This document comprises the Contract Documents and Specifications for the Entrada Way Culvert Slip-Out Bank Stabilization Project issued by the County of San Mateo, California Department of Public Works. The project involves stabilization and repair of the left bank failure along La Honda Creek upstream of Entrada Way, spanning approximately 600 feet. Work includes roadway and drainage improvements such as pavement removal, aggregate base compaction, asphalt concrete repaving, guardrail installation and removal, stormwater drainage structure and pipe installation, road embankment rock slope protection, concrete and steel soldier pile retaining wall construction with ground anchors, three engineered log structures with vegetated soil lifts, creek channel realignment of approximately 190 feet, clearing and grubbing, erosion control measures, temporary creek diversion systems, and revegetation and plant maintenance. Sealed bids were due July 23, 2026, at 2:00 p.m., with bid opening and public reading at that time. The contract award was anticipated for August 11, 2026, with Notice to Proceed issued one week thereafter. The contractor must begin work within ten calendar days of Notice to Proceed and complete the work within seventy working days, with an in-water work window restricted to June 15 through October 15. The engineer's estimate totals $2,249,400, comprising 65 line items across multiple divisions including general construction, earthwork and landscape, structures, drainage facilities, and traffic control devices.

The project is federally funded under FEMA-4683-DR-CA with California OES No. 081-00000 and is subject to prevailing wage requirements established by the California Department of Industrial Relations, with federal wage rates applicable where higher than state rates. Contractors and subcontractors must be registered with the Department of Industrial Relations and must not be on the debarred contractor list. A bidder's bond and separate performance and payment bonds, each equaling 100 percent of the contract price, are required. The contract includes mandatory compliance with the Equal Employment Opportunity Program for minority employment, federal non-discrimination requirements, Buy America requirements for steel and iron materials, California Labor Code provisions including certified payroll records submission, and various environmental compliance requirements including erosion control and water quality certifications. Liquidated damages are assessed at $4,800 per calendar day for delays beyond the specified working days, with additional task-specific damages of $500 per day for failure to comply with Best Management Practices or submit required payroll records. The project requires submission of a baseline schedule, construction work plan, and updated schedules throughout the contract period. Contractor must perform at least 50 percent of the original contract work with its own organization, and no subcontract may exceed specified thresholds without proper listing and compliance documentation.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TitleSht.E5103

Last Updated: June 26, 2026 F:\Users\design\C3D\E5103000_Entrada Way Slip-Out Project\12 Design\100% Final P&S\Spec Compilation\FINAL_SMC_Fed Specs_Front End_Section 1-9.docx

COUNTY OF SAN MATEO

STATE OF CALIFORNIA

CONTRACT DOCUMENTS

AND

SPECIFICATIONS

ENTRADA WAY CULVERT SLIP-OUT BANK STABILIZATION PROJECT

TOTAL PROJECT APPROXIMATELY 600 FEET IN LENGTH

WITH APPURTENANT WORK THERETO

IN SAN MATEO COUNTY

COUNTY PROJECT NO. 13311

PROJECT FILE NO. E5103

FEDERAL-AID PROJECT NO. FEMA-4683-DR-CA

CAL OES NO. 081-00000

KRZYSZTOF LISAJ

(R.C.E. No. 84003)

County Engineer

Department of Public Works San Mateo County

555 County Center, 5th Floor

Redwood City, California 94063-1665

APPROVED: June 26 , 2026

This page intentionally left blank

TableCon.E5103 i

TABLE OF CONTENTS

NOTICE TO CONTRACTORS

Bid Opening Date Engineer's Estimate General Bidder's Information

SPECIAL PROVISIONS

Section

1. Definitions

2. Bidding 2-1. Plans and Specifications 2-1.015. Federal Lobbying Restrictions 2-2 In-Use Off-Road Diesel-Fueled Vehicle Fleet Compliance Certification

3. Contract Award and Execution

4. Description of Work

5. Control of Work 5-1. Differing Site Conditions 5-2. Repair of Equipment 5-3. Cooperation 5-4. Permits and Licenses 5-5. Project Appearance 5-6. Preservation of Property 5-7. Air Pollution Control 5-8. Obstructions 5-9. Sound Control 5-10. Public Convenience 5-11. Disposal of Material Outside the Highway Right Of Way 5-12. Sanitary Sewer Monitoring and Reporting Requirements 5-13. Subcontracting

6. Control of Materials 6-1. Certificates of Compliance 6-2. Materials Testing

7. Legal Relations and Responsibility 7-0.10 Federal Forms, Posters and Data Required of Contractor During Construction 7-0.11 Required Listing of Proposed Subcontractors 7-0.12 Labor Nondiscrimination 7-0.13 Prevailing Wage 7-0.14 Buy America Requirements 7-0.15 Removal of Asbestos and Hazardous Substances 7-0.16 Subcontracting 7-0.17 Prompt Progress Payment to Subcontractors ii

TABLE OF CONTENTS (Continued)

SPECIAL PROVISIONS (Continued)

Section 7-0.18 Prompt Payment of Funds Withheld to Subcontractors 7-0.19 Partnering 7-0.20 Procurement of Recovered Materials 7-1. Equal Employment Opportunity Program for Minority Employment 7-1.1. Definitions 7-1.2. Certifications of Compliance and Intent 7-1.3. Equal Employment Opportunity Program 7-1.4. Equal Employment Opportunity Program Evaluation 7-1.5. Inclusion of EEOP and Certificates 7-1.6. Compliance of Contractor 7-1.7. Compliance of Subcontractor 7-1.8. Penalties for Non-Compliance 7-1.9. Waiver of Compliance 7-1.10. Employee Benefits 7-1.11. Non-Discrimination 7-2. Prevailing Wages 7-2.1. Payroll Records 7-2.2. Contractor Employee Jury Service 7-3. Highway Construction Equipment 7-4. Public Safety 7-5. Excavation Safety 7-6 Public Convenience

8. Progress of Work and Time of Completion 8-1. Time of Completion 8-2. Liquidated Damages 8-3. Progress Schedule 8-4. Construction Work Plan

9. Measurement and Payment 9-1. Force Account Work 9-2. Payments to Contractor 9-3. Payments Withheld from Contractor 9-4. Stop Notices 9-5. Construction Claims iii

