Crane_Repairs.docx
DOCX document 93 KB Posted
- Attached to
- Training Ship GOLDEN BEAR Crane Repairs
- Solicitation number
- DTMA94Q1500034
About this file
Statement of Work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 10Sept2015_Corrections_-Crane_Repairs.pdf | ||
| downloadForm.pdf | ||
| 05-2069.htm | HTM file | |
| DTMA94Q15000_.docx | DOCX document | |
| dtma94q1500034_.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2015 POST CRUISE CRANE REPAIRS
GENERAL REQUIREMEMTS – TS Golden Bear (TSGB)
2015 POST CRUISE CRANE REPAIRS
Intent:
The following general requirements apply to all work performed in the execution of this SOW including all Supplemental Labor and Supplemental Material ITEMS. Additional requirements are stated with each CLIN ITEM. The costs associated with implementation and accomplishment of these requirements during the planning and performance of each specification item and subsequent delivery orders shall be included in the pricing of each line item of the specification.
Work Description:
Definitions
The following terms shall be understood to have these meanings:
“As approved”, “for approval” - When used without further qualification, the decision of the Regulatory Body representative is intended. For items which are not covered by regulations, the decision of the COR is intended.
“Brand Name or Equal” - As used in this provision, the term "brand name" includes identification of products by make and model. Equal to Brand Name must be established prior to time of award
“Contract” - The agreement entered into between the Owner or Owner’s representative and the Contractor for the accomplishment of the work specified in the Specifications.
“Contractor” - The shipyard or ship repair firm acting as the prime contractor responsible for accomplishing the provisions of the subject Contract.
“COTR/COR” - Contracting officer’s technical representative overseeing the repair availability.
“Critical Path Items” – means any CLIN item that has specific time restrictions that might affect the completion date of April 1, 2014. The contractor must alert the COR and Contracting Officer as soon as they are aware of any condition that might affect the scheduled completion and identify the CLIN as a Critical Path item.
"Detach" - means that the Contractor shall unbolt, unpipe, and disconnect all attachments to the unit to enable the unit to be moved, and/or to unbolt, unpipe, and disconnect a fixed unit. All attachment points shall be tagged, identified, and protected to facilitate reinstallation. This definition also covers reinstallation of detached units.
“Deliverables” – means specific information or materials or services that are part of the contract and are a required part of the job that must be delivered to the Ship and/or COR before the job for CLIN number is considered to be completed.
“Gant Chart” – means a formalize chart (Gant Chart) which shows the exact start and completion for each CLIN item of the contract and pertinent steps for each CLIN with their start and finish dates. This is a deliverable and must be updated weekly.
“Government” - Means the United States Government, including the Maritime Administration (MARAD).
"Install", "extend", and "modify" mean that the Contractor shall provide the piece of equipment to be installed, and, in addition, shall provide the materials and labor to install, connect, test, remove and reinstall interferences, and effect a finished, fully operational installation. When "install" is used with reference to GFE, all conditions of the previous definition except the requirement to provide the piece of equipment are applicable.
“Owner” - The U.S. Department of Transportation, Maritime Administration (MARAD), and authorized representatives.
“Provide” - Means to furnish and install all services, materials, equipment and systems to accomplish stated requirements.
“Regulatory Body” - Means the American Bureau of Shipping (ABS) or a Federal Government or international regulatory agency or an organization which is authorized by the agency to perform delegated regulatory functions on its behalf.
“Regulatory Body Requirements” - means the regulations, rules, requirements, and interpretations issued by Regulatory Bodies.
“Remove” - Means to take the existing off the ship without replacement.
“Repair” - Means to fix the existing thereby restoring it to its original capabilities.
”Renew” - Means to remove the existing then replace with new of similar or specified capability
“Specifications” - The document containing the Work Items that specifies the work requirements to be performed by the Contractor
“Substitution”- Means agreed upon change of OEM or specified Manufacturer’s parts by Chief Engineer and COR. The reason that this is necessary is to insure proper replacement parts for specific equipment manufacture to maintain warranty and reliability
“Unforeseen Growth Work and Supplementary” If additional work within the scope of the work is required the vendor must submit a condition found report with recommended change and obtain COR advance approval to the agreed change at a specific price before starting any work. The vendor works at company risk without COR or Contracting Officer’s advance authorization in accordance with FAR CLAUSE “MCL.H-2 Supplementary Work Requests”.
TSGB HR00- Contractor Familiarization
Each contractor who has been awarded a contract to work aboard TSGB must complete the TSGB HR00- Contractor Familiarization form prior to that time that they begin their work aboard the vessel. This must be completed with the Chief Mate or his designee and any stipulations that apply must be relayed to all contractor employees prior to the time the contracted work is begun.
Some of the following statements are a part of the TSGB HR00 but must be followed both in the Familiarization Form and any additional details cited below.
Accomplish the Requirements of the Contract
The Contractor shall satisfactorily perform all work and details therewith, to the required standards and shall provide all the necessary resources in that performance. Details that are not mentioned in these specifications, but which are usual and necessary for shipboard work shall be furnished by the contractor.
Noncompliance/nonconformance with the requirements of the Contract or Work Items, discovered by the Government will be reported to the contractor in writing.
