunity Certification (Federal Requirement) Public Contract Code Section 10285.1 Statement Public Contract Code Section 10162 Questionnaire Public Contract Section 10232 Statement Non-Collusion Affidavit (Federal Requirement) Certification of Bidder’s Qualifications and Experience In-Use Off-Road Diesel-Fueled Vehicle Fleet Acknowledgement Form Debarment and Suspension Certification (Title 49, Code of Federal Regulations, Part 29) Non-Lobbying Certification for Federal-Aid Contracts Disclosure of Lobbying Activities – Exhibit 10-Q Bidder’s List of Subcontractor (DBE and Non-DBE) – Exhibit 12-B
AGREEMENT
Signature Sheet viii
NC. E5103
NOTICE TO CONTRACTORS
NOTICE IS HEREBY GIVEN, that
Sealed bids will be received either by mail to the office of the County Executive’s
Office, or hand-delivered prior to the bid opening to the County of San Mateo at 500
County Center, 5th Floor, Redwood City, California, 94063 until the hour of
2:00 p.m., Thursday, July 23, 2026 where the bids will be publicly opened and read aloud for the following project in accordance with the specifications therefore and to which special reference is made as follows:
Bids are required for the entire work described herein.
Bidders are advised of the following:
1. Contractor should be placed on a Plan Holders List for bidding. To be placed on the Plan Holders List, the Contractor shall either:
a. Bidder shall register and create an account on the OpenGov website to download all bidding documents, including forms of proposal and contract, directly from https://procurement.opengov.com/portal/smcgov/projects/267320
Project’s OpenGov Reference:
ENTRADA WAY CULVERT SLIP-OUT BANK STABILIZATION PROJECT
Project ID: E5103 https://procurement.opengov.com/portal/smcgov/projects/267320
b. If bidding documents are obtained through a source other than those outlined in 1a above, complete and sign the following Plan Holder’s Affidavit and return to the County by PDF either via email to mclement@smcgov.org, and wng@smcgov.org or by fax at (650) 361-8220. The Contractor is advised that the table should be received by the County no later than three (3) working days prior to the bid opening date.
Plan Holder’s Affidavit
Project Title
ENTRADA WAY CULVERT SLIP-OUT BANK
STABILIZATION PROJECT
Project No. 13311 Project Engineer: Michael Clement
Project Manager: Wency Ng
Bid Open Date and Time: 2:00 p.m., Thursday, July 23, 2026
Company Name:
Mailing Address:
Phone Number:
Fax Number:
E-mail Address:
(Name and Title of Authorized Representative of Bidder)
(Signature of Authorized Representative of Bidder)
2. The Plan Holders List will be posted to the County of San Mateo’s Public
Works website two (2) working days prior to the bid open date.
3. Questions regarding the Contract Documents concerning items such as discrepancies, conflicts, omissions, doubts as to meanings, or regarding scope of bid items shall be referred to the Engineer. Inquiries must be received in writing via email, to mclement@smcgov.org and mailto:rhan@smcgov.org mailto:wng@smcgov.org mailto:alai@smcgov.org wng@smcgov.org, by 5 PM on July 16, 2026. Inquiries will be answered in writing via email response if written clarification is warranted, in the opinion of the Engineer, then inquiries and responses will be posted to the Project’s page on the County of San Mateo’s Public Works website. It will be the Contractor’s sole responsibility to ensure that they receive responses, if any. The County will not be responsible for oral clarifications.
4. It will be the Contractor’s sole responsibility to ensure that they have received addendums, if any, which will be posted to the County of San Mateo’s Public Works website on the same day issued. Said addendums will also be sent to all current plan holders and made available during purchase of Plans and Specifications.
5. Proposals in which the prices obviously are unbalanced may be rejected.
6. The Contractor’s attention is directed to the importance of complying with the provisions of Section 7-0.10, “Federal Forms, Posters and Data Required of Contractor During Construction,” and Appendix G, “Pre- Construction Handout Packet for Federal-Aid Contracts,” of these Special Provisions.
7. Bids which are not received in a sealed envelope by bid opening will be rejected. This includes all envelopes which are secured by metal clasp, twist tie, string or those which do not otherwise preclude unauthorized access. Bidders who deliver their bids in an envelope which is not sealed may be allowed to correct this deficiency provided they do so before time/date specified for opening of bids.
The Department of Public Works website will be updated as needed and can be accessed under the Department’s tab found on the County of San Mateo website (http://publicworks.smcgov.org/publicworks).
mailto:wng@smcgov.org http://www.co.sanmateo.ca.us/
ENGINEER’S ESTIMATE
Item No.
Section No.