DIVISION II GENERAL CONSTRUCTION

10. Develop and Apply Water

11. Mobilization

12. Maintaining Traffic

13. Water Pollution Control

14. Construction Waste Management

15. Existing Facilities

DIVISION III GRADING EARTHWORK AND LANDSCAPE

17. Clearing and Grubbing

19. Earthwork

20. Landscape

21. Erosion and Sediment Control

22. Finishing Roadway

DIVISION IV SUBBASES AND BASES

26. Aggregate Base (Class 2)

DIVISION V SURFACINGS AND PAVEMENTS

39. Asphalt Concrete (Type A HMA)

DIVISION VI STRUCTURES

46. Ground Anchors and Soil Nails

49. Piling

51. Concrete Structures

52. Reinforcement

53. Shotcrete

57. Wood and Plastic Lumber Structures

59. Structural Steel Coatings

DIVISION VII DRAINAGE FACILITIES

64. Plastic Pipe

DIVISION VIII MISCELLANEOUS CONSTRUCTION

72. Rock Slope Protection

80. Chain Link Fence

DIVISION IX TRAFFIC CONTROL DEVICES

83. Metal Beam Guard Railing 83-2. Cable Railing iv

DIVISION XI MATERIALS

89. Aggregate

90. Portland Cement Concrete

96. Geosynthetics

98. Wood Materials for Engineered Log Structures

DIVISION XIII COUNTY MISCELLANEOUS

100. Construction Survey and Staking

101. Soldier Pile Retaining Wall

109. Restoration of Paved Surfaces

110. Connector Pipe Screen

Note: Gaps in Section numbering, above, indicate that the Section is either blank or does not apply.

v

FEDERAL REQUIREMENTS for FEDERAL-AID CONSTRUCTION PROJECTS FR-1 Federal Forms, Posters and Data Required of Contractor During Construction FR-2 Federal Wage Rates FR-3 Federal-Aid Construction Projects Forms:

o FHWA-1391 – Federal-Aid Highway Construction Contractor’s Annual EEO Report

FR-4 Required Federal-Aid Contract Language:

o LAPM Exhibit 12-G – includes FHWA Form-1273 o Appendix E, Title VI Assurances in Contracts – US DOT Order

1050.2A

APPENDIX A

County of San Mateo Waste Management Plan Form Waste Management Daily Transport Report

APPENDIX B

Sanitary Sewer Monitoring and Reporting Requirements:

State Water Resources Control Board Order No. WQ 2013-0058-EXEC

APPENDIX C

Sample “Payment Bond” Form Sample “Performance Bond” Form

APPENDIX D

Daily Personnel and Equipment Log

APPENDIX E

Construction Claims:

Public Contract Code Section 9204 and 20104 et seq.

APPENDIX F

County of San Mateo Memo B-33 for Senate Bill 1383 Compost, Mulch, and Renewable Natural Gas Procurement Reporting

APPENDIX G

Quality Assurance Program July, 2025 (QAP) vi

APPENDIX H

Regulatory Environmental Documents

United States Army Corps of Engineers –Nationwide Permit 13 Authorization – File Number SPN-2017-00048 (Pending)

US Fish and Wildlife Service (USFWS) Biological Opinion

National Marine Fisheries Service (NMFS) Biological Opinion

San Francisco Bay Regional Water Quality Control Board – 401 Water Quality Certification CIWQS Place ID No. TBD (Pending)

California Department of Fish and Wildlife – Streambed Alteration Agreement Notification No. EPIMS-SMO-61382-R3 (Pending)

CEQA IS/ND (State Clearinghouse Number 2025120514)

Best Management Practices

County of San Mateo Routine Maintenance Program Manual Table 9-1, 9- 2 and 9-3

San Mateo Countywide Water Pollution Prevention Program Construction Best Management Practices

APPENDIX I

Pre-Construction Handout Packet for Federal-Aid Contracts vii

PROPOSAL

Contractor’s Check-Off List Name and Address of Bidder Contractor Declaration Statement Bid Schedules Bidder's Bond Signature of Bidder Subcontractors San Mateo County Equal Employment Opportunity Program Equal Benefits Compliance Ordinance No. 04026 (Title 2, Chapter 2.84, San Mateo County Ordinance Code) Equal Benefits Compliance Declaration Form Contractor Employee Jury Service Ordinance No. 04269 (Title 2, Chapter 2.85, San Mateo County Ordinance Code) Contractor Employee Jury Service Compliance Declaration Form Non-Collusion Declaration Form Equal Employment Opportunity Certification (Federal Requirement) Public Contract Code Section 10285.1 Statement Public Contract Code Section 10162 Questionnaire Public Contract Section 10232 Statement Non-Collusion Affidavit (Federal Requirement) Certification of Bidder’s Qualifications and Experience In-Use Off-Road Diesel-Fueled Vehicle Fleet Acknowledgement Form Debarment and Suspension Certification (Title 49, Code of Federal Regulations, Part 29) Non-Lobbying Certification for Federal-Aid Contracts Disclosure of Lobbying Activities – Exhibit 10-Q Bidder’s List of Subcontractor (DBE and Non-DBE) – Exhibit 12-B

AGREEMENT

Signature Sheet viii

NC. E5103

NOTICE TO CONTRACTORS

NOTICE IS HEREBY GIVEN, that

Sealed bids will be received either by mail to the office of the County Executive’s

Office, or hand-delivered prior to the bid opening to the County of San Mateo at 500

County Center, 5th Floor, Redwood City, California, 94063 until the hour of

2:00 p.m., Thursday, July 23, 2026 where the bids will be publicly opened and read aloud for the following project in accordance with the specifications therefore and to which special reference is made as follows:

Bids are required for the entire work described herein.