Contractor shall respond in writing to the COR, indicating the corrective action taken and, where applicable, the action to be taken to correct the cause of the deficiency.
Written responses shall be within two (2) working days from notification. Payment as stated in FAR 52.212-4 is subject to requirement completion and acceptance.
Provide Labor, Material, and Equipment and Travel Provide all labor, material and equipment and travel required for the completion of the specifications, unless specifically identified as Government Furnished Material (GFM) in the individual work items.
Report Production Delays and Difficulties
In the event difficulty is encountered or anticipated in complying with the contract requirements or schedule dates, notify the COR immediately by verbal means, followed on the next work day, by written correspondence stating the pertinent details. Receipt of this notification by the COR is not to be construed as a waiver of the contract requirements or delivery schedule by the government; nor is it a waiver of rights or remedies provided by law or under this contract relating to jeopardy of the contract schedule. The contractor is responsible for identifying this type of problem as a “Critical Path” item that might extend the completion date.
Verify Dimensions
Any and all dimensions, measurements, size, shape, quantities, etc., in the specifications including drawings, sketches, etc., contained therein, are not guaranteed to be correct. The contractor shall be responsible for the tasking, determination, and ascertaining of any and all dimensions, measurements. The contractor should take full advantage of any ship check/inspection periods offered for this purpose.
Accomplish Joint Vessel Inspection.
Once issuance of the Notice to Proceed Modification is received, the Contractor and MARAD COR and/or Chief Engineer and Chief Mate shall meet aboard the TS Golden Bear for a vessel inspection.
A videotape with commentary shall be prepared by the Contractor concurrent with the inspection. The videotape and one copy shall be submitted to the COR with a serialized Condition Report within five working days. This requirement will be applied on a case by case basis depending upon the scope of the work for the individual contractor.
Provide Closures Against Weather and Service lines, hoses and cables
The contractor shall use existing closures and provide temporary closures as necessary to prevent intrusion of weather related elements (rain, snow, sleet, etc.), into the vessel. Temporary closures materials may include the use of plywood, canvas, herculite or other materials at the contractor’s option and expense to cover temporary access openings or the opening of doors, scuttles and cargo hatches for periods in excess of 24 hours. Additional protection from sandblast grit intrusion shall be provided per contract or a separate item.
Cargo hatches shall be closed at the completion of daily work unless work is scheduled in specific cargo holds around the clock.
Service lines, hoses and cables shall be run through a single door as mutually agreed upon by the contractor and COR. The service line access shall be separate from the primary personnel access. Electrical Cables shall be protected from being damaged by blocking the door or using special access if fitted.
Workmanship and Nondestructive Testing
Workmanship shall be of the highest quality commercial marine standard and shall be subject to the approval of the COR upon completion. Welding shall meet ABS and USCG requirements and conform to American Welding Society (AWS) standards. All welds shall be cleaned prior to painting. All surfaces which have been cut, drilled, welded, or otherwise modified shall be cleaned free of grease, slag, and foreign matter
All welding shall be in accordance with ABS requirements and Welders must be certified by the local ABS Representative. All Non-destructive testing of welds shall be in accordance with ABS requirements and certified by the local ABS representative
Welded connections of major items installed and modified by the Contractor shall be subjected to nondestructive testing as delineated for the particular items in this specification. All such testing shall be performed by qualified personnel and shall be in accordance with ABS “Rules for Non-Destructive Testing of Hull Welds Contractor Use of Vessel Equipment and Materials and Toilet Facilities
The Contractor shall NOT use, without explicit permission on a case by case basis, any vessel spare parts, equipage, equipment, special tools or materials.
Vessel’s machinery and equipment are NOT to be operated by the contractor’s personnel or subcontractors except as explicitly authorized on a case by case basis by the COR (or designated crew such as Chief Mate or Chief Engineer), or as explicitly required elsewhere in the specifications. The Contractor shall sign for all drawings and tech manuals deemed necessary for examination off site.
MARAD will supply Port-A-Potty and Wash Basins on the pier. Contractors should not use the Ship’s Toilets.
Cleanliness, Tests and Job Completion
Upon item and job completion, all interior and exterior spaces, equipment, machinery, tanks, cargo holds and accommodations affected by repairs shall be left in a clean and orderly condition and ready to serve their intended purposes. A joint redelivery inspection will be held by the COR (or his appointed Crew Member such as Chief Mater or Chief Engineer) and Contractor at least 2 days prior to scheduled delivery date and vessel acceptance by the Government. During this joint inspection, any further cleaning and outstanding deficiencies will be noted, which shall be completed prior to the delivery of the ship. No work may be deferred for accomplishment after the ship’s redelivery, unless it is shown to be advantageous to the Owner.
All new, disturbed and/or soiled materials, surfaces, equipment, etc., affected by the accomplishment of these Specifications and any Delivery Orders shall be cleaned, prepared, coated, recoated, re-lagged, reinsulated as directed in other applicable items in this contract.
Work that requires testing shall be completed in time to allow correction of deficiencies prior to any dock trials, sea trials, and other applicable milestones established in the contract.