Estimated Quantity
Unit of Measure
Item Description
GENERAL CONSTRUCTION
1 10 1 LS Develop and Apply Water
2 11 1 LS Mobilization
3 12 1 LS Maintaining Traffic
4 13 1 LS Water Pollution Control Plan
5 13 1 LS Water Pollution Control
6 13-12 1 LS Temporary Creek Diversion Systems
7 14 1 LS Construction Waste Management
8 14-11 1 LS Treated Wood Waste
9 15-1 1 LS Remove Drainage Facilities
10 15-2 2 EA Adjust Water Valve Box to Grade
11 15-3 5 EA Pothole and Protect Existing Utilities
Engineer’s Estimate – Continued from Previous Page
Item No.
Section No.
Estimated Quantity
Unit of Measure
Item Description
EARTHWORK AND LANDSCAPE
12 17-1 1 LS Clearing and Grubbing
13 17-1 1 LS Tree Removal
14 17-1 10 EA Additional Tree Removal
15 19-1.01 81 CY Roadway Excavation
16 19-1.02 2.3 CY Roadway Backfill
17 19-2 1 LS Pipe Outfall Construction
18 19-2 381 CY Channel Excavation
19 19-2 183 TON Streambed Sediment
20 19-3 40 CY Imported Topsoil
21 19-3 1,404 CY Structure Excavation (ELS)
22 19-3 122 CY Structure Excavation (Soldier Pile Wall)
23 19-3 102 CY Structure Backfill (Soldier Pile Wall)
24 19-3 15 CY Concrete Backfill (Soldier Pile)
25 19-3 9 CY Lean Concrete Backfill (Soldier Pile)
26 19-3 100 TON Import Structure Backfill (ELS)
27 19-11 480 SQ.YD. Vegetated Soil Lifts
28 20-3 0.3 AC Planting
29 20-4 1 LS Weed and Pest Control
Item
No.
Section
No.
Estimated
Quantity
Unit of
Measure
Item
Description
EARTHWORK AND LANDSCAPE
30 20-5 100 CY Wood Mulch
31 21 700 LF Wildlife Exclusion Fence
32 21 800 LF
High Visibility Silt Fence (with Wildlife
Exclusion)
33 21 1 LS Hydroseed
SUBBASES AND BASES
34 26 59 TON Aggregate Base (Class 2)
SURFACINGS AND PAVEMENTS
35 39-1 36 TON Asphalt Concrete (Type A HMA)
36 39-5 30 LF Place Asphalt Concrete Dike
STRUCTURES
37 46 4 EA Ground Anchor (Subhorizontal)
38 49-4 193 LF Steel Soldier Piling (W12x72)
39 49-4 194 LF 24" Drilled Hole
40 49-7 48 LF Drilled Hole and Drive Timber Pile (ELS)
41 49-7 16 LF Additional Drilling and Driving Timber Pile
(ELS)
42 51-1 1 EA Type GO Inlet
43 51-1 1 EA 3’x2’ Drop Inlet
Item
No.
Section
No.
Estimated
Quantity
Unit of
Measure
Item
Description
44 51-1 1 EA 3’x4’ Drain Inlet
45 51-2 2.0 CY Class 3 Concrete
46 53 (F) 19 CY
Structural Shotcrete (Retaining Wall-
Shotcrete Facing)
47 57 (F) 2 MFBM Timber Lagging
48 57 1 EA Engineered Log Structure (ELS) - Type A
49 57 1 EA Engineered Log Structure (ELS) - Type B
50 57 1 EA Engineered Log Structure (ELS) - Type C
Drainage Facilities
51 64 17 LF
12" SDR 17 HDPE Storm Drain Pipe
(within roadway)
52 64 38 LF
24" SDR 9 HPDE Storm Drain Pipe (within roadway)
53 64 22 LF
24" SDR 9 HPDE Storm Drain Pipe
(outside roadway)
Miscellaneous Construction
54 72 6 CY Road Embankment RSP
55 72-2 255 TON Scour Protection Rock
Traffic Control Devices
56 83 122 LF Metal Beam Guard Railing
57 83-2 (F) 80 LF Cable Railing
Item
No.
Section
No.
Estimated
Quantity
Unit of
Measure
Item
Description
Materials
58 86 1.5 CY Road Embankment Gravel Filter Aggregate
59 98 8 EA Timber Piling
60 98 16 EA Type R Key Logs
61 98 17 EA Type L Key Logs
62 98 36 EA Racking Logs
63 98 1 LS Slash Material
County Miscellaneous
64 100 1 LS Construction Staking and Survey
65 110 1 EA Connector Pipe Screen
Engineer's Estimate of Costs: $ 2,249,400
(F) Final Pay Quantities - See Section 9-1.02C, “Final Pay Item Quantities,” of the
Standard Specifications.
(Note: Gaps in section numbering, above, indicate the Section is blank or does not apply.)
The foregoing quantities are approximate only, being given as a basis for the comparison of bids, and the County of San Mateo does not, expressly or by implication, agree that the actual amount of work will correspond herewith, but reserves the right to increase or decrease the amount of any class or portion of the work, or to omit any portion of the work, as may be deemed necessary or expedient by the Engineer.