Bidders are advised of the following:

1. Contractor should be placed on a Plan Holders List for bidding. To be placed on the Plan Holders List, the Contractor shall either:

a. Bidder shall register and create an account on the OpenGov website to download all bidding documents, including forms of proposal and contract, directly from https://procurement.opengov.com/portal/smcgov/projects/267320

Project’s OpenGov Reference:

ENTRADA WAY CULVERT SLIP-OUT BANK STABILIZATION PROJECT

Project ID: E5103 https://procurement.opengov.com/portal/smcgov/projects/267320

b. If bidding documents are obtained through a source other than those outlined in 1a above, complete and sign the following Plan Holder’s Affidavit and return to the County by PDF either via email to mclement@smcgov.org, and wng@smcgov.org or by fax at (650) 361-8220. The Contractor is advised that the table should be received by the County no later than three (3) working days prior to the bid opening date.

Plan Holder’s Affidavit

Project Title

ENTRADA WAY CULVERT SLIP-OUT BANK

STABILIZATION PROJECT

Project No. 13311 Project Engineer: Michael Clement

Project Manager: Wency Ng

Bid Open Date and Time: 2:00 p.m., Thursday, July 23, 2026

Company Name:

Mailing Address:

Phone Number:

Fax Number:

E-mail Address:

(Name and Title of Authorized Representative of Bidder)

(Signature of Authorized Representative of Bidder)

2. The Plan Holders List will be posted to the County of San Mateo’s Public

Works website two (2) working days prior to the bid open date.

3. Questions regarding the Contract Documents concerning items such as discrepancies, conflicts, omissions, doubts as to meanings, or regarding scope of bid items shall be referred to the Engineer. Inquiries must be received in writing via email, to mclement@smcgov.org and mailto:rhan@smcgov.org mailto:wng@smcgov.org mailto:alai@smcgov.org wng@smcgov.org, by 5 PM on July 16, 2026. Inquiries will be answered in writing via email response if written clarification is warranted, in the opinion of the Engineer, then inquiries and responses will be posted to the Project’s page on the County of San Mateo’s Public Works website. It will be the Contractor’s sole responsibility to ensure that they receive responses, if any. The County will not be responsible for oral clarifications.

4. It will be the Contractor’s sole responsibility to ensure that they have received addendums, if any, which will be posted to the County of San Mateo’s Public Works website on the same day issued. Said addendums will also be sent to all current plan holders and made available during purchase of Plans and Specifications.

5. Proposals in which the prices obviously are unbalanced may be rejected.

6. The Contractor’s attention is directed to the importance of complying with the provisions of Section 7-0.10, “Federal Forms, Posters and Data Required of Contractor During Construction,” and Appendix G, “Pre- Construction Handout Packet for Federal-Aid Contracts,” of these Special Provisions.

7. Bids which are not received in a sealed envelope by bid opening will be rejected. This includes all envelopes which are secured by metal clasp, twist tie, string or those which do not otherwise preclude unauthorized access. Bidders who deliver their bids in an envelope which is not sealed may be allowed to correct this deficiency provided they do so before time/date specified for opening of bids.

The Department of Public Works website will be updated as needed and can be accessed under the Department’s tab found on the County of San Mateo website (http://publicworks.smcgov.org/publicworks).

mailto:wng@smcgov.org http://www.co.sanmateo.ca.us/

ENGINEER’S ESTIMATE

Item No.

Section No.

Estimated Quantity

Unit of Measure

Item Description

GENERAL CONSTRUCTION

1 10 1 LS Develop and Apply Water

2 11 1 LS Mobilization

3 12 1 LS Maintaining Traffic

4 13 1 LS Water Pollution Control Plan

5 13 1 LS Water Pollution Control

6 13-12 1 LS Temporary Creek Diversion Systems

7 14 1 LS Construction Waste Management

8 14-11 1 LS Treated Wood Waste

9 15-1 1 LS Remove Drainage Facilities

10 15-2 2 EA Adjust Water Valve Box to Grade

11 15-3 5 EA Pothole and Protect Existing Utilities

Engineer’s Estimate – Continued from Previous Page

Item No.

Section No.

Estimated Quantity

Unit of Measure

Item Description

EARTHWORK AND LANDSCAPE

12 17-1 1 LS Clearing and Grubbing

13 17-1 1 LS Tree Removal

14 17-1 10 EA Additional Tree Removal

15 19-1.01 81 CY Roadway Excavation

16 19-1.02 2.3 CY Roadway Backfill

17 19-2 1 LS Pipe Outfall Construction

18 19-2 381 CY Channel Excavation

19 19-2 183 TON Streambed Sediment

20 19-3 40 CY Imported Topsoil

21 19-3 1,404 CY Structure Excavation (ELS)

22 19-3 122 CY Structure Excavation (Soldier Pile Wall)

23 19-3 102 CY Structure Backfill (Soldier Pile Wall)

24 19-3 15 CY Concrete Backfill (Soldier Pile)

25 19-3 9 CY Lean Concrete Backfill (Soldier Pile)

26 19-3 100 TON Import Structure Backfill (ELS)

27 19-11 480 SQ.YD. Vegetated Soil Lifts

28 20-3 0.3 AC Planting

29 20-4 1 LS Weed and Pest Control

Item

No.

Section

No.

Estimated

Quantity

Unit of

Measure

Item

Description

EARTHWORK AND LANDSCAPE

30 20-5 100 CY Wood Mulch

31 21 700 LF Wildlife Exclusion Fence

32 21 800 LF

High Visibility Silt Fence (with Wildlife

Exclusion)

33 21 1 LS Hydroseed

SUBBASES AND BASES

34 26 59 TON Aggregate Base (Class 2)

SURFACINGS AND PAVEMENTS

35 39-1 36 TON Asphalt Concrete (Type A HMA)

36 39-5 30 LF Place Asphalt Concrete Dike

STRUCTURES

37 46 4 EA Ground Anchor (Subhorizontal)

38 49-4 193 LF Steel Soldier Piling (W12x72)

39 49-4 194 LF 24" Drilled Hole

40 49-7 48 LF Drilled Hole and Drive Timber Pile (ELS)

41 49-7 16 LF Additional Drilling and Driving Timber Pile

(ELS)

42 51-1 1 EA Type GO Inlet

43 51-1 1 EA 3’x2’ Drop Inlet

Item

No.

Section

No.