The Contractor is responsible for disposal of all waste and debris generated as a result of any work performed. Use of shipboard or California Maritime Academy waste bins is prohibited. Coordinate with the Chief Mate for an acceptable place to place a contractor furnished disposal bin on the pier or the ship, if deemed necessary. All hazmat waste streams generated as a result of this contract are the responsibility of the contractor for lawful disposal, manifesting and transportation. No hazmat, including blasting debris, may be disposed of on ship or CMA premises.
Daily and Weekly Communications
The contractor, or his foreman representative, shall meet with the First Assistant Engineer and/or Chief Mate at the beginning of each day they will be onboard to discuss the day’s work plan, number of workers aboard, hot work anticipated, ship’s systems affected, and other ship coordination issues. This shall be a formal meeting and must take place before work begins, at the same time daily. The representative for the Contractor shall be the same individual for the duration of the voyage repair package.
Once a week or as dictated by the COR, the ship superintendent shall walk each onboard job with the COR.
Contractor is responsible for all of their required loading operations and activities including opening/closing of hatch and operating ship’s crane (when available) under the authority and permission of the Chief Officer. CMA may be able to assist contractor with forklift and crane services. Contractor must arrange for crane and forklift services 24 hours in advance.
Contractor will at all times (each day) coordinate with Chief Officer on pier and ship access and availability, including vehicle parking. In the absence of the Chief Officer, coordination shall be conducted with PIC of the boathouse.
Hotwork and Co-ordination with Ship for same Hot work will only be allowed during normal work hours on weekdays. The Chief Mate or Chief Engineer shall be notified before any hotwork is commenced so that fire detection systems can be temporarily disabled. All hotwork will be done with proper fire watch and fire extinguishers on hand. Fire watch to stay on site for a minimum of 30 minutes after any hotwork is performed. Contractor must get permission for doing hotwork outside of normal work hours after 1700hrs and on weekends or holidays and it must be approved by the Chief Engineer and/or Chief Mate.
Designated work hours and Weekends, Holidays including School Breaks Regular working hours are weekdays from 0700/0800 until 1700.
All work, tests, and inspections shall be performed in this time frame.
COR may authorize work outside these hours on a case by case basis.
No work will be allowed to take place during campus breaks, unless approved in advance by the COR.
Bidders should request an academy calendar from the COR one week before bid submissions.
Contractor Log and Contractor’s ID
The contractor shall maintain a log of all persons on board the ship, who are employees, agents, or subcontractors for work being performed. Daily, all personnel are to sign the logbook upon arrival onboard, and to sign out upon departure. The logbook is a deliverable, separate from the ship’s log book, and shall be provided and maintained by the contractor. The contractor is responsible for its accuracy and content. Each week during the contract performance period, provide the COR with a copy of the previous week’s log or more frequently if requested. At the end of the contract, provide the COR with a complete copy of the logbook (or the original). These deliverables are to be attached to a serialized condition report.
All onboard workers, including subcontractors, must wear a badge identifying themselves as contractor employees. Those persons without badges may be escorted off the ship Painting and Paint Inspection All painting shall be approved by the First Engineer and/or Chief Mate to insure proper procedures and products are used for each location.
ABS Surveyors Payment and Scheduling and USCG Inspectors The Contractor is responsible for scheduling all ABS and USCG inspections, surveys and checkpoints cited in the CLIN’s. The contractor shall pre-inspect and pretest prior to making these arrangements to assure successful completion of checkpoints. The Contractor must alert the COR and/or Chief Engineer and Chief Mate regarding USCG or ABS inspections at least two (2) days in advance of their arrival.
MARAD pays for the local ABS Surveyor under a separate purchase order.
The Contractor is responsible for any review or approval by ABS outside the Oakland ABS office.
Parking Permits and Pier Access Contractor is responsible for all employees and sub-contracting employees to purchase valid parking permits when on campus and to be briefed on waterfront and pier parking regulations. Pier access for work trucks is by permission of Chief Mate only. All contractor personal vehicles shall be parked in either Lots E or F and ferried down by others or parked outside the gates and similarly ferried. Any parking citations received are the contractor’s responsibility. Any ferrying for employees is the contractor’s responsibilities. The Waterfront parking lot has limited parking and a monthly pass is required from the Cashier’s office in the Administration Building to use this parking lot. Waterfront parking lot is on a first come first serve basis for Ship Superintendents only. Contractors are requested to use other parking if available.
MARAD Warehouse and Transfer of Articles to/from same When a CLIN tasks the contractor to transfer articles to the MARAD warehouse, the Contractor shall perform the following steps:
· Assist the ship storekeeper in entering a property transfer into NS-5.
Notify warehouse in advance of delivery. POC is Mike Streblow at (510) 337-5084.
· Transfer article with the form.
Provide COR with a copy of the form with both signatures (warehouse and storekeeper).
The address for the warehouse is:
MARAD SBS Warehouse 1651 Viking St.
Alameda, CA 94501
Substitutions and General Criteria Costs and Technical Representatives Substitutions for specific materials and equipment cited in CLIN’s must be pre-approved by the COR prior to Notice to Proceed (NTP).
When cited in a CLIN, The contractor and applicable tech reps shall attend the ship’s one-day sea trial, date to be determined.
The requirements within this General Criteria are not to be separately priced. Cost for this item shall be spread out and incorporated against the appropriate awarded work CLIN(s).