Payment to the Contractor for materials furnished and work completed shall be made by the County in accordance with Section 9 of the "Special Provisions" portion of these Contract Documents. Pursuant to Section 22300 of the Public Contract Code, Contractor may, upon his request and at Contractor's expense, substitute equivalent securities for any moneys retained from such payment for the fulfillment of the Contract.
Pursuant to Section 1773 of the California Labor Code, prevailing wage rates in the County have been established by the California Department of
Industrial Relations, and copies are available in the office of the Director of Public
Works. Said prevailing wage rates shall be made available to any interested party on request, and the successful Bidder shall post a copy of the wage rates at the job site. The Contractor’s attention is directed to Section 7-1.02K(2), “Wages,” of the Standard Specifications and the Federal Requirements section of these
Special Provisions. More specifically, reference is made to section FR-2, “Federal
Wage Rates (North County)”.
Additionally:
a. When applicable, both Contractor and Subcontractor hereby agree to pay not less than prevailing rates of wages and be responsible for compliance with all the provisions of the California Labor Code, Article 2-
Wages, Chapter 1, Part 7, Division 2, Section 1770 et seq and Section 1810 et seq. A copy of the prevailing wage scale established by the Department of Industrial Relations is on file in the office of the Director of Public Works, and available at www.dir.ca.gov/DLSR or by phone at 415-703-4774.
California Labor Code Section 1776(a) requires each contractor and subcontractor keep accurate payroll records of trades workers on all public works projects and to submit copies of certified payroll records upon request.
b. Pursuant to State Senate Bill SB 854 (Stat. 2014, chapter 28), effective January 1, 2015:
i. No contractor or subcontractor may be listed on a bid proposal for a public works project unless registered with the Department of
Industrial Relations pursuant to Labor Code section 1725.5 [with limited exceptions from this requirement for bid purposes only under
Labor Code section 1771.1(a)].
ii. No contractor or subcontractor may be awarded a contract for public work on a public works project unless registered with the
Department of Industrial Relations pursuant to Labor Code section
1725.5.
iii. This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.
Attention is directed to the Federal minimum wage rate requirements in the
Contract documents for this Project. If there is a difference between the minimum wage rates predetermined by the Secretary of Labor and the general prevailing wage rates determined by the Director of the California Department of Industrial Relations for similar classifications of labor, the Contractor and subcontractors shall pay not less than the higher wage rate. The Department will not accept lower State wage rates not specifically included in the Federal minimum wage determinations. This includes
"helper" (or other classifications based on hours of experience) or any other classification not appearing in the Federal wage determinations. Where Federal wage determinations do not contain the State wage rate determination otherwise available for use by the Contractor and subcontractors, the Contractor and subcontractors shall pay not less than the Federal minimum wage rate, which most closely approximates the duties of the employees in question.
Anyone with knowledge of possible bid rigging, bidder collusion, or other fraudulent activities should use the hotline provided below to report these activities.
Reference is made to Section 2-1.50, Bid Rigging,” of the Standard Specifications, which states: “The U.S. Department of Transportation (DOT) provides a toll-free hotline service to report bid rigging activities. Use the hotline to report bid rigging, bidder collusion, or other fraudulent activities. The hotline number is (800)-424-9071. The service is available 24 hours 7 days a week and is confidential and anonymous. The hotline is part of the DOT’s effort to identify and investigate highway construction contract fraud and abuse and is operated under the direction of the DOT Inspector
General.”
Wage rates for overtime shall be paid at not less than one and one-half (1-1/2) times the above rates. Wage rates for Sundays and holidays shall be paid at not less than two (2) times the above rates.
The holidays upon which such rates shall be paid shall be all holidays recognized in the collective bargaining agreement applicable to the particular craft, classification, or type of worker employed on the Project.
It is the policy of the County that Contractors on public projects employ their workers and craftsmen from the local labor market whenever possible. "Local Labor
Market" is defined as the labor market within the geographical confines of the County of
San Mateo, State of California. Consistent with this policy, the Contractor is requested to employ craftsmen and other workers from the local labor market whenever possible to do so.
Each bidder shall submit with the bid, Certificates of Compliance and Intent on a form provided in the "Proposal" section of these Contract Documents, a certificate that bidder is in compliance with the provisions of Title VII of the Civil Rights Act of 1964, the
California Fair Employment and Housing Act and any other federal, State and local laws and regulations relating to equal employment opportunity. With the execution of said certificates, bidder also agrees that bidder will maintain or develop and implement, during the course of the work concerned, a program of hiring and employment, conducted without regard to race, religion, color, national origin, ancestry, sexual orientation, or sex of the applicants. With this certification, bidder shall submit any and all information that may be required by the County in connection with the particular project.