Estimated

Quantity

Unit of

Measure

Item

Description

44 51-1 1 EA 3’x4’ Drain Inlet

45 51-2 2.0 CY Class 3 Concrete

46 53 (F) 19 CY

Structural Shotcrete (Retaining Wall-

Shotcrete Facing)

47 57 (F) 2 MFBM Timber Lagging

48 57 1 EA Engineered Log Structure (ELS) - Type A

49 57 1 EA Engineered Log Structure (ELS) - Type B

50 57 1 EA Engineered Log Structure (ELS) - Type C

Drainage Facilities

51 64 17 LF

12" SDR 17 HDPE Storm Drain Pipe

(within roadway)

52 64 38 LF

24" SDR 9 HPDE Storm Drain Pipe (within roadway)

53 64 22 LF

24" SDR 9 HPDE Storm Drain Pipe

(outside roadway)

Miscellaneous Construction

54 72 6 CY Road Embankment RSP

55 72-2 255 TON Scour Protection Rock

Traffic Control Devices

56 83 122 LF Metal Beam Guard Railing

57 83-2 (F) 80 LF Cable Railing

Item

No.

Section

No.

Estimated

Quantity

Unit of

Measure

Item

Description

Materials

58 86 1.5 CY Road Embankment Gravel Filter Aggregate

59 98 8 EA Timber Piling

60 98 16 EA Type R Key Logs

61 98 17 EA Type L Key Logs

62 98 36 EA Racking Logs

63 98 1 LS Slash Material

County Miscellaneous

64 100 1 LS Construction Staking and Survey

65 110 1 EA Connector Pipe Screen

Engineer's Estimate of Costs: $ 2,249,400

(F) Final Pay Quantities - See Section 9-1.02C, “Final Pay Item Quantities,” of the

Standard Specifications.

(Note: Gaps in section numbering, above, indicate the Section is blank or does not apply.)

The foregoing quantities are approximate only, being given as a basis for the comparison of bids, and the County of San Mateo does not, expressly or by implication, agree that the actual amount of work will correspond herewith, but reserves the right to increase or decrease the amount of any class or portion of the work, or to omit any portion of the work, as may be deemed necessary or expedient by the Engineer.

Payment to the Contractor for materials furnished and work completed shall be made by the County in accordance with Section 9 of the "Special Provisions" portion of these Contract Documents. Pursuant to Section 22300 of the Public Contract Code, Contractor may, upon his request and at Contractor's expense, substitute equivalent securities for any moneys retained from such payment for the fulfillment of the Contract.

Pursuant to Section 1773 of the California Labor Code, prevailing wage rates in the County have been established by the California Department of

Industrial Relations, and copies are available in the office of the Director of Public

Works. Said prevailing wage rates shall be made available to any interested party on request, and the successful Bidder shall post a copy of the wage rates at the job site. The Contractor’s attention is directed to Section 7-1.02K(2), “Wages,” of the Standard Specifications and the Federal Requirements section of these

Special Provisions. More specifically, reference is made to section FR-2, “Federal

Wage Rates (North County)”.

Additionally:

a. When applicable, both Contractor and Subcontractor hereby agree to pay not less than prevailing rates of wages and be responsible for compliance with all the provisions of the California Labor Code, Article 2-

Wages, Chapter 1, Part 7, Division 2, Section 1770 et seq and Section 1810 et seq. A copy of the prevailing wage scale established by the Department of Industrial Relations is on file in the office of the Director of Public Works, and available at www.dir.ca.gov/DLSR or by phone at 415-703-4774.

California Labor Code Section 1776(a) requires each contractor and subcontractor keep accurate payroll records of trades workers on all public works projects and to submit copies of certified payroll records upon request.

b. Pursuant to State Senate Bill SB 854 (Stat. 2014, chapter 28), effective January 1, 2015:

i. No contractor or subcontractor may be listed on a bid proposal for a public works project unless registered with the Department of

Industrial Relations pursuant to Labor Code section 1725.5 [with limited exceptions from this requirement for bid purposes only under

Labor Code section 1771.1(a)].

ii. No contractor or subcontractor may be awarded a contract for public work on a public works project unless registered with the

Department of Industrial Relations pursuant to Labor Code section

1725.5.

iii. This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.

Attention is directed to the Federal minimum wage rate requirements in the

Contract documents for this Project. If there is a difference between the minimum wage rates predetermined by the Secretary of Labor and the general prevailing wage rates determined by the Director of the California Department of Industrial Relations for similar classifications of labor, the Contractor and subcontractors shall pay not less than the higher wage rate. The Department will not accept lower State wage rates not specifically included in the Federal minimum wage determinations. This includes

"helper" (or other classifications based on hours of experience) or any other classification not appearing in the Federal wage determinations. Where Federal wage determinations do not contain the State wage rate determination otherwise available for use by the Contractor and subcontractors, the Contractor and subcontractors shall pay not less than the Federal minimum wage rate, which most closely approximates the duties of the employees in question.

Anyone with knowledge of possible bid rigging, bidder collusion, or other fraudulent activities should use the hotline provided below to report these activities.

Reference is made to Section 2-1.50, Bid Rigging,” of the Standard Specifications, which states: “The U.S. Department of Transportation (DOT) provides a toll-free hotline service to report bid rigging activities. Use the hotline to report bid rigging, bidder collusion, or other fraudulent activities. The hotline number is (800)-424-9071. The service is available 24 hours 7 days a week and is confidential and anonymous. The hotline is part of the DOT’s effort to identify and investigate highway construction contract fraud and abuse and is operated under the direction of the DOT Inspector

General.”

Wage rates for overtime shall be paid at not less than one and one-half (1-1/2) times the above rates. Wage rates for Sundays and holidays shall be paid at not less than two (2) times the above rates.

The holidays upon which such rates shall be paid shall be all holidays recognized in the collective bargaining agreement applicable to the particular craft, classification, or type of worker employed on the Project.

It is the policy of the County that Contractors on public projects employ their workers and craftsmen from the local labor market whenever possible. "Local Labor

Market" is defined as the labor market within the geographical confines of the County of

San Mateo, State of California. Consistent with this policy, the Contractor is requested to employ craftsmen and other workers from the local labor market whenever possible to do so.