INTERFERENCES
Intent: The Contractor shall detach and reinstall all interference in way of accomplishing specified work.
An interference is any part of a ship, whether installed or portable, that must be moved or disturbed in the accomplishment of work specified in the Work Item. Contractor is responsible for identifying all interferences to all items during the ship-check period.
Statement of Work:
Identify all the interferences at formal bidders’ ship-check of the vessel.
When work on the vessel is started:
· Visually examine each interference before removal. Note any damage or deterioration to it that was already there, and protect it from damage before it is removed.
· When removing the interference, take caution not to damage it.
After interference removal, inspect it again. If it is damaged, make a note and notify the COR in writing. Tag it for reinstallation, or disposal if approved by COR.
Before reinstalling an interference:
· Check it again.
· If it is acceptable, go ahead and reinstall it.
· Do not reinstall anything that was damaged before, deteriorated, or damaged later. Notify COR if this takes place.
Protect interferences from damage or loss, and prevent contamination of detached or removed components and remaining parts of the system.
Visually examine interferences prior to and during detachment for previous damage and deterioration. Report any damage or deterioration to the COR.
Material containing asbestos which requires removal as an interference shall not be reinstalled. The Golden Bear is an asbestos free ship.
Install stamped or engraved solid metal tags on interference’s to indicate the ship’s name, location and Work Item number prior to detachment or removal from system or shipboard location.
Reinstall interferences which were neither reported as previously damaged or deteriorated nor rendered unsuitable for reinstallation during removal.
Install new material in place of material rendered unsuitable for reinstallation during detachment, removal, or storage.
New material shall be equal in composition, strength, design, type, and size as existed prior to removal of the interferences.
Install new insulation and lagging in place of that removed as interference.
Install new reusable covers except when reinstallation of existing reusable covers is identified by the invoking Work Item.
Install new fasteners and gaskets when reinstalling interferences.
Restore compartment, equipment, and systems labeling.
Install new deck covering in place of that removed or damaged as interference.
New material shall be equal to existing in color and composition.
Align and accomplish appropriate strength, tightness, system cleanliness, and operational tests and ensure that the reinstalled interferences perform their normal functions within the system.
These requirements are not to be separately priced. Cost for this item shall be spread out and incorporated against the appropriate awarded work CLIN(s).
SCHEDULING AND PROGRESS REPORTS
Intent: The contractor shall prepare and submit for review and acceptance by the COR, accurate contract scheduling data, which is relevant to the scheduling and progress of the repair availability for the entire project. A Gant chart shall be presented at the time of the Post Award Conference detailing the exact start and completion dates and milestones for each CLIN to the COR and Contracting Officer and Ship’s Senior Officers. Contractor must identify any Critical Path items at the time of award.
The reports should be indicative of the planning and scheduling required to ensure an integrated and timely completion of all CLINS, and to ensure the contract delivery date is achieved. CLIN items must reach completion before April 1, 2015 if at all possible. If completion cannot be accomplished by this date, alert COR in writing of that fact and supply a schedule of when the job will be completed.
Scope of Work: Each Thursday, provide the COR with a weekly report denoting the percentage completed on each CLIN item and show them on an updated Gant Chart. Incorporate all task orders and contract modifications to this report.
At minimum, the weekly report and Gant Chart shall depict:
· CLIN items with controlling work items clearly indicated
· Scheduled start and completion date of the production work for each CLIN
· Actual start date for each CLIN
· Actual finish date for each CLIN
· Provide the COR with a separate weekly PERCENTAGE COMPLETE REPORT
· Percent completion to date of each CLIN and each TASK ORDER in the work package
· Overall percentage completion of the work package
Both reports shall be delivered to the COR within (3) three days of award of contract, and shall be updated and submitted weekly to reflect the addition, deletion, or modification of CLINS, and changes made by the Contractor or Contracting Officer.
Manage and schedule subcontractors’ production work/progress, material procurement, and interface control to support the overall production schedule.
Provide a list of subcontractors by CLIN Number to the COR within (3) three days of award of contract. A revised list is to be provided whenever changes occur to the list.
The subcontractor list shall include:
· CLIN number
· Specific work to be accomplished
· Subcontractor’s business address and telephone number
On the first week of the availability, provide the COR with a list of all the deliverables cited in the contract, and the intended delivery date for each of these deliverables.
These requirements are not to be separately priced. Cost for this item shall be spread out and incorporated against the appropriate awarded work CLIN(s).
Upon completion of a CLIN, conduct a walk-through of the work cited in the CLIN accompanied by the COR, First Engineer, and Chief Mate. Develop and submit a sign–off sheet for each CLIN, to be signed by ship superintendent and COR. Provide the COR with a copy of all sign-off sheets as they occur.
DELIVERABLES:
· Weekly report denoting the progress on each critical path CLIN
· Weekly PERCENTAGE REPORT
· Subcontractor list
· List of deliverables Sign–off sheet for each CLIN
Security
Security requirements as outlined in the following “Security Instruction” titled “Security Instruction number 1” shall be strictly adhered to.
