STATEMENT OF WORK
Yoccum Sailing Center Boat Bay Heat Replacement
U.S. MERCHANT MARINE ACADEMY
KINGS POINT, NEW YORK
U.S. DEPARTMENT OF TRANSPORTATION
MARITIME ADMINISTRATION
U.S. MERCHANT MARINE ACADEMY
BACKGROUND
The United States Merchant Martine Academy (USMMA) is an agency of the Maritime
Administration (MARAD) managed by the United States Department of Transportation.
The USMMA is listed on the National Register of Historic Places. Therefore, all work shall be consistent with the Secretary of the Interior's Standards for the Treatment of Historic
Properties (36 CFR part 68) http://www.nps.gov/tps/standards/four-treatments/treatment-guidelines.pdf.
All work shall meet or exceed the standards provided in the Secretary of the Interior’s
Standards for Rehabilitation and guidelines for applying the standards published by the
National Park Service, U.S. Department of the Interior 36 CFR 67.7 - Standards for rehabilitation.
OBJECTIVE
The USMMA seeks to replace the current heating equipment for the Yoccum Sailing Center boat bay.
SCOPE
The USMMA is looking for a qualified, licensed and insured contractor to provide labor, material, transportation, tools, equipment and supervision for the replacement of the existing hot water boiler and forced air heat convectors that serve the boat servicing bay at Yoccum Sailing
Center. The selected contractor will be responsible for the following:
properly sizing, purchasing and installing a forced air heating system, to include hot air furnace and all ductwork as needed for the boat bay ensure proper sizing of existing gas service and upsize any piping as needed run all required electric circuits from the existing power supply panels. All wiring will be sized by the contractor, according to load and will be of copper stranded materials. All electrical wiring will be run in code approved conduit using steel compression fittings.
All electrical disconnects will be new, Square D heavy duty disconnects or equivalent.
ensure all new equipment will be installed according to manufactures recommendations, and should be set up to operate with one thermostat that the contractor will also supply and install.
the weather proofing of all building penetrations for piping and ductwork removal of the current hot water heating boiler, unit heaters and all associated piping
All debris will be removed from the academy grounds by the contractor. All paperwork for new equipment will be submitted to the Department of Public Works in one three ring binder, and the contractor will provide any necessary training on operation and maintenance of the new equipment for Academy maintenance staff.
DELIVERY
1. The contractor shall furnish all labor and material, transportation and supervision in the performance of all tasks detailed in this statement of work.
2. The Contractor will ensure all materials and parts are compatible with the specific unit specified in this statement of work.
3. Contractor shall ensure that all systems will be checked, tested and started.
4. All work is to conform to federal, state and local building regulations and codes.
5. Maintain a work area compliant with safety standards.
6. Area worked on shall be cleaned and secured on a daily basis.
7. Any damage to existing facilities or appurtenances shall be repaired or replaced in kind, by the contractor at no additional cost to the Government.
8. Examine existing conditions prior to any repair activities, a site visit will be scheduled to inspect the site where services are to be performed.
9. Excess material and debris shall be disposed of in accordance with local and state ordinances.
10. No vehicles shall be driven on the sidewalks or grass. Unless granted specific exception due to site access limitations. Repair of landscape, if any, will be the sole responsibility of the contractor.
11. Make every effort to minimize the impact to the daily routine of the Academy.
12. Contractors shall be licensed, bonded and insured as mandated by federal, state and local municipal regulations.
CLOSE OUT:
The contractor shall provide a signed warranty of any damage, defective material and improper workmanship on any material provided in this contract.
Materials and labor to be warranted for a minimum of one year after completion of installation, and equipment to be warranted per manufacturer.
EVALUATION CRITERIA
The quote that is determined to be the best value to the government will be awarded this procurement. The following criteria will be evaluated in determining best value;
1. Technical Approach (40%)
The Contractor will demonstrate through documentation submitted, technical expertise in performing the tasks detailed in this statement of work.
2. Past Performance (25%)
The Contractor must have worked satisfactorily for a minimum of three (3) years on projects of this type and size.
3. Price (35%)
GOVERNMENT FURNISHED PROPERTY, MATERIAL, EQUIPMENT OR
INFORMATION.
N/A
CONSIDERATIONS
• Submit schedule seven (7) days in advance of work to be accomplished for approval.
• Submit schedule showing area to be worked on, dates of work, and estimated timeline for completion of the task(s).
• Maintain communication with the COR (and immediately inform the COR of any unforeseen issues or problems that arise).
• Inform COR of any anticipated disruption in services for construction at least three (3) days in advance
PLACE OF PERFORMANCE
Contractor will perform the task at the Yoccum Sailing Center, USMMA, 300 Steamboat
Road, Kings Point, N.Y. 11024
PERIOD OF PERFORMANCE
Work is to be completed within 30 calendar days after NTP is approved. Work is to be performed during normal business hours 0700 to 1630, Monday through Friday unless approval is granted by the Contracting Officer.
ACRONYMS
ANSI American National Standards Institute
ASME (Formally known as) American Society of Mechanical Engineers
ASHRAE American Society of Heating Refrigeration and Air Conditioning Engineers
CFR Code of Federal Regulations
COR Contract Officer Representative
EPA The United States Environmental Protection Agency
IEEE The Institute of Electrical and Electronics Engineers
MARAD United States Maritime Administration
NEC National Electrical Code ANSI/NFPA 70
NEMA National Electrical Manufacturers Association
NFPA National Fire Protection Association
NTP Notice to Proceed
TBD To Be Determined
USMMA Unites States Merchant Marine Academy