IFB_Solicitation_-_NP-EVER_10(4).pdf
PDF 775 KB Posted
- Attached to
- Everglades National Park Federal contract opportunity
- Solicitation number
- DTFH71-17-B-00005
About this file
Bid Opening date is scheduled for November 17 2016 at 2 00 pm EST.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ROBO_-_NP-EVER_10(4).pdf | ||
| Report_2_Pavement.pdf | ||
| Report_4_Bridge_Inspection_5280-003P.pdf | ||
| Plans_-_NP-EVER_10(4).pdf | ||
| ADV_Bidder's_Qualifications_Form.doc | DOC document | |
| VETS-4212.pdf | ||
| Report_1_NEPA.pdf | ||
| Report_5_Bridge_Inspection_5280-004P.pdf | ||
| Report_3_Bridge_Inspection_5280-002P.pdf | ||
| FP14_Eng.pdf | ||
| Synopsis_-_NP-EVER_10(4).doc | DOC document |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION
IFB No. DTFH71- 17-B-00005
This Contract Cites
STANDARD SPECIFICATIONS (FP-14)
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
NP-EVER 10(4)
EVERGLADES NATIONAL PARK
REHABILITATION OF MAIN PARK ROAD (ROUTE 10)
AND THREE BRIDGES
Contract No.
PMIS# 186976
ADDRESS:
CONTRACTOR:
STATE Florida
COUNTIES Monroe and Miami-Dade
PARK Everglades National Park
Schedule Parking Area Roadway / Parking Area / Other Stations / SQFT Linear
Feet Route Miles
Lane Miles
A Main Park Road 827+00 To 915+00 8,800 1.67 3.34
A Main Park Road 2008+85 To 2071+95 6,310 1.20 3.40
B Main Park Road 709+00 To 827+00 11,800 2.23 4.46
C Taylor Slough Bridge # 1 105+68 To 108+19 251 0.05 0.10
C Taylor Slough Bridge # 2 117+05 To 120+81 376 0.07 0.14
C Buttonwood Canal Bridge 1989+75 To 1993+60 385 0.07 0.17
Project Length Totals 5.29 11.61
For Parking Areas, Lane Miles is calculated as SQFT / 11ft (nominal) lane
TYPE OF IMPROVEMENT
Schedules A and B. Asphalt pavement milling and patching, asphalt concrete pavement, shoulder reconditioning, pavement markings, and other miscellaneous work.
Schedule C. Inspecting concrete substructure bents and piles, repairing spalled and deteriorated concrete, cleaning and sealing concrete cracks, sealing bridge deck joints and concrete deck surfaces, and other miscellaneous work.
TABLE OF CONTENTS
Page
Notice to Bidders 1 through 2
Checklist for Bid Submission 1 through 2
*SF-1442 Solicitation, Offer, and Award 1 through 4
Bid Schedule Instructions 1 through 3
*Bid Schedule B-1 through B-5
*SF-24 Bid Bond C-1 through C-2
FEDERAL ACQUISITION REGULATION & TRANSPORTATION ACQUISITION
REGULATION SOLICITATION PROVISIONS & CONTRACT CLAUSES
Index to Federal and Transportation Acquisition Regulations 1 through 6
Representations and Certifications (OCRA online) D-1 through D-2
Instructions to Bidders E-1
*Socioeconomic Program Requirements F-1 through F-4
Minimum Wage Schedule F-5 through F-15
*General Contract Requirements G-1 through G-4
Construction Contract Requirements H-1 through H-5
Special Contract Requirements J-1 through J-22
Section K K-1 through K-3
SPECIFICATIONS On CD
Plans 1 through 53 Report 1 – NEPA (Categorical Exclusion Form) 1 through 59 Report 2 – Pavement Report 1 through 156 Report 3 – Bridge Inspection_5280-002P 1 through 23 Report 4 – Bridge Inspection_5280-003P 1 through 22 Report 5 – Bridge Inspection_5280-004P 1 through 20
* Bidder’s Qualifications Form 1 through 7
* Federal Contractor Veterans’ Employment Report VETS-4212 1 through 5
*BOLD FACED ITEMS ARE TO BE INCLUDED WITH THE BID SUBMITTAL PACKAGE
NOTICE TO BIDDERS
CONTRACT FORMAT:
Bidders should note that the format of this contract is in accordance with Federal Acquisition Regulations (FAR), promulgated by the General Services Administration (GSA), effective April 1, 1984, including all applicable revisions. Applicable FAR provisions and clauses are incorporated in this contract by reference or full text as indicated in the INDEX before the D-page in this booklet.