Security Instruction number one
DATE: November 10, 2014
TO: All Contracting and Vendor Personnel
| FROM: | Captain Harry Bolton | |
| Company Security Officer, California Maritime Academy |
This is to inform all persons that may visit, conduct work, provide technical or sales services or have other official business aboard or in any way need access to be alongside or aboard the training ship GOLDEN BEAR , that International and Coast Guard regulations requires stringent access control to all U.S. vessels by all persons in accordance with those regulations. This includes the training ship, whether she is in a foreign or in any domestic port. Additionally, the California Maritime Academy may invoke additional requirements to gain access to the campus if it is determined by the U.S. Coast Guard that the CMA is a “port facility” under the new regulations.
These security requirements will require that all visitors, contracting personnel, vendors, sales-persons and any technical consultants comply with the requirements outlined herein before being allowed to board or approach the training ship. Failure to comply in whole or in part of these regulations may lead to the expulsion of personnel from the vessel until full compliance is achieved. Any and all additional costs resulting from this eventuality, including delays in work, denial of access for subcontractors or any other interruption of contracted services, is to be completely borne by the contracting or vendor companies. Only pre-authorized persons will be allowed onboard. This includes visitors.
All contracting, vendor, or visiting personnel, must at all times, comply with any and all requirements and rules promulgated by the ship’s Security Officer, which in the case of the GOLDEN BEAR, is the vessel’s Chief Officer. These requirements are those made by the training ship and the California Maritime Academy. Any additional security procedures, rules or requirements promulgated by MARAD will be in addition to these requirements.
Any or all of the following rules and procedures must be complied with depending on the official national maritime threat level:
1. Campus access and parking may be controlled by the school’s Police Service department.
2. All personnel wanting unescorted access on the TSGB must possess and produce a valid TWIC card. All personnel wanting entry into a “Restricted Area” must be authorized by the Captain, Chief Mate, Chief Engineer or COTR. The primary contractor shall be responsible for issuing all of their direct employees and as well as their designated sub-contractor’s employee’s identity verification and authorized company photo ID cards. Non-photo company identification cards will not be accepted. These identification cards are required to be worn in a visible location. Subcontractors and employees without company ID shall be required to obtain from the CMA/GOLDEN BEAR a daily visitor pass in the form of a generic ID card that authorizes the holder to be onboard. The daily visitor cards will be required to be worn in a conspicuous manner so that each person is readily identifiable by ship’s officers and security personnel. The cards will be used to log workers and vendors on and off of the vessel using the ship’s logging system. These Golden Bear Visitor cards must be issued and surrendered at the beginning and end of each day for logging in and out. Failure to surrender the visitor card at the end of the day shall be treated as a security violation.
3. Outside company employees newer than six months and all temporary visitors not known to the Academy are subject to security background inquires by the CMA consistent with current laws before they will be permitted to board the vessel.
4. Materials or parts delivered directly to the campus/ship are subject to search and screening by the ship’s Security Officer. Deliveries of equipment, parts and materials must be declared to the ship Security Officer at least 24-hours in advance of the delivery and must be scheduled for screening before being loaded aboard.
5. Materials and supplies shipped in advance or drop shipped to CMA’s facility must pass through the campus warehouse for screening. This screening process shall be conducted by the ship’s security officer (Chief Mate) and an authorized person designated by the contractor. This inspection and shipping documentation screening must be accomplished before any materials can be loaded onto the vessel.
1. Contractor vehicles will not be allowed onto the pier without first being screened by the vessel’s security officer. This may be done daily. The same applies for contractor tool boxes or other equipment when first loaded aboard. Ship security personnel shall work closely with contractor’s management personnel to achieve workable but effective security concerns.
7. Depending on the national security threat level, all persons needing access to the vessel may be subject to random personal and bag checks. If the vessel is at a heightened security level, ALL persons may be subject to these searches or screenings.
8. The contractor and shipboard management supervisors must attend a one-hour security orientation on or before the first day of a contract performance period. This orientation will be conducted onboard the vessel by the Ship’s Security Officer. It must be emphasized that contracting personnel or their sub-contractors who have not been authorized to be onboard the vessel will be denied access to the vessel.
9. In conjunction with the orientation, a short security briefing will be conducted before the contract begins. This briefing shall be attended by:
· MARAD COR
· Company Security Officer
· Ship Security Officer
· Director of Campus Public Safety
· Warehouse Supervisor
It must be emphasized to contractors and visitors that these requirements are mandatory, and that any disruption or recalcitrance demonstrated by visiting or contracting persons onboard concerning these requirements will be denied access to the vessel until full cooperation is achieved. If necessary, persons who are being uncooperative or belligerent will be removed from the vessel permanently and reported to national authorities. It is the desire of the CMA and the training ship that all work is accomplished in the spirit of security awareness and cooperation and every accommodation that can be given while maintaining compliance with the regulations is encouraged.
Regards, Captain Harry Bolton CMA Security Officer
SHIP’S CRANES MAINTENANCE & REPAIR
FY15 – POST CRUISE REPAIRS PERIOD
ABSTRACT
Contractor to furnish the services of a qualified Crane technician to perform needed maintenance and repairs as noted in April 2015 Inspection Reports. Specific repairs are noted in the following Statement of Work and CLIN items.