Each bidder shall submit with the bid, Certificates of Compliance and Intent on a form provided in the "Proposal" section of these Contract Documents, a certificate that bidder is in compliance with the provisions of Title VII of the Civil Rights Act of 1964, the

California Fair Employment and Housing Act and any other federal, State and local laws and regulations relating to equal employment opportunity. With the execution of said certificates, bidder also agrees that bidder will maintain or develop and implement, during the course of the work concerned, a program of hiring and employment, conducted without regard to race, religion, color, national origin, ancestry, sexual orientation, or sex of the applicants. With this certification, bidder shall submit any and all information that may be required by the County in connection with the particular project.

Each bidder is hereby notified of Section 9204 and Section 20104 et seq. of the

Public Contract Code as those Sections (attached hereto as Appendix E) relate to resolution of construction claims, and to Section 3186 of the Civil Code, as amended

January 1, 1999 with regard to stop notices and public entity’s rights to retain monies in order to provide for that entity’s reasonable cost of litigation. The bidder is further notified that all provisions of Section 9204 and Section 20104 et seq. of the Public

Contract Code and Section 3186 of the Civil Code, as outlined above shall be considered as incorporated into and become an integral part of these specifications.

Questions relating to equal employment should be directed to the San Mateo

County Department of Public Works, Equal Employment Opportunity Program, 555

County Center, 5th Floor, Redwood City, CA 94063-1665, telephone (650) 363-4100.

Additional technical questions should be directed to the office of the Director of

Public Works, 555 County Center, Redwood City, California, 94063-1665, telephone

(650) 363-4100.

The Contractor shall possess either a Class A License or a combination of Class

C licenses that are applicable for the majority of the work at the time this contract is awarded. No Contract will be awarded to a Bidder who is not licensed as required by laws of the State of California.

The County of San Mateo reserves the right to reject any or all bids and/or waive any informalities or irregularities in any bid received.

Bidders may not withdraw their bid for a period of FORTY-FIVE (45) DAYS after the date set from the opening thereof.

BY ORDER OF THE

BOARD OF SUPERVISORS

DATE: June 26, 2026 Michael Callagy, County Executive Officer/ Clerk of the Board of Supervisors

SP.E5103

SPECIAL PROVISIONS

FOR

DATE: June 26, 2026

SECTION 1.

DEFINITIONS OF TERMS TO BE USED IN THE SPECIAL PROVISIONS,

NOTICE TO CONTRACTORS, PROPOSAL, AGREEMENT OR

OTHER CONTRACT DOCUMENTS

Except as specifically stated herein, the definitions contained in the Standard

Specifications of the State of California, Department of Transportation, as set forth per

Section 2-1, “Plans and Specifications,” of these Special Provisions and hereafter referred to as “Standard Specifications,” shall be applicable with the understanding that where said definitions specifically refer to the State of California, a department or division of the State or an official, officer or employee of the State, said definition shall be interpreted to refer to the County of San Mateo, the Department of Public Works, or other appropriate department, division, official, officer or employee of the County of San

Mateo.

Definition 7-1.02L, “Public Contract Code,” of the Standard Specifications shall not be interpreted to include the provisions of Article 7.1 of Division 2, Part 2, Chapter 1 of the Public Contract Code.

END OF SECTION

SECTION 2.

BIDDING

The Bidder’s attention is directed to all the provisions of Section 2, “Bidding,” of the Standard Specifications and these Special Provisions. The County will accept a

Bidder’s Bond in the form issued by an admitted surety insurer in lieu of the sample forms provided herein in Appendix C of these Special Provisions. The County will not be responsible for any oral interpretations to Bidders with respect to any of the work embraced herein.

The contractor, sub-recipient or subcontractor shall not discriminate on the basis of race, color, sex, or national origin in the performance of this contract.

Failure of the bidder to fulfill the requirements of the Special Provisions for submittals required to be furnished after bid opening, including but not limited to escrowed bid documents, where applicable, may subject the bidder to a determination of the bidder's responsibility in the event it is the apparent low bidder on a future public works contracts.

All proposals must be made upon the blank form contained herein.

2-1. Plans and Specifications

Subject to the exceptions stated herein, the work embraced herein shall be done in accordance with the Standard Plans and Specifications as adopted by the County of San Mateo insofar as the same may apply, and in accordance with the following Special Provisions.

As set forth in Resolution No. 077277 of the Board of Supervisors of the

County of San Mateo, adopted February 11, 2020, which approved the 2018

Standard Plans and Standard Specifications, of the State of California, Department of Transportation as the Standard Plans and Standard Specifications of the County of San Mateo, State of California.

In the event that a discrepancy arises between the project Plans, these

Special Provisions, the Standard Plans and the Standard Specifications, the provisions of Section 5-1.02, “Contract Components,” of the Standard

Specifications shall apply.

2-1.015. Federal Lobbying Restrictions

Title 31, Subtitle II, Chapter 13, Subchapter III, Section 1352, of the United

States Code prohibits Federal funds from being expended by the recipient or any lower tier sub-recipient of a Federal-aid contract to pay for any person for influencing or attempting to influence a Federal agency or Congress in connection with the awarding of any Federal-aid contract, the making of any

Federal grant or loan, or the entering into of any cooperative agreement.

If any funds other than Federal funds have been paid for the same purposes in connection with this Federal-aid contract, the recipient shall submit an executed certification and, if required, submit a completed disclosure form as part of the bid documents.

Certification for Federal-aid contracts regarding payment of funds to lobby

Congress or a Federal agency is required. Included in the Proposal is Exhibit 10-

Q (Standard Form LLL), “Disclosure of Lobbying Activities,” with instructions for completing. Signing the Proposal shall constitute both signature of Standard

Form LLL and said Certification.

The above referenced certification and disclosure of lobbying activities shall be included in each subcontract and any lower-tier contracts exceeding

$100,000. All disclosure forms shall be forwarded from tier to tier until received by the Engineer.

The Contractor, subcontractors and any lower-tier contractors shall file a disclosure form at the end of each calendar quarter in which there occurs any event that requires disclosure or that materially affects the accuracy of the information contained in any disclosure form previously filed by the Contractor, subcontractors and any lower-tier contractors. An event that materially affects the accuracy of the information reported includes:

(1) A cumulative increase if $25,000 or more in the amount paid or expected to be paid for influencing or attempting to influence a covered Federal action; or

(2) A change in the person(s) or individual(s) influencing or attempting to influence a covered Federal action; or

(3) A change in the officer(s), employees(s), or Member(s) contacted to influence or attempt to influence a covered Federal Action.