Each bidder is hereby notified of Section 9204 and Section 20104 et seq. of the
Public Contract Code as those Sections (attached hereto as Appendix E) relate to resolution of construction claims, and to Section 3186 of the Civil Code, as amended
January 1, 1999 with regard to stop notices and public entity’s rights to retain monies in order to provide for that entity’s reasonable cost of litigation. The bidder is further notified that all provisions of Section 9204 and Section 20104 et seq. of the Public
Contract Code and Section 3186 of the Civil Code, as outlined above shall be considered as incorporated into and become an integral part of these specifications.
Questions relating to equal employment should be directed to the San Mateo
County Department of Public Works, Equal Employment Opportunity Program, 555
County Center, 5th Floor, Redwood City, CA 94063-1665, telephone (650) 363-4100.
Additional technical questions should be directed to the office of the Director of
Public Works, 555 County Center, Redwood City, California, 94063-1665, telephone
(650) 363-4100.
The Contractor shall possess either a Class A License or a combination of Class
C licenses that are applicable for the majority of the work at the time this contract is awarded. No Contract will be awarded to a Bidder who is not licensed as required by laws of the State of California.
The County of San Mateo reserves the right to reject any or all bids and/or waive any informalities or irregularities in any bid received.
Bidders may not withdraw their bid for a period of FORTY-FIVE (45) DAYS after the date set from the opening thereof.
BY ORDER OF THE
BOARD OF SUPERVISORS
DATE: June 26, 2026 Michael Callagy, County Executive Officer/ Clerk of the Board of Supervisors
SP.E5103
SPECIAL PROVISIONS
FOR
DATE: June 26, 2026
SECTION 1.
DEFINITIONS OF TERMS TO BE USED IN THE SPECIAL PROVISIONS,
NOTICE TO CONTRACTORS, PROPOSAL, AGREEMENT OR
OTHER CONTRACT DOCUMENTS
Except as specifically stated herein, the definitions contained in the Standard
Specifications of the State of California, Department of Transportation, as set forth per
Section 2-1, “Plans and Specifications,” of these Special Provisions and hereafter referred to as “Standard Specifications,” shall be applicable with the understanding that where said definitions specifically refer to the State of California, a department or division of the State or an official, officer or employee of the State, said definition shall be interpreted to refer to the County of San Mateo, the Department of Public Works, or other appropriate department, division, official, officer or employee of the County of San
Mateo.
Definition 7-1.02L, “Public Contract Code,” of the Standard Specifications shall not be interpreted to include the provisions of Article 7.1 of Division 2, Part 2, Chapter 1 of the Public Contract Code.
END OF SECTION
SECTION 2.
BIDDING
The Bidder’s attention is directed to all the provisions of Section 2, “Bidding,” of the Standard Specifications and these Special Provisions. The County will accept a
Bidder’s Bond in the form issued by an admitted surety insurer in lieu of the sample forms provided herein in Appendix C of these Special Provisions. The County will not be responsible for any oral interpretations to Bidders with respect to any of the work embraced herein.
The contractor, sub-recipient or subcontractor shall not discriminate on the basis of race, color, sex, or national origin in the performance of this contract.
Failure of the bidder to fulfill the requirements of the Special Provisions for submittals required to be furnished after bid opening, including but not limited to escrowed bid documents, where applicable, may subject the bidder to a determination of the bidder's responsibility in the event it is the apparent low bidder on a future public works contracts.
All proposals must be made upon the blank form contained herein.
2-1. Plans and Specifications
Subject to the exceptions stated herein, the work embraced herein shall be done in accordance with the Standard Plans and Specifications as adopted by the County of San Mateo insofar as the same may apply, and in accordance with the following Special Provisions.
As set forth in Resolution No. 077277 of the Board of Supervisors of the
County of San Mateo, adopted February 11, 2020, which approved the 2018
Standard Plans and Standard Specifications, of the State of California, Department of Transportation as the Standard Plans and Standard Specifications of the County of San Mateo, State of California.
In the event that a discrepancy arises between the project Plans, these
Special Provisions, the Standard Plans and the Standard Specifications, the provisions of Section 5-1.02, “Contract Components,” of the Standard
Specifications shall apply.
2-1.015. Federal Lobbying Restrictions
Title 31, Subtitle II, Chapter 13, Subchapter III, Section 1352, of the United
States Code prohibits Federal funds from being expended by the recipient or any lower tier sub-recipient of a Federal-aid contract to pay for any person for influencing or attempting to influence a Federal agency or Congress in connection with the awarding of any Federal-aid contract, the making of any
Federal grant or loan, or the entering into of any cooperative agreement.
If any funds other than Federal funds have been paid for the same purposes in connection with this Federal-aid contract, the recipient shall submit an executed certification and, if required, submit a completed disclosure form as part of the bid documents.