Once repairs are completed, each crane is to be weight tested as noted in the Statement of Work and similar to the weight testing performed and as described in the inspection report from April 2015.
Final repairs to be documented in a final report and submitted as a deliverable with recommended additional maintenance needed in the future
LOCATION AND DESCRIPTION
Location of Trident Cranes:
Trident Cranes are located on the 01 Deck Midships between the Forward and After Houses Description of Trident Crane Repairs
TRIDENT MODEL: TMP 20-23T38 - REVOLVING MARINE PEDESTAL CRANE
SERIAL NO.1223862220- 0524872222 & 1224862221 - 0529872228
TRIDENT MARINE CRANES
18071-B MT. WASHINGTON STREET
FOUNTAIN VALlEY, CALIFORNIA 92708 S-8603-2001 /2002
MARCH 20, 1986
TAGS 39/40- HULLS 4667/4668
Trident Cranes:
Port Crane:
Corrosion control for hardware Hydraulic System leak repair and service Systems Maintenance and component renewal Boom removal, corrosion control and structural inspection
Starboard Crane:
Corrosion control for hardware
Systems maintenance and component renewal
Hoisting winch re-seal and test
Boom removal, corrosion control and structural inspection
Rotary bearing fastener renewal
Location of After Crane After Crane is located on the After Main Deck Description of After Crane Repairs Mfgr: EBI Cranes EBI – Elevated Boats LLC St Bernard Park Way, Poydras, LA 70040
(504) 682-5245 P.O. # TM61918; Serial No. TC40-40-73E Load Line Winch:
Model and S/N = W20-1000 P/N = 8205-3330090 Motor Model and MFG = COMM.WM512SPD P/N = 4931-3337145 Fast Line Winch:
Model and S/N = EBI W5-500 P/N = 8205-3330050 Motor Model and MFG = COMM. 2” Gear 50 Series P/N = 4931-3337125
After Crane items:
Recommendation:
1. Replace rusted hydraulic hose supports and hangers with new.
2. Slewing bearing and race be inspected and renewed if found to be beyond acceptable wear
3. Load Test upon completion of repairs
STATEMENT OF WORK
CLIN No: 0001 – SR No 0301887 – After Crane--AFT EBI CRANE S/N TC 40-40-73E
1) Crane Technician to have proof of experience of working on similar cranes on at least 3 ships or shoreside installations.
2) Contractor is responsible for all Labor, Transportation, Rigging and Materials to complete the repairs and weight test as noted in the contract.
3) Contractor to supply their costs for changing the Slewing Bearing (bearing and race) in the event that it is found to be beyond its useful life. Costs to include use of a shoreside crane or support via scaffold or steel supports whichever is the acceptable practice to the Contractor’s Crane Technician.
4) Contactor’s primary focus is to be the Slewing Bearing inspection and repairs. If other conditions are found to be in need of repair or maintenance, the Contractor is to submit a Condition Found Report with recommended repairs and estimated costs for same
5) Upon completion of the repairs, the Contractor is to supply weights and manpower to conduct the weight test as noted in the inspection report as to weights and Jib and Boom positions. All Weight Testing will be conducted in the presence of the Chief Mate or his designee and a 5 day notice to Chief Mate to be given prior to the test
6) After any repairs are completed, the crane will be tested by the Chief Mate or his designee to prove acceptable operation and reliability
Inspection Report – Bay Ship & Yacht
The Aft EBI Crane was visually inspected and operated for OSHA Standards Compliance.
1. Hydraulic Hoses: All hydraulic hoses on the crane have been renewed with Parker hoses and stainless steel crimp fittings. An operational test was performed and zero leaks were detected. All work was witnessed and approved to the satisfaction of Chief Mate and the COR. After testing all exposed hose fittings were wrapped with densyl tape. Found all the hydraulic hose supports and hangers rusted and deteriorated.
Contractor removed existing 3/8” pipe from hydraulic system that was previously abandoned (not used). Also renewed 3/8” steel pipe and fittings for the boom hose reel. Supplied new piping and fittings and hydraulic connections. Upon repairs, operational test was performed, all repairs were witnessed to the satisfaction of Chief Mate and the COR.
2. Anti-Two Block Devise: Contractor tested and repaired, as necessary, the anti-two block protective device. Contractor found the anti-two block devise batteries were expired. Ship supplied contractor with new batteries. Replaced expired batteries with new. Operational test was performed and found the anti-two block devise working satisfactory.
3. Hydraulic Controller and Electric Controller: Contractor performed operational test on the hydraulic system, while performing weight test at 17,000 lbs. on the main boom and 5,000 lbs. on the jib boom, all hydraulics performed in satisfactory condition. Witnessed to the satisfaction of Chief Mate and COR.
Electrical controller was surveyed and megger tested. All megger testes were witnessed to the satisfaction of the Chief Mate and Chief Electrician and COR. All electrical components are operating in satisfactory condition.
4. Crane Load Test: Contractor performed an operational load test on crane. The Jib was tested to 5,000 lbs. at 52 degrees. The main boom was tested to 17,000 lbs. at 52 degrees. All weight testing was witnessed to the satisfaction of Chief Mate and COR.