FAR provisions and clauses incorporated by reference can be accessed on the Internet on the GSA website at www.arnet.gov/far/. Bidders are encouraged to review the documents thoroughly before bidding.
PROPOSAL BOOKLET AND OFFER SUBMITTAL:
It is the responsibility of the Bidder to verify that this proposal is complete as listed in the Table of Contents. The Bidder is responsible for submitting all required forms and documents with the offer.
Offerors should use the Checklist for Bid Submission included in this booklet to check that their bids are complete.
CONSTRUCTION CONTRACTS:
Additional guidance is given in FAR Subpart 35.005 where the majority of the project work is complex and specialized such as restoration work, bridge painting, and proprietary construction techniques (i.e. proprietary Cintec arch strengthening.) There are exceptions and they will be reviewed on a case-by-case basis.
HAZARDOUS MATERIALS IDENTIFICATION AND MATERIAL SAFETY DATA:
As required by FAR Clause 52.223-3, Hazardous Materials Identification and Safety Data, the apparent low Offeror must submit prior to award a Material Safety Data Sheet (MSDS's) for all hazardous materials that the Offeror identifies in paragraph (b) of this clause in the D-pages of this booklet. Failure to submit MSDS's may render the Offeror ineligible for award of contract. The apparent low Offeror should submit their MSDS's within two weeks after bid opening.
FINANCING ASSISTANCE: Minority, Women-owned, and Disadvantaged Business Enterprises (DBE's). The Department of Transportation (DOT) offers working capital financing assistance for transportation related contracts. DOT's Short-Term Lending Program (STLP) offers lines of credit to finance accounts receivable. Maximum line of credit is $750,000 with interest at the prime rate. For further information, call (800) 532-1169 or 202-366-1930. Internet address: http://osdbuweb.dot.gov
INTERNET BASED DATA BASES - REQUIRED INPUT:
According to the FAR Subpart 4.1102 contractors MUST be registered in System for Award Management (SAM) prior to contract award. Access the following web site to register:
www.sam.gov
According to the FAR Subpart 4.1201 contractors MUST complete their Online Annual Representations and Certifications Application prior to contract award online at http://sam.gov/.
According to the FAR Subpart 22.1302 (b) contractors and sub-contractors MUST complete the required Annual Vets-4212 Form in order to be eligible for a contract award. It can be completed on-line at http://www.dol.gov/vets/vets4212.htm. 2015 VETS-4212 Filing Cycle Effective August 1, 2015 and ends on September 30, 2015, Customers will no longer be able to electronically file a VETS-4212 Report. Customers may still file, but must first download the form from the VETS website http://www.dol.gov/vets/vets4212.htm, fill out the form and mail or email it to: VETS-4212 Service Center C/O Department of Labor National Contact Center (DOL-NCC)15000 Conference Center Drive, Suite B0132 Chantilly, VA 20151(866) 237-0275 Or email to: vets100-customersupport@dolncc.dol.gov
PAYMENT:
Offerors are advised to review the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP), subsection 109.05, concerning direct and indirect payment included under a pay item in the bid schedule.
NOTICE TO BIDDERS
PROGRESS PAYMENTS:
ALL payments will be made via Electronic Funds Transfer (EFT) as such; the payment information in the CCR must be accurate in order for contractors' invoices to be considered proper invoices for the purpose of prompt payment under DOT contracts. Contractors must input and maintain (update as necessary) their EFT information in the CCR database. Offerors are advised that under FAR Clause 52.232-5, Payments Under Fixed Price Construction Contracts, upon request, progress payments will include premiums paid by the Contractor to obtain performance and payment bonds as required under this contract. These payments shall not be made in addition to the contract price. As specified in the FP, “Section 151 - MOBILIZATION", payments for performance and payment bond premiums shall be included in mobilization.