Certification for Federal-aid contracts regarding payment of funds to lobby
Congress or a Federal agency is required. Included in the Proposal is Exhibit 10-
Q (Standard Form LLL), “Disclosure of Lobbying Activities,” with instructions for completing. Signing the Proposal shall constitute both signature of Standard
Form LLL and said Certification.
The above referenced certification and disclosure of lobbying activities shall be included in each subcontract and any lower-tier contracts exceeding
$100,000. All disclosure forms shall be forwarded from tier to tier until received by the Engineer.
The Contractor, subcontractors and any lower-tier contractors shall file a disclosure form at the end of each calendar quarter in which there occurs any event that requires disclosure or that materially affects the accuracy of the information contained in any disclosure form previously filed by the Contractor, subcontractors and any lower-tier contractors. An event that materially affects the accuracy of the information reported includes:
(1) A cumulative increase if $25,000 or more in the amount paid or expected to be paid for influencing or attempting to influence a covered Federal action; or
(2) A change in the person(s) or individual(s) influencing or attempting to influence a covered Federal action; or
(3) A change in the officer(s), employees(s), or Member(s) contacted to influence or attempt to influence a covered Federal Action.
2-2. In-Use Off-Road Diesel-Fueled Vehicle Fleet Compliance Certification
In conformance with Title 13 CCR § 2449 et seq., bidders must submit the
In-Use Off-Road Diesel-Fueled Vehicle List form, list each fleet used by the contractor and the subcontractor to perform work. A copy of a valid Certificate of
Reported Compliance for each fleet listed on the form must be submitted with the bid or within three (3) calendar days of bid opening. Failure to list a fleet used by the contractor or subcontractor to perform work on the In-Use Off-Road
Diesel-Fueled Vehicle List form may result in a nonresponsive bid. Failure to submit the Certificate of Reported Compliance for a fleet listed on the In-Use
Off-Road Diesel-Fueled Vehicle List form may result in a nonresponsive bid.
SECTION 3.
CONTRACT AWARD AND EXECTION
The bidder's attention is directed to the provisions in Section 3, "Contract Award and Execution," of the Standard Specifications and these Special Provisions for the requirements and conditions concerning award and execution of contracts.
However, the following supersedes the second paragraph in Section 3-1.04, “Contract Award,” of the Standard Specifications:
“The award of contract, if awarded, will be made to the lowest responsible bidder within SIXTY (60) DAYS after the opening of the proposals. If the lowest responsible bidder refuses or fails to execute the contract, the County may award the contract to the second lowest responsible bidder. If the second lowest responsible bidder refuses or fails to execute the contract, the County may award the contract to the third responsible bidder. The period of time after that specified above within which the award of the contract may be made shall be subject to extension for such further period as may be agreed upon, in writing, between the County and the bidder concerned.”
Bidders who wish to lodge a protest for consideration as to the bidding process or the award of a contract to the lowest responsible bidder must do so as follows:
(1) Protests based upon alleged improprieties in a solicitation, which are apparent prior to bid opening, shall be filed two (2) business days prior to bid opening.
(2) Protests other than those covered by paragraph 1, above, shall be filed no later than ten (10) calendar days after the bid opening.
(3) All protests shall be delivered to:
Director of Public Works County of San Mateo 555 County Center, 5th Floor Redwood City, CA 94063
Untimely protests, which do not meet the deadline requirements specified above, will not be accepted or considered.
Bid protests must be submitted in writing to the addressee and address listed above. Bid protests must at a minimum include the following:
• Project Name
• Project File Number
• A complete statement describing the basis for the bid protest, which includes a detailed statement of all legal and factual grounds for the protest
• Documentation supporting the protestor's grounds for the protest
• The type of relief requested and the legal basis for such relief
If a valid protest is filed timely, the Department will investigate the bid protest.
The protested bidder shall have three (3) business days to respond to the Department and to provide any information requested by the Department. The Department shall respond to the protesting party, stating its findings. The Department Director shall make a recommendation to the San Mateo County Board of Supervisors regarding the bid protest.
Bid protests are to be delivered to the following address: 555 County
Center, 5th Floor Redwood City, CA 94063.
The award of the contract, if it is awarded, will be to the lowest responsible bidder whose proposal complies with all the requirements prescribed.
The contract shall be executed by the successful bidder and shall be returned, together with the contract bonds, to the County so that it is received within ten (10) days, not including Saturdays, Sundays and legal holidays, after the bidder has received the contract for execution. Failure to do so shall be just cause for forfeiture of the proposal guaranty. The executed contract documents shall be delivered to the following address:
555 County Center, 5th Floor Redwood City, CA 94063.
Paragraph 1 of Section 3-1.02, “Contract Bonds,” of the Standard Specifications is amended to read:
“The Contractor shall provide, at the time of the execution of the Agreement or Contract for work, at his own expense, a surety bond in an amount equal to at least one hundred percent (100%) of the contract price as security for the faithful performance of said agreement. Contractor shall also provide, at the time of the execution of the agreement or contract for work, and at his own expense, a separate surety bond in the amount equal to at least one hundred percent (100%) of the contract price as security for the payment of all persons performing and furnishing materials in connection with said agreement. Sureties on each of said bonds shall be satisfactory to County Counsel.”