2-2. In-Use Off-Road Diesel-Fueled Vehicle Fleet Compliance Certification

In conformance with Title 13 CCR § 2449 et seq., bidders must submit the

In-Use Off-Road Diesel-Fueled Vehicle List form, list each fleet used by the contractor and the subcontractor to perform work. A copy of a valid Certificate of

Reported Compliance for each fleet listed on the form must be submitted with the bid or within three (3) calendar days of bid opening. Failure to list a fleet used by the contractor or subcontractor to perform work on the In-Use Off-Road

Diesel-Fueled Vehicle List form may result in a nonresponsive bid. Failure to submit the Certificate of Reported Compliance for a fleet listed on the In-Use

Off-Road Diesel-Fueled Vehicle List form may result in a nonresponsive bid.

SECTION 3.

CONTRACT AWARD AND EXECTION

The bidder's attention is directed to the provisions in Section 3, "Contract Award and Execution," of the Standard Specifications and these Special Provisions for the requirements and conditions concerning award and execution of contracts.

However, the following supersedes the second paragraph in Section 3-1.04, “Contract Award,” of the Standard Specifications:

“The award of contract, if awarded, will be made to the lowest responsible bidder within SIXTY (60) DAYS after the opening of the proposals. If the lowest responsible bidder refuses or fails to execute the contract, the County may award the contract to the second lowest responsible bidder. If the second lowest responsible bidder refuses or fails to execute the contract, the County may award the contract to the third responsible bidder. The period of time after that specified above within which the award of the contract may be made shall be subject to extension for such further period as may be agreed upon, in writing, between the County and the bidder concerned.”

Bidders who wish to lodge a protest for consideration as to the bidding process or the award of a contract to the lowest responsible bidder must do so as follows:

(1) Protests based upon alleged improprieties in a solicitation, which are apparent prior to bid opening, shall be filed two (2) business days prior to bid opening.

(2) Protests other than those covered by paragraph 1, above, shall be filed no later than ten (10) calendar days after the bid opening.

(3) All protests shall be delivered to:

Director of Public Works County of San Mateo 555 County Center, 5th Floor Redwood City, CA 94063

Untimely protests, which do not meet the deadline requirements specified above, will not be accepted or considered.

Bid protests must be submitted in writing to the addressee and address listed above. Bid protests must at a minimum include the following:

• Project Name

• Project File Number

• A complete statement describing the basis for the bid protest, which includes a detailed statement of all legal and factual grounds for the protest

• Documentation supporting the protestor's grounds for the protest

• The type of relief requested and the legal basis for such relief

If a valid protest is filed timely, the Department will investigate the bid protest.

The protested bidder shall have three (3) business days to respond to the Department and to provide any information requested by the Department. The Department shall respond to the protesting party, stating its findings. The Department Director shall make a recommendation to the San Mateo County Board of Supervisors regarding the bid protest.

Bid protests are to be delivered to the following address: 555 County

Center, 5th Floor Redwood City, CA 94063.

The award of the contract, if it is awarded, will be to the lowest responsible bidder whose proposal complies with all the requirements prescribed.

The contract shall be executed by the successful bidder and shall be returned, together with the contract bonds, to the County so that it is received within ten (10) days, not including Saturdays, Sundays and legal holidays, after the bidder has received the contract for execution. Failure to do so shall be just cause for forfeiture of the proposal guaranty. The executed contract documents shall be delivered to the following address:

555 County Center, 5th Floor Redwood City, CA 94063.

Paragraph 1 of Section 3-1.02, “Contract Bonds,” of the Standard Specifications is amended to read:

“The Contractor shall provide, at the time of the execution of the Agreement or Contract for work, at his own expense, a surety bond in an amount equal to at least one hundred percent (100%) of the contract price as security for the faithful performance of said agreement. Contractor shall also provide, at the time of the execution of the agreement or contract for work, and at his own expense, a separate surety bond in the amount equal to at least one hundred percent (100%) of the contract price as security for the payment of all persons performing and furnishing materials in connection with said agreement. Sureties on each of said bonds shall be satisfactory to County Counsel.”

“Reference is made to Appendix C of these Special Provisions for a sample of both a “Payment Bond” and “Performance Bond” that have been approved as to form by County Counsel.”

SECTION 4.

DESCRIPTION OF WORK

The work to be done consists, in general, of the stabilization and repair of the left bank failure along La Honda Creek, upstream of Entrada Way. The work will consist of roadway and drainage improvements that involve pavement removal, compacting aggregate base, repaving with asphalt concrete, removal and installation of guardrail, installation of stormwater drainage structures and pipes, and construction of a road embankment rock slope protection. Stabilization of the bank will include the removal and salvage of existing boulders, excavation of the left bank and creek channel, construction of a concrete and steel soldier pile retaining wall with ground anchors, construction of three engineered log structures (ELS) with vegetated soil lifts on the upper slopes of the ELS, and realigning approximately 190 feet of La Honda Creek. The work will also consist of clearing and grubbing, installing erosion control measures and temporary creek diversion systems, revegetation and plant maintenance as well as any other items and details not mentioned above, but required by the Project Plans, Standard Specifications and these Special Provisions, and the directions of the

Engineer.

SECTION 5.

CONTROL OF WORK

Attention is directed to the provisions of Section 5, “Control of Work,” of the

Standard Specifications, except as herein provided, and to Section 2-1, “Plans and

Specifications,” of these Special Provisions.

5-1. Differing Site Conditions

This section shall be used in lieu of Section 4-1.06, “Differing Site

Conditions (23 CFR 635.109),” of the Standard Specifications. Section 4-1.06 of the Standard Specifications shall not apply.

Contractor's Notification

Contractor shall promptly notify the Engineer if either of the following conditions are found:

1. Physical conditions differing materially from either of the following:

• Contract documents

• Job site examination

2. Physical conditions of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in the work provided for in the contract.

Contractor shall include details explaining the information relied on and the material differences discovered.