5. Contractor found that the slewing bearing and race for the EBI Aft Crane are worn.
6. Contractor finds the exterior of the Aft Crane in need of preserving, with rust build up and scale.
Recommendation:
1. Replace rusted hydraulic hose supports and hangers with new.
2. Contractor recommends the slewing bearing and race be inspected.
CLIN No: 0002 – SR No 0301888 – Trident Midship’s Cranes (2)
1) Contractor to address all of the items Iisted in the Inspection report by All Cal Equipment Services Inc. Focus should be on the mechanical and structural parts of the crane. Chipping and priming and painting items should be noted as a deficiency and reported via a Condition Found Report with specific conditions and suggested repairs with listed costs.
2) Contractor to supply a Crane Technician who can supply proof of having worked on 3 or more similar cranes on ships.
3) Once the repairs are completed, Contractor to supply weights to test the cranes to 10,000lbs as noted in the inspection report
4) Contractor to supply, labor, transportation, material and rigging to accomplish the following:
Port Crane and Starboard Crane
· Both Booms to be opened for inspection and gauged to determine what the thickness of the metal is and if any steel has to be renewed or doubled. Any structural changes must be approved by ABS prior to execution. If access is not possible then openings may have to be made and then covered after inspections and repairs. If Crane Technician believes that that the booms must be removed to allow for proper maintenance, inspection and repairs then this should be stated in the bid and become a part of the overall job scope.
· Contractor to fabricate and print new stainless steel load charts and controls instruction sheets that are presently illegible. These are to be mounted using a double sided adhesive tape (such as 3M product).
· Contractor to change any frozen valves or gages with stainless steel design and also correct any leaks in any parts of either of the two cranes
· Clear all grease points to allow proper maintenance by Crew. At a minimum, Contractor to renew all the zerk fittings and tubing if they do not pass grease
· Inspect and repair all electrical faults noted in the inspection reports including the indicating lights and electrical connections and watertight fittings
Port Crane
· Articulating portion of the base boom- Boom Heel Pin – Remove and clean and polish; clear all the grease points and prove that grease can pass; Renew the pins and retaining washers with stainless steel fittings
· Upper Turret Section – Boom Heel Pin –Mounting Ear – Repair to reduce or correct the movement as noted in the inspection report
· Boom Tip Sheave – Repair or renew
· Load Block – Repair or renew
· Address all of the items in the inspection report if not listed above
Starboard Crane
· Contractor to correct the Starboard controls problems noted in the inspection report so that proper operation is possible including the proper mounting of the controls
· Contractor to Renew all the Rotary Bearing Fasteners using stainless steel materials
· Boom Base and Boom Inner Slide Pad – Replace the missing slide pad and retaining bracket
· Electrical deficiencies – Correct the deficiencies noted in the inspection report
· Address all of the items in the inspection report if not listed above
Inspection Report All Cal Equipment Services, Inc.- Scott Webster
Subject: Safety Inspection of Trident 10,000lb capacity port and starboard stores cranes
M/N: TMP20-10-23T38
Dear Sirs, The Scope of Work Accomplishments: Port Trident 10,000 lb capacity unit:
The unit was inspected visually for OSHA standards compliance.
Deficiency: Boom Heel Pin- the pin at the articulating portion of the base boom is seized into the boom. No presence of lubrication presented. The pin retaining washers are corroded beyond standards for simple washers. The pin protrudes out of the left side of the boom mounting ear on the operator’s left hand side. This condition requires attention immediately.
Deficiency: Boom Heel pin mounting on the upper turret section- the mounting ear on the operators left side of the turret has excessive TIR. The movement within the mounting ear is visual. The mounting ear is devoid of lubrication. This condition requires attention immediately, continued use will degrade the mounting ears as the crane continues to be used in normal operations.
Deficiency: Hydraulic extensible boom- large corroded debris accumulating at the turret below the rear exit of the boom. Visual inspection of the interior of the boom presents further excessive steel pack rust and de-lamination at the interior visible portion of the boom steel structure. Further inspection would be required to confirm the condition of the box steel boom sections. Condition would be considered serious, and at the minimum would need an internal inspection for structural integrity.
Deficiency: Hoisting winch supporting structure- The operators left side hoist side support plate presents heavy corrosion and minor pack rust. Coating removal necessary, after removal, inspection to determine condition of steel structure. If condition left unattended condition will degrade, creating a possible unsafe condition.
Deficiency: Crane load chart- Illegible; unit does have a variable load chart. Standards require a clearly visible load chart to be present to the operator. Unit has a Hydraulic control to further effect chart.
Deficiency: Crane controls- controls present to the operator not clearly indicated. Standards require all controls to be clearly marked when presented to the operator.
Deficiency: Crane controls- active oil leak at operator’s console. Oil leak present at operators left side. This condition presents an unnecessary operation condition that may at some point adversely affect the operator. If condition left unattended it may degrade to affect crane performance and safety.
Deficiency: Crane control- system pressure gauge, is not intact. The needle is indicating pressure when in fact no pressure is present. Gauge face has become foggy and difficult to read. To the above mentioned oil leak; the gauge has a valve to allow operation. The valve has the actual leak, and has been “duct” taped to prevent the oil leak.
Deficiency: Crane Boom Tip- upper boom tip sheave has excessive TIR at the cross shaft. The excessive TIR is most notably transverse to the axle. Indicating that the bushing / bearing has excessive wear.