WELFARE-TO-WORK INITIATIVE:
The President’s Welfare Reform Bill was initiated to assist welfare recipients and hopefully aid welfare recipients to find gainful employment. In support of this bill, Contractors are encouraged to hire welfare recipients whenever possible and to use welfare recipients in performance of duties on Government contracts.
INCREASING SEAT BELT USE IN THE UNITED STATES:
The President’s Executive Order 13043 dated April 16, 1997, was issued to increase the use of seat belts in the United States. In support of this Order, contractors and subcontractors are encouraged to adopt and enforce on-the-job seat belt policies for their employees when operating company-owned, rented, or personally owned vehicles.
OBTAINING BID DOCUMENTS:
Bid documents will not be mailed. All bid documents are available for direct download from the Federal Business Opportunities (FBO) website: http://www.fbo.gov/. Contractors are encouraged to register on the FBO website (for this specific project) in order to receive Email Notifications automatically when a document is added or updated for this specific project. All questions about this construction project must be emailed to the following address:
eflhd.contracts@dot.gov.
THE CONTRACTOR IS SOLELY RESPONSIBLE FOR MONITORING THE WEB PAGES
NOTED ABOVE FOR ALL CHANGES TO THE SOLICITATION AND ACTING ON SAID
CHANGES.
PLEASE NOTE: for security reasons, individuals requiring access to all government buildings must present a valid photo ID and be escorted to their destination by a Government employee. All visitors attending bid openings are urged to arrive at least 1 hour prior to schedule bid opening. All visitors must register with the receptionist in Room 100. A Government employee will collect all bids. Prior to bid opening, a Government employee will escort all bidders to the bid opening. Unescorted visitors will be denied entry and no exceptions will be made.
CHECKLIST FOR BID SUBMISSION
The following is a checklist of items included in the proposal/bid package that are required to be completed and returned (or filled in on-line) to the address in Block 7 of the Standard Form 1442, Solicitation, Offer, and Award (page 1). This checklist is for informational purposes only and is not required to be filled out by the bidder. Failure to submit a complete bid may be cause to reject your bid.
1. Bid Envelope:
a. Addressed as shown in Block 7 of SF-1442
b. In lower left corner, indicate the following: Solicitation No., Project Name & Number, mail to room
105, if proposals are hand delivered bring them to Reception Area Room 100 and a Contract Specialist will be notified.
2. Standard Form 1442: Solicitation, Offer and Award
a. Block 14: Name and Address of Bidder.
b. Block 15: Telephone Number of Bidder.
c. Block 16: Remittance Address if different from Block 14.
d. Block 19: All Amendments Acknowledged, with dates of Amendments.
e. Block 20: Bid is signed and dated.
3. Bid Schedule - (Pages B-1 through B-5)
a. Unit bid price and bid amount provided for each pay item in numbers.
b. Corrections initialed.
4. Standard Form 24, Bid Bond (Pages C-1 through C-2) (Required if bid guarantee is bid bond)
a. Date executed
b. Legal name and address of bidder.
c. Type of organization.
d. State of incorporation (if applicable).
e. Name and business address of Treasury approved surety.
f. Penal sum of bond (not less than 20% of bid total).
g. Bid identification.
h. Signature of Bidder
i. Seal, if corporation
j. Signature of Surety
k. Seal, if corporation
BIDS RECEIVED WITHOUT A VALID BID BOND WILL BE REJECTED.
5. Power of Attorney.
a. Dated on or before execution date of bond
b. Power has original signature of surety, or is embossed with surety's seal in the certification section
BIDS RECEIVED WITHOUT A VALID POWER OF ATTORNEY WILL BE REJECTED.
CHECKLIST FOR BID SUBMISSION
6. Bidder's Qualifications form (provided separately as part of the Bid Documents Package).
Form completed, signed and submitted with bid
THE FOLLOWING THREE ITEMS IF NOT SUBMITTED WITH THE BID; MUST
BE COMPLETED ELECTRONICALLY PRIOR TO CONTRACT AWARD.