If Contractor fails to notify the Engineer promptly, the differing site condition claim is waived, for the period between discovery of the differing site condition and notification to the Engineer.

If Contractor disturbs the site after discovery and before the Engineer's investigation, Contractor waives the differing site condition claim.

Engineer's Investigation and Decision

Upon Contractor’s notification, Engineer shall investigate job site conditions and:

1. Notify Contractor whether to resume affected work

2. Decide whether the condition differs materially and is cause for an adjustment of time, payment, or both

Contractor may protest the Engineer's decision.

5-2. Repair of Equipment

The work of installing, assembling, repairing or reconditioning, or other work of any nature on machinery, equipment or tools used in or upon the work shall be considered a part of the work to be performed under the contract and any laborers, workers or mechanics working on the machinery, equipment or tools, unless employed by bona fide commercial repair shops, garages, blacksmith shops or machine shops, which have been established and operating on a commercial basis for a period of at least 2 months prior to the award of the contract, shall be subject to all the requirements relating to labor set forth in these specifications and in the special provisions.

5-3. Cooperation

Attention is directed to Sections 5-1.20, “Coordination with Other Entities,” and 5-1.36, “Property and Facility Preservation,” of the Standard Specifications, and to these Special Provisions. The utility companies may be rearranging their facilities within the project area and it is expected that they will cooperate with the

Contractor to the end that the work may be handled in an efficient manner.

There is an existing AT&T line at the top of slope adjacent to the proposed guardrail location. Contractor shall coordinate with AT&T and County staff in all aspects of construction that may impact any AT&T facility in the location of the project. AT&T is in possession of an open encroachment permit from County

DPW to repair their facilities. Coordination is required between the contractor, AT&T, and County to ensure the AT&T line is repaired prior to paving the street section behind the proposed retaining well. County shall not entertain any delay claim from the contractor for this coordination and/or repair of the AT&T line.

The Contractor shall contact USA North811 (USA) service alert a minimum of forty-eight (48) hours in advance of any excavation or trenching work. USA may be contacted either on-line at usanorth811.org or by phone by dialing (800) 642-2444 or 811.

5-4. Permits and Licenses

Attention is directed to Section 5-1.20B, “Permits, Licenses, Agreements, and Certifications,” of the Standard Specifications and these Special Provisions.

The Contractor shall have at least two employees trained in confined space entry regulations CAL/OSHA Confined Space Regulations, Title 8 CCR

GISO 5156, 5157, and 5158 at the site whenever there are open trenches or underground work going on. It is understood that all fall protection, retrieval and atmospheric monitoring equipment shall be furnished and maintained by the

Contractor at the Contractor’s expense. This shall include but not be limited to cost associated with compliance with Confined Space Entry Regulations shall be at the expense of the Contractor.

Contractor’s attention is directed to Appendix H, “Regulatory

Environmental Documents,” of these Project Specifications.

5-5. Project Appearance

The Contractor shall maintain a neat appearance to the work. Full compensation for conforming to the provisions in this section, not otherwise provided for, shall be considered as included in the unit prices paid for the various Contract items of work involved, and no additional compensation will be allowed therefore.

5-6. Preservation of Property

The Contractor's attention is directed to Section 5-1.36, “Property and

Facility Preservation,” of the Standard Specifications.

5-7. Air Pollution Control

Air pollution control shall conform to the provisions of Section 14-9.02, “Air

Pollution Control,” of the Standard Specifications.

5-8. Obstructions

Attention is directed to the provisions in Sections 5-1.36C, “Nonhighway

Facilities,” 15, “Existing Facilities,” and 51-1.03E(9), “Utility Facilities,” of the

Standard Specifications.

5-9. Sound Control

Sound control shall conform to the provisions in Section 14-8.02, “Noise

Control,” of the Standard Specifications.

5-10. Public Convenience

Public Convenience shall conform to the provisions in Section 7-1.03, “Public Convenience,” of the Standard Specifications and to these Special

5-11. Disposal of Material Outside the Highway Right of Way

Disposal of Material Outside the Highway Right Of Way shall conform to the provisions of Sections 5-1.20B(4), “Contractor-Property Owner Agreement,” and 14-10, “Solid Waste Disposal and Recycling,” of the Standard Specifications, and Section 14, “Construction Waste Management,” of these Special Provisions.

The Contractor’s attention is further directed to Appendix “A”, “Construction

Waste Management Plan,” of these Special Provisions.

5-12. Sanitary Sewer Monitoring and Reporting Requirements

The Contractor’s attention is directed to Appendix B for sanitary sewer monitoring and reporting requirements.

5-13. Subcontracting

Attention is directed to the provisions in Section 7-0.20, “Subcontracting,” of these Special Provisions and Section 5-1.13, "Subcontracting," of the

Standard Specifications.

The Contractors engaged in Federal-aid projects shall physically incorporate provisions contained in Federal Form FHWA-1273 in all subcontracts, lower tier contracts, and purchase orders. Copies of subcontracts shall be available to the Engineer upon written request as stated in Section 8-

1.01, “Subcontracting,” of the Standard Specifications.

5-14. Order of Work

Order of work shall conform to the provisions in Section 5-1.05, “Order of

Work,” of the Standard Specifications and these Special Provisions.

The Contractor’s first order of work shall be to coordinate the acquisition of materials required to complete the project. If guarantees cannot be obtained that will allow the project to be completed within the allowable in-water construction window as specified in Section 8-1 “Time of Completion” of these Special

Provisions, the Contractor shall adhere to the following phasing plan.

If phasing is required to complete the project, the following would be the anticipated construction sequence plan:

Phase 1: June 15, 2026 – October 15, 2026: Removal of existing drainage facilities, construction of roadway and storm drain improvements, including storm drain inlets and outfall into the La Honda Creek south of

Entrada Way. Limited preparations, such as tree trimming, can occur north of Entrada Way in areas where Rights of Entry have been obtained. The project area will be winterized following the conclusion of the Phase 1 work.

Phase 2: June 15, 2027 – October 15, 2027: Construction of the remainder of the project, including the concrete headwall, engineered log structure, and creek regrading north of Entrada Way.