“Reference is made to Appendix C of these Special Provisions for a sample of both a “Payment Bond” and “Performance Bond” that have been approved as to form by County Counsel.”
SECTION 4.
DESCRIPTION OF WORK
The work to be done consists, in general, of the stabilization and repair of the left bank failure along La Honda Creek, upstream of Entrada Way. The work will consist of roadway and drainage improvements that involve pavement removal, compacting aggregate base, repaving with asphalt concrete, removal and installation of guardrail, installation of stormwater drainage structures and pipes, and construction of a road embankment rock slope protection. Stabilization of the bank will include the removal and salvage of existing boulders, excavation of the left bank and creek channel, construction of a concrete and steel soldier pile retaining wall with ground anchors, construction of three engineered log structures (ELS) with vegetated soil lifts on the upper slopes of the ELS, and realigning approximately 190 feet of La Honda Creek. The work will also consist of clearing and grubbing, installing erosion control measures and temporary creek diversion systems, revegetation and plant maintenance as well as any other items and details not mentioned above, but required by the Project Plans, Standard Specifications and these Special Provisions, and the directions of the
Engineer.
SECTION 5.
CONTROL OF WORK
Attention is directed to the provisions of Section 5, “Control of Work,” of the
Standard Specifications, except as herein provided, and to Section 2-1, “Plans and
Specifications,” of these Special Provisions.
5-1. Differing Site Conditions
This section shall be used in lieu of Section 4-1.06, “Differing Site
Conditions (23 CFR 635.109),” of the Standard Specifications. Section 4-1.06 of the Standard Specifications shall not apply.
Contractor's Notification
Contractor shall promptly notify the Engineer if either of the following conditions are found:
1. Physical conditions differing materially from either of the following:
• Contract documents
• Job site examination
2. Physical conditions of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in the work provided for in the contract.
Contractor shall include details explaining the information relied on and the material differences discovered.
If Contractor fails to notify the Engineer promptly, the differing site condition claim is waived, for the period between discovery of the differing site condition and notification to the Engineer.
If Contractor disturbs the site after discovery and before the Engineer's investigation, Contractor waives the differing site condition claim.
Engineer's Investigation and Decision
Upon Contractor’s notification, Engineer shall investigate job site conditions and:
1. Notify Contractor whether to resume affected work
2. Decide whether the condition differs materially and is cause for an adjustment of time, payment, or both
Contractor may protest the Engineer's decision.
5-2. Repair of Equipment
The work of installing, assembling, repairing or reconditioning, or other work of any nature on machinery, equipment or tools used in or upon the work shall be considered a part of the work to be performed under the contract and any laborers, workers or mechanics working on the machinery, equipment or tools, unless employed by bona fide commercial repair shops, garages, blacksmith shops or machine shops, which have been established and operating on a commercial basis for a period of at least 2 months prior to the award of the contract, shall be subject to all the requirements relating to labor set forth in these specifications and in the special provisions.
5-3. Cooperation
Attention is directed to Sections 5-1.20, “Coordination with Other Entities,” and 5-1.36, “Property and Facility Preservation,” of the Standard Specifications, and to these Special Provisions. The utility companies may be rearranging their facilities within the project area and it is expected that they will cooperate with the
Contractor to the end that the work may be handled in an efficient manner.
There is an existing AT&T line at the top of slope adjacent to the proposed guardrail location. Contractor shall coordinate with AT&T and County staff in all aspects of construction that may impact any AT&T facility in the location of the project. AT&T is in possession of an open encroachment permit from County
DPW to repair their facilities. Coordination is required between the contractor, AT&T, and County to ensure the AT&T line is repaired prior to paving the street section behind the proposed retaining well. County shall not entertain any delay claim from the contractor for this coordination and/or repair of the AT&T line.
The Contractor shall contact USA North811 (USA) service alert a minimum of forty-eight (48) hours in advance of any excavation or trenching work. USA may be contacted either on-line at usanorth811.org or by phone by dialing (800) 642-2444 or 811.
5-4. Permits and Licenses
Attention is directed to Section 5-1.20B, “Permits, Licenses, Agreements, and Certifications,” of the Standard Specifications and these Special Provisions.
The Contractor shall have at least two employees trained in confined space entry regulations CAL/OSHA Confined Space Regulations, Title 8 CCR
GISO 5156, 5157, and 5158 at the site whenever there are open trenches or underground work going on. It is understood that all fall protection, retrieval and atmospheric monitoring equipment shall be furnished and maintained by the
Contractor at the Contractor’s expense. This shall include but not be limited to cost associated with compliance with Confined Space Entry Regulations shall be at the expense of the Contractor.