7. System for Award Management (SAM): The Contractor is currently registered in the Internet-Based SAM database at http://www.sam.gov. If contractor elects to not have SAM viewed by public they must submit a copy with Bidder’s Qualification Package.
8. Online Representations and Certifications Application: The Contractor's Representations and Certifications have been input online via the Internet-Based electronic database at http://sam.gov.
9. VETS – 4212 Reporting: The Contractor has completed the annual Internet-Based reporting requirement online at http://www.dol.gov/vets/vets4212.htm.
VETS 4212 Filing Cycle Effective August 1, 2015 and ends on September 30, 2015, Customers will no longer be able to electronically file a VETS 4212 Report. Customers may still file, but must first download the form from the VETS website http://www.dol.gov/vets/programs/fcp/vets-4212.pdf, fill out the form and mail or email it to: vets-4212 Service Center, In Care of: Department of Labor National Contact Center (DOL-NCC), 15000 Conference Center Drive, Suite B0132 Chantilly, VA 20151 (866) 237-0275 Or email to: VETS4212-customersupport@dol.gov.
NOTE: THE CONTRACTOR IS FULLY RESPONSIBLE TO VERIFY THAT ALL
DATA IN THE ABOVE DATABASES IS CORRECT EACH TIME A BID PACKAGE IS
SUBMITTED. FAILURE TO PROPERLY INPUT AND/OR UPDATE YOUR DATA
PRIOR TO CONTRACT AWARD MAY CAUSE THE BID TO BE REJECTED.
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
EFL16PP107
Federal Highway Administration
Eastern Federal Lands Highway Div.
Acquisitions Office 21400 Ridgetop Circle
EFLHD-AC
Sterling VA 20166-6511
See Block 7
Christopher Long eflhd.contracts@dot.gov
SEE BLOCK 10
x
10/19/2016
DTFH7117B00005
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
This Invitation for Bids is for the Everglades National Park, Project NP-EVER 10(4), located in Monroe and Miami-Dade Counties, Florida in strict accordance with the
Solicitation/Contract instructions, notices, clauses, provisions, items listed below, and for the quantities of work actually performed at the unit prices as bid in the Bid Schedule, including all applicable Federal, State, and local taxes.
FP - Standard Specification for Construction of Roads & Bridges on Federal Highway
Projects.
Bid Schedule, Section B - pages B-1 through B-5.
Special Contract Requirements, Section J - pages J-1 through J-22.
Plans, Sheets 1 through 53.
Report 1 – NEPA (Categorical Exclusion Form), pages 1 through 59.
Report 2 – Pavement Report, pages 1 through 156.
Report 3 – Bridge Inspection_5280-002P, pages 1 through 23.
Report 4 – Bridge Inspection_5280-003P, pages 1 through 22.
Report 5 – Bridge Inspection_5280-004P, pages 1 through 20.
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 calendar days and complete it within ________________ ________________ calendar days after receiving
Continuation Sheet, Block 11
11/17/2016
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
�����./�0::/303�#73//5�20�9/3:03;�2./�=03D�3/AB83/>�#2�2./�9384/5�59/48:8/>�$/60=�81�523842�#4403>#14/�=82.�2./�2/3;5�0:�2.85�5068482#2801?�8:�2.85�0::/3�85�#44/92/>
$@�2./��0E/31;/12�81�=382817�=82.81�--------------------�4#6/1>#3�>#@5�#:2/3�2./�>#2/�0::/35�#3/�>B/����������
| � | %(�� |
| �) | �� |
| �� | ����� |
| � | �� |
| ����� ���������� | ���� | ����� |
| � | �� |
�����./�0::/303�#73//5�20�:B3185.�#1@�3/AB83/>�9/3:03;#14/�#1>�9#@;/12�$01>5�
0��#������ ��2�
| ����� | ������ | � |
| H���� | �� |
������� �)4��
3�2���%����
| �����" | ��� � ����� | ��� |
| ����������� | �� |
| ��" ���� | ���������� | |
| �������� | ����� | "��� |
����������3 4��� '5 '6 �--����7��
3�2���%���
| �� | ������ | �� | ������ | ������ | � |
| H���� | �� |
������� )4������ �$���� �� �4������
����2�� #��0 ��2�����
�)��������� )�&4'��������������� ������������ &4'���������������
�"������&��*���G��'����, Block 26
Federal Highway Administration Eastern Federal Lands Highway Division ATTN: Construction Office 21400 Ridgetop Circle Sterling, VA 20166-6511
Federal Highway Administration Eastern Federal Lands Highway Division A/P Branch, AMZ-150 P.O. Box 25710 or E-MAIL
9-AMC-AMZ-EFLINVOICES@FAA.GOV
Oklahoma City, OK 73125
EFLHD-CO
peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text
CONTINUATION OF SF 1442
Block 2:
This project is RESTRICTED - Bids will be accepted from Certified Small Business Concerns only.