The necessity of a phasing plan shall be determined prior to any work beginning north of Entrada Way. Should the Contractor determine that they are able to construct the project as a single phase, the Contractor shall have no claim for construction delays caused by material or equipment lead times.

SECTION 6.

CONTROL OF MATERIALS

Attention is directed to Section 6, "Control of Materials," of the Standard

Specifications and these Special Provisions.

The Contractor shall furnish all materials required to complete the work under this Contract.

The County uses a Quality Assurance Plan (QAP) to provide assurance that the materials incorporated into construction projects are in conformance with the contract specifications. Contractor may examine records and reports of tests performed by the

County if they are available on the job site. Contractor shall schedule work to allow time for the testing requirements in the QAP.

The Contractor’s attention is directed to Section 7-0.15, “Buy America

Requirements,” of these Special Provisions.

The Contractor shall furnish steel and iron materials to be incorporated into the work that are produced in the United States except:

1. Foreign pig iron and processed, pelletized, and reduced iron ore may be used in the domestic production of the steel and iron materials [60 Fed Reg 15478

(03/24/1995)]

2. If the total combined cost of the materials does not exceed the greater of

0.1 percent of the total bid or $2,500, material produced outside the United States may be used

Production includes:

1. Processing steel and iron materials, including smelting or other processes that alter the physical form or shape (such as rolling, extruding, machining, bending, grinding, and drilling) or chemical composition

2. Coating application, including epoxy coating, galvanizing, and painting, that protects or enhances the value of steel and iron materials

For steel and iron materials to be incorporated into the work, Contactor shall submit a Certificate of Compliance under Section 6-2.03C, "Certificates of Compliance," of the Standard Specifications that certifies all production processes occurred in the

United States except for the above exceptions.

6-1. Certificates of Compliance

Certificates of Compliance, conforming to the provisions in Section 6-

2.03C, “Certificates of Compliance,” of the Standard Specifications shall be furnished for all manufactured products, unless otherwise waived by the

Engineer.

6-2. Materials Testing

Whenever the specifications require compliance with specified values for the following applicable properties, tests will be made as indicated:

Material To Be Tested

Property Being Tested

Acceptable Test Method(s)

Description

Aggregate Base Relative Compaction

CT 216/CT 231

Determines field densities using a nuclear gage.

Concrete Strength CT 521

Determines compressive strength of molded concrete cylinders

Grout Compressive Strength

ASTM C1019

Determines compressive strength of freshly-mixed grout using grout sample box.

Steel Rebar

Tensile Strength & Bend Capability

ASTM A625;

A370

Determines tensile strength and bend capability

Any costs to the County for testing layers which fail the compaction requirements may be deducted from any progress payment due to the Contractor when, in the opinion of the Engineer, such failure results from the Contractor's lack of diligence in pursuing compaction effort. In the event that a test fails, any testing after the first shall be at the Contractor’s expense.

SECTION 7.

LEGAL RELATIONS AND RESPONSIBILITY

Attention is directed to the provisions of Section 7, “Legal Relations and

Responsibility to the Public,” of the Standard Specifications, these Special Provisions, and to the provisions of paragraph VIII, “Insurance,” of the Agreement (AG) portion of the Contract Documents for insurance requirements “Electronic Signature,” of the

Agreement (AG) portions of the Contract Documents.

7-0.10.Federal Forms, Posters and Data Required of Contractor During Construction

The Contractor is advised that there are Federal posters required to be posted at the job site and forms required to be submitted during construction.

Reference is made to the “Federal Requirements for Federal-Aid Construction

Projects” section of these Special Provisions for a listing of the most-commonly required forms. Reference is made to the pre-construction checklist titled

“Federal-Aid Maintenance Contract” (Appendix G, “Pre-Construction Hand-Out

Packet for Federal-Aid Projects”.

The Contractor is further advised that, should Contractor fail to post the required posters at the job site or provide the Federal forms in a timely manner without due cause, as determined by the Engineer, the Engineer shall have the option, at his discretion, to either withhold the progress payment or issue a stop work order until such forms have been submitted to the Engineer.

7-0.11.Required Listing of Proposed Subcontractors

All proposed subcontractors shall be listed by the Contractor in conformance with Section 2-1.10, “Subcontractor List,” of the Standard

Specifications.

Each proposal shall have listed therein the name and address of each subcontractor to whom the bidder proposed to subcontract portions of the work in an amount in excess of one-half of one percent (0.5%) of his total bid or $10,000, whichever is greater, in accordance with the Subletting and Subcontracting Fair

Practices Act, commencing with Section 4100 of the Public Contract Code. The bidder's attention is directed to other provisions of said Act related to the imposition of penalties for a failure to observe its provisions by using unauthorized subcontractors or by making unauthorized substitutions.

A sheet for listing the subcontractors, as required herein, is included in the

Proposal.

7-0.12.Labor Nondiscrimination

The Contractor is advised that the State Standard Specifications shall apply if and where any conflicts between this Section 7-0.13, "Labor

Nondiscrimination," and Section 7-1, "Equal Employment Program for Minority

Employment," of these Special Provisions and the State Standard Specifications exist.

Attention is directed to the following Notice that is required by Chapter 5 of

Division 4 of Title 2, California Code of Regulations:

NOTICE OF REQUIREMENT FOR

NONDISCRIMINATION PROGRAM

(GOV. CODE, SECTION 12990)

Your attention is called to the "Nondiscrimination Clause", set forth in

Section 7-1.02I(2)), "Nondiscrimination," of the Standard Specifications, which is applicable to all non-exempt State contracts and subcontracts, and to the

"Standard California Nondiscrimination Construction Contract Specifications" set forth therein. The Specifications are applicable to all nonexempt State construction contracts and subcontracts of $5,000 or more.

7-0.13.Prevailing Wage

Attention is directed to Section 7-1.02K(2), "Wages," of the Standard

Specifications.

In accordance with the provisions of Section 1770 of the Labor Code, the

Board of Supervisors of the County of San Mateo has ascertained the prevailing rate of wages applicable to the work to be done, which prevailing wage rates have been established as indicated in the Notice to Contractors and are incorporated herein by reference.

7-0.14.Buy America…