Deficiency: Load block and system- Excessive play in load hook swivel pin. Load hook safety latch operates incorrectly. Standards require regular inspections, Manufacturers maximum wear tolerances to be adhered to, and deficient devices removed from service Load hook safety latch is not held within the interior of the hook throat. This presentation would indicate a condition that may require a new safety latch to become compliant.
Deficiency: Boom Hoist upper connection point- the rod end of the boom hoist cylinder is retained by a fixing pin. The boom structure has additional backing half shells. These half shells have excessive pack rust development. Recommend, measures be taken to reduce the effect of the corrosion and possible re-coating of the components.
Deficiency: maintenance- attempts were made to lubricate the existing grease points. Many points will not receive lubrication. The unit presents no recent maintenance
Starboard Trident 10,000 lb capacity unit:
The unit was inspected visually for OSHA standards compliance.
Deficiency: Boom Heel Pin- the pin at the articulating portion of the base boom. No presence of lubrication presented. The pin retaining washers are corroded beyond standards for simple washers. This condition as presented may require further investigation to determine why the pin lubrication points will not accept grease.
March 17, 2015 Deficiency: The unit turret is fixed to the rotary bearing to allow for slew action to the right and left. The upper structure and boom assembly rely on the structural connection fasteners for load capacity and safety. The fixing fasteners that are exposed to the starboard side of the ship (when unit is in storage) present exposure to the environment and exhibit corrosion. The level of corrosion presented has caused the fasteners to delaminate. This effect may drastically affect the stability of the crane when in use. It would be recommended to renew all the rotary bearing fasteners.
Deficiency: Hydraulic extensible boom- large corroded debris accumulating at the turret below the rear exit of the boom. Visual inspection of the interior of the boom presents further excessive steel pack rust and de-lamination at the interior visible portion of the boom steel structure. Further inspection would be required to confirm the condition of the box steel boom sections. Condition would be considered serious, and at the minimum would need an internal inspection for structural integrity.
Deficiency: Boom base and boom inner slide pad- the forward lower assembly consist of two slide pads and a retainer bracket. This unit has one missing slide pad and the retainer bracket If this condition is left unattended condition will degrade creating a possible unsafe condition.
Deficiency: Crane load chart- Illegible; unit does have a variable load chart. Standards require a clearly visible load chart to be presented to the operator. Unit has a Hydraulic control to further effect chart.
Deficiency: Crane controls- controls presented to the operator are not clearly indicated. Standards require all controls to be clearly marked when present to the operator.
Deficiency: Crane controls- This unit has two hydraulic controls on the operator panel. One, for the heated oil circulation; and the other for hoist capacity/speed. The operator’s panel has been upgraded to a stainless steel unit. The two hydraulic controls were not installed into the new panel, and hang down below the panel. Thus, these controls are not able to be operated properly. This condition presents an unnecessary operation condition that may at some point adversely affect the operator. If condition left unattended it may degrade to affect crane performance and safety.
Deficiency: Crane control- operators panel, the operators control for the on/off of the crane has exposed conductors from a failed cord grip at the control station. The ‘on’ light is also inoperative. Standards and the environment required single conductors to be protected by electrical conduit or similar protection method, this condition could present an unsafe electrical hazard to the operator.
Deficiency: Crane Boom Tip- lower boom tip sheave has excessive TIR at the cross shaft. The excessive TIR is most notably transverse to the axle. Indicating that the bushing / bearing has excessive wear. This may create further hazards in the case of a bearing/bushing failure.7, 15
Deficiency: Hoist winch- the hoist winch has developed an oil leak at the support plate on the hydraulic motor drive side of the unit. This can only further degrade to a larger discharge of hydraulic fluid. Hoisting standards require all hydraulic components to be maintained and no oil leaks in the system.
Deficiency: Boom Hoist upper connection point- the rod end of the boom hoist cylinder is retained by a fixing pin. The boom structure has additional backing half shells. These half shells have excessive pack rust development. Recommend, measure be taken to reduce the effect of the corrosion and possible re-coating of the components.
Deficiency: maintenance- attempts were made to lubricate the existing grease points. Many points will not receive lubrication. The unit presents no recent maintenance.
General Information:
The inspection conducted was during ships stores operation. The starboard crane was in use by ship staff. Area’s not visually inspected include the base stanchion of the crane units, the interior of the inner boom section, and hydraulic swivel below the turret. Both units were operated after ship stores operations had completed. The wire rope has been “slushed” adequately. However the coating precluded the inspection of the wire rope in its entirety.
It should be noted that the lower base section of the boom has received welding repair previously. Generally, the crane units have not received periodic maintenance lubrication and are beginning to suffer corrosion in critical areas of the structure. With attention to the fixing hardware, and steel structural components. Attention to the functions of the crane control system may require further retraining of the ship operation staff.
At this time a fully function “anti two block system” is installed on the unit. this system has lock out incorporated to allow only limited operation of the when the ATB is activated. The base components have the ability to add additional devices to provide a system that would disallow any other misuse of the units (i.e. overload control). Also, actual load measurement could be included
Recommendation Port Crane:
Corrosion…