This procurement falls under North American Industry Classification System (NAICS) code 237310 - Highway, Street, and Bridge Construction (see FAR Subpart 19.10)
Facsimile and electronic bids will not be accepted.
PHYSICAL DATA AVAILABLE FOR REVIEW
1. Manual on Uniform Traffic Control Devices for Streets and Highways, 2009 Edition, published by the Federal Highway Administration. http://mutcd.fhwa.dot.gov.
2. National Park Service Sign Manual, revised - January 1988, United States Department of the Interior. http://flh.fhwa.dot.gov/resources/design/library.
3. Report 1 – NEPA (Categorical Exclusion Form)
4. Report 2 – Pavement Report
5. Report 3 – Bridge Inspection_5280-002P
6. Report 4 – Bridge Inspection_5280-003P
7. Report 5 – Bridge Inspection_5280-004P
Block 9:
In accordance with FAR Provision 52.236-27, Site Visit, a Government representative can be available to show the project to prospective bidders. All requests for site visits see Section E of the solicitation and e-mail all questions concerning this construction project to the following e-mail address eflhd.contracts@dot.gov. Interested parties must provide the Solicitation Number and the relevant project name with all requests and questions.
Block 11:
Maximum time allowed for the contract if Schedules A, B, and C are awarded at the same time:
All work must be completed by no later than December 22, 2017.
Maximum time allowed for each schedule of work if awarded separately:
If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 230 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.
If Schedule B (Government Option 1) is exercised after the award of the original contract, the Performance period to complete all Schedule B work will be 120 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.
CONTINUATION OF SF 1442
If Schedule C (Government Option 2) is exercised after the award of the original contract, the performance period to complete all Schedule C work will be 90 calendar days and will start on the effective date of Schedule C’s Notice to Proceed.
Notice to Proceed will be issued within 30 days following receipt of acceptable performance and payment bonds. (Actual Notice to Proceed date will be 10 days from issuance or the date specified in the Notice.) Bidders are to assume that the award of the contract and approval of the Contractor’s Performance and Payment Bonds may result in the start of construction activities to be no earlier than March 2017. See Subsection 108.01 of the SCR’s for additional details.
See other applicable information in the COMPLETION OF WORK section of the “B Pages - Bid Schedule Instructions.” Work restrictions can be found in SCR Sections 108 and 156.
Block 12A:
Furnish performance and payment bonds in accordance with FAR Clause 52.228-15.
Block 13:
A bid guarantee in the amount of not less than 20 percent of the bid price or $3 million, whichever is less, is required with this bid. If the bidder fails to provide the required bid guarantee, such failure may require rejection of the bid. Reference FAR Provision 52.228-1, Bid Guarantee.
Block 17:
Amounts should be completed as follows:
Schedule A - $ Schedule B (Option 1) - $ Schedule C (Option 2) - $
Other:
The estimated price is expected to fall within the price range of $1,000,000 to $5,000,000.
Responsibility of bidders shall be evaluated in accordance with the information provided on the Bidder's Qualification Form, which can be downloaded from FHWA web site.
FP-14 versions can be downloaded at the FHWA web site. FHWA web site is http://flh.fhwa.dot.gov/resources/specs/ then click on “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects”.