Contractor’s attention is directed to Appendix H, “Regulatory
Environmental Documents,” of these Project Specifications.
5-5. Project Appearance
The Contractor shall maintain a neat appearance to the work. Full compensation for conforming to the provisions in this section, not otherwise provided for, shall be considered as included in the unit prices paid for the various Contract items of work involved, and no additional compensation will be allowed therefore.
5-6. Preservation of Property
The Contractor's attention is directed to Section 5-1.36, “Property and
Facility Preservation,” of the Standard Specifications.
5-7. Air Pollution Control
Air pollution control shall conform to the provisions of Section 14-9.02, “Air
Pollution Control,” of the Standard Specifications.
5-8. Obstructions
Attention is directed to the provisions in Sections 5-1.36C, “Nonhighway
Facilities,” 15, “Existing Facilities,” and 51-1.03E(9), “Utility Facilities,” of the
Standard Specifications.
5-9. Sound Control
Sound control shall conform to the provisions in Section 14-8.02, “Noise
Control,” of the Standard Specifications.
5-10. Public Convenience
Public Convenience shall conform to the provisions in Section 7-1.03, “Public Convenience,” of the Standard Specifications and to these Special
5-11. Disposal of Material Outside the Highway Right of Way
Disposal of Material Outside the Highway Right Of Way shall conform to the provisions of Sections 5-1.20B(4), “Contractor-Property Owner Agreement,” and 14-10, “Solid Waste Disposal and Recycling,” of the Standard Specifications, and Section 14, “Construction Waste Management,” of these Special Provisions.
The Contractor’s attention is further directed to Appendix “A”, “Construction
Waste Management Plan,” of these Special Provisions.
5-12. Sanitary Sewer Monitoring and Reporting Requirements
The Contractor’s attention is directed to Appendix B for sanitary sewer monitoring and reporting requirements.
5-13. Subcontracting
Attention is directed to the provisions in Section 7-0.20, “Subcontracting,” of these Special Provisions and Section 5-1.13, "Subcontracting," of the
Standard Specifications.
The Contractors engaged in Federal-aid projects shall physically incorporate provisions contained in Federal Form FHWA-1273 in all subcontracts, lower tier contracts, and purchase orders. Copies of subcontracts shall be available to the Engineer upon written request as stated in Section 8-
1.01, “Subcontracting,” of the Standard Specifications.
5-14. Order of Work
Order of work shall conform to the provisions in Section 5-1.05, “Order of
Work,” of the Standard Specifications and these Special Provisions.
The Contractor’s first order of work shall be to coordinate the acquisition of materials required to complete the project. If guarantees cannot be obtained that will allow the project to be completed within the allowable in-water construction window as specified in Section 8-1 “Time of Completion” of these Special
Provisions, the Contractor shall adhere to the following phasing plan.
If phasing is required to complete the project, the following would be the anticipated construction sequence plan:
Phase 1: June 15, 2026 – October 15, 2026: Removal of existing drainage facilities, construction of roadway and storm drain improvements, including storm drain inlets and outfall into the La Honda Creek south of
Entrada Way. Limited preparations, such as tree trimming, can occur north of Entrada Way in areas where Rights of Entry have been obtained. The project area will be winterized following the conclusion of the Phase 1 work.
Phase 2: June 15, 2027 – October 15, 2027: Construction of the remainder of the project, including the concrete headwall, engineered log structure, and creek regrading north of Entrada Way.
The necessity of a phasing plan shall be determined prior to any work beginning north of Entrada Way. Should the Contractor determine that they are able to construct the project as a single phase, the Contractor shall have no claim for construction delays caused by material or equipment lead times.
SECTION 6.
CONTROL OF MATERIALS
Attention is directed to Section 6, "Control of Materials," of the Standard
Specifications and these Special Provisions.
The Contractor shall furnish all materials required to complete the work under this Contract.
The County uses a Quality Assurance Plan (QAP) to provide assurance that the materials incorporated into construction projects are in conformance with the contract specifications. Contractor may examine records and reports of tests performed by the
County if they are available on the job site. Contractor shall schedule work to allow time for the testing requirements in the QAP.
The Contractor’s attention is directed to Section 7-0.15, “Buy America
Requirements,” of these Special Provisions.
The Contractor shall furnish steel and iron materials to be incorporated into the work that are produced in the United States except:
1. Foreign pig iron and processed, pelletized, and reduced iron ore may be used in the domestic production of the steel and iron materials [60 Fed Reg 15478
(03/24/1995)]
2. If the total combined cost of the materials does not exceed the greater of
0.1 percent of the total bid or $2,500, material produced outside the United States may be used
Production includes:
1. Processing steel and iron materials, including smelting or other processes that alter the physical form or shape (such as rolling, extruding, machining, bending, grinding, and drilling) or chemical composition
2. Coating application, including epoxy coating, galvanizing, and painting, that protects or enhances the value of steel and iron materials
For steel and iron materials to be incorporated into the work, Contactor shall submit a Certificate of Compliance under Section 6-2.03C, "Certificates of Compliance," of the Standard Specifications that certifies all production processes occurred in the
United States except for the above exceptions.