BID SCHEDULE INSTRUCTIONS
PROJECT: NP-EVER 10(4)
BIDDERS PLEASE NOTE: Before preparing the bid, carefully read the Instructions to
Bidders. While preparing the bid, comply with the following:
COMPLETING THE BID SCHEDULE
Complete the Bid Schedule(s) by handwriting in ink or typing. Specify a Unit Bid Price, in figures with cents to only two decimal places, for each pay item in the Unit Bid Price column for which a quantity is given. Do not enter or tender a Unit Bid Price for any pay item for which no estimated quantity appears in the Bid Schedule. Determine the products of the respective unit prices and quantities, and show them, in figures, in the Amount Bid column. If a Unit Bid Price and Amount Bid have been inserted by the Government for a pay item, do not change the Unit Bid Price and Amount Bid for the pay item. Determine the Bid Total by adding the amounts of the several items, and show in the block provided on Page B-2 for Schedule A, Page B-3 for Schedule B, and Page B-4 for Schedule C. In case of multiplication errors, the Amount Bid for the item will be based on the Unit Bid Price.
To be eligible for award, bidders must submit prices for each pay item.
Review Subsection 109.05 of the FP (standard specifications book) regarding scope of payment for direct and indirect payment work.
Fill in the Bid Total(s) as directed on the Bid Summary page. Fill in the Evaluation Total Price of Project in the space provided on the Bid Summary page.
The amount in Block 17 should be completed as follows:
Schedule A - $ .
Schedule B - $ .
Schedule C - $ .
SCHEDULES OF WORK
The Bid Schedule is comprised of the following separate schedules and options of work:
Schedule A (Base Contract) - Pages B-1 thru B-2
Schedule B (Government Option 1) - Page B-3
Schedule C (Government Option 2) - Page B-4
The Government will award the project as a Base Contract (Schedule A) with the option to award Schedule B (Government Option 1) and Schedule C (Government Option 2); see FAR Clauses 52.217-4 and 52.217-5.
The purpose of the multiple schedules and options is to give the Government maximum flexibility in completing the project in a timely manner and at a cost-effective price, by proper utilization of available funds and upon receipt of all required funding. If complete funding is in place at the time of award of Schedule A (Base Contract), the Government may award Schedule B (Government Option 1) and Schedule C (Government Option 2) at that time. If funding for Schedules B and C (Government Options 1 and 2) is received after award of Schedule A (Base Contract), the Government has the right to exercise Schedules B and C (Government Options 1 and 2) at the unit prices bid according to the following schedule:
Schedule B (Government Option 1): No later than the contract completion date for Schedule A (Base Contract).
Schedule C (Government Option 2): No later than March 1, 2017.
COMPLETION OF WORK
The Government has estimated the number of calendar days necessary to complete all contract work from the effective date of the Notice To Proceed to contract completion for the various contract award scenarios. The maximum number of calendar days allowed (i.e., the contact performance period) is shown in Block 11 of the SF-1442 and described below.
If the Government awards the contract as Schedules A + B + C, the performance period to complete all contract work will be as stated in Subsection 108.01 of the Special Contract Requirements (J Pages), which specifies all work must be completed by no later than December 22, 2017.
If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 230 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.
If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 120 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.
If Schedule C (Government Option 2) is exercised after the award of the original contract, the performance period to complete all Schedule C work will be 90 calendar days and will start on the effective date of Schedule C’s Notice to Proceed.
In developing a construction schedule to determine the number of calendar days, the Government considered and included the work limitations shown in Sections 108 and 156 of the FP and Special Contract Requirements (SCR’s). Specific work limitations may be (but are not limited to): National legal holidays, weekends, rush hours, night work, specified no work periods, work or traffic control phasing, etc. The Government also considered those work items that are weather sensitive and when those work items will be performed. Specific work items are (but not limited to): those that require a minimum ambient air temperature (asphalt paving and surface treatment, pavement striping, stone masonry, etc); those that require maintaining a minimum surface temperature (concrete pavement, structural concrete, painting, etc); and those that have specific planting seasons (turf establishment, sod, trees, plants, etc). The Government also considered time required for preparing material and drawing submittals, and the allowable Government review times for those submittals (Subsection 104.03 of the FP and SCR’s).