6-1. Certificates of Compliance
Certificates of Compliance, conforming to the provisions in Section 6-
2.03C, “Certificates of Compliance,” of the Standard Specifications shall be furnished for all manufactured products, unless otherwise waived by the
Engineer.
6-2. Materials Testing
Whenever the specifications require compliance with specified values for the following applicable properties, tests will be made as indicated:
Material To Be Tested
Property Being Tested
Acceptable Test Method(s)
Description
Aggregate Base Relative Compaction
CT 216/CT 231
Determines field densities using a nuclear gage.
Concrete Strength CT 521
Determines compressive strength of molded concrete cylinders
Grout Compressive Strength
ASTM C1019
Determines compressive strength of freshly-mixed grout using grout sample box.
Steel Rebar
Tensile Strength & Bend Capability
ASTM A625;
A370
Determines tensile strength and bend capability
Any costs to the County for testing layers which fail the compaction requirements may be deducted from any progress payment due to the Contractor when, in the opinion of the Engineer, such failure results from the Contractor's lack of diligence in pursuing compaction effort. In the event that a test fails, any testing after the first shall be at the Contractor’s expense.
SECTION 7.
LEGAL RELATIONS AND RESPONSIBILITY
Attention is directed to the provisions of Section 7, “Legal Relations and
Responsibility to the Public,” of the Standard Specifications, these Special Provisions, and to the provisions of paragraph VIII, “Insurance,” of the Agreement (AG) portion of the Contract Documents for insurance requirements “Electronic Signature,” of the
Agreement (AG) portions of the Contract Documents.
7-0.10.Federal Forms, Posters and Data Required of Contractor During Construction
The Contractor is advised that there are Federal posters required to be posted at the job site and forms required to be submitted during construction.
Reference is made to the “Federal Requirements for Federal-Aid Construction
Projects” section of these Special Provisions for a listing of the most-commonly required forms. Reference is made to the pre-construction checklist titled
“Federal-Aid Maintenance Contract” (Appendix G, “Pre-Construction Hand-Out
Packet for Federal-Aid Projects”.
The Contractor is further advised that, should Contractor fail to post the required posters at the job site or provide the Federal forms in a timely manner without due cause, as determined by the Engineer, the Engineer shall have the option, at his discretion, to either withhold the progress payment or issue a stop work order until such forms have been submitted to the Engineer.
7-0.11.Required Listing of Proposed Subcontractors
All proposed subcontractors shall be listed by the Contractor in conformance with Section 2-1.10, “Subcontractor List,” of the Standard
Specifications.
Each proposal shall have listed therein the name and address of each subcontractor to whom the bidder proposed to subcontract portions of the work in an amount in excess of one-half of one percent (0.5%) of his total bid or $10,000, whichever is greater, in accordance with the Subletting and Subcontracting Fair
Practices Act, commencing with Section 4100 of the Public Contract Code. The bidder's attention is directed to other provisions of said Act related to the imposition of penalties for a failure to observe its provisions by using unauthorized subcontractors or by making unauthorized substitutions.
A sheet for listing the subcontractors, as required herein, is included in the
Proposal.
7-0.12.Labor Nondiscrimination
The Contractor is advised that the State Standard Specifications shall apply if and where any conflicts between this Section 7-0.13, "Labor
Nondiscrimination," and Section 7-1, "Equal Employment Program for Minority
Employment," of these Special Provisions and the State Standard Specifications exist.
Attention is directed to the following Notice that is required by Chapter 5 of
Division 4 of Title 2, California Code of Regulations:
NOTICE OF REQUIREMENT FOR
NONDISCRIMINATION PROGRAM
(GOV. CODE, SECTION 12990)
Your attention is called to the "Nondiscrimination Clause", set forth in
Section 7-1.02I(2)), "Nondiscrimination," of the Standard Specifications, which is applicable to all non-exempt State contracts and subcontracts, and to the
"Standard California Nondiscrimination Construction Contract Specifications" set forth therein. The Specifications are applicable to all nonexempt State construction contracts and subcontracts of $5,000 or more.
7-0.13.Prevailing Wage
Attention is directed to Section 7-1.02K(2), "Wages," of the Standard
Specifications.
In accordance with the provisions of Section 1770 of the Labor Code, the
Board of Supervisors of the County of San Mateo has ascertained the prevailing rate of wages applicable to the work to be done, which prevailing wage rates have been established as indicated in the Notice to Contractors and are incorporated herein by reference.
7-0.14.Buy America…
This is the start of the file's text. The full file is on GovTribe.