Bidders are to assume that the award of the contract and approval of the Contractor’s Performance and Payment Bonds (see Block 12a of the SF-1442 and FAR Clause 52.228-
15) may result in the start of construction activities to be no earlier than March 2017. See Subsection 108.01 of the SCR’s for additional details.
BASIS FOR AWARD
The contract will be awarded to the responsive, responsible bidder with the lowest Evaluation Total Price of Project, which is defined as:
Schedule A (Base Contract) Bid Total + Schedule B (Government Option 1) Bid Total + Schedule C (Government Option 2) Bid Total.
B I D S C H E D U L E Schedule A
Project No: NP-EVER 10(4)
Name: Everglades National Park
Item No. Quantity Unit Unit Price Amount
15101-0000
Line A0020 ALL LPSM $
15201-0000
Line A0040 ALL LPSM $
15401-0000
Line A0060 ALL LPSM $
20301-2400
Line A0080 30 EACH $ $
20302-2600
Line A0100 1,500 LNFT $ $
20303-1600
Line A0120 170 SQYD $ $
30101-0000
Line A0140 980 TON $ $
30302-2000
Line A0160 18,000 LNFT $ $
40101-0600
Line A0180 5,800 TON $ $
41301-0000
Line A0200 48,000 SQYD $ $
41801-1000
Line A0220 390 SQYD $ $
41801-3000
Line A0240 35 SQYD $ $
63304-0900
Line A0260 300 SQFT $ $
63401-1500
Line A0280 27,500 LNFT $ $
63401-1600
Line A0300 15,000 LNFT $ $
63406-0200
Line A0320 500 EACH $ $
RAISED PAVEMENT MARKER, NON-PLOWABLE, BI-DIRECTIONAL REFLECTIVE
MOBILIZATION
CONSTRUCTION SURVEY AND STAKING
CONTRACTOR TESTING
REMOVAL OF SIGN
REMOVAL OF PAVEMENT MARKINGS
REMOVAL OF PAVEMENT, ASPHALT
SIGNS, ALUMINUM PANELS, TYPE 3 SHEETING
PAVEMENT MARKINGS, TYPE H, SOLID
PAVEMENT MARKINGS, TYPE H, BROKEN
AGGREGATE BASE (LIMEROCK)
SHOULDER RECONDITIONING
ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH NOMINAL MAXIMUM SIZE
AGGREGATE, 0.3 TO <3 MILLION ESAL, PG 64-22 (TYPE III PAVEMENT ROUGHNESS)
ASPHALT PAVEMENT MILLING
ASPHALT CONCRETE PAVEMENT PATCH, TYPE 1
ASPHALT CONCRETE PAVEMENT PATCH, TYPE 3
B-1 (Base Contract)
Schedule A
Project No: NP-EVER 10(4)
Name: Everglades National Park
Item No. Quantity Unit Unit Price Amount
63502-1300
Line A0340 40 EACH $ $
63503-0300
Line A0360 70 LNFT $ $
63503-0700
Line A0380 46,000 LNFT $ $
63504-1000
Line A0400 390 SQFT $ $
63506-0500
Line A0420 700 HOUR $ $
63708-0000
Line A0440 11 MO $ $
64501-0000
Line A0460 ALL LPSM $
CELLULAR PHONE SERVICE
LOCATE UTILITIES
TEMPORARY TRAFFIC CONTROL, DRUM
TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
TEMPORARY TRAFFIC CONTROL, FLAGGER
B-2 (Base Contract)
25.70 17,990.00
Schedule Total:__________
Submitted by:___________
Schedule B
Project No: NP-EVER 10(4)
Name: Everglades National Park
Item No. Quantity Unit Unit Price Amount
15101-0000
Line B0020 ALL LPSM $
15201-0000
Line B0040 ALL LPSM $
15401-0000
Line B0060 ALL LPSM $
30101-0000
Line B0080 1,300 TON $ $
30302-2000
Line B0100 24,500 LNFT $ $
40101-0600
Line B0120 3,600 TON $ $
41301-0000
Line B0140 29,500 SQYD $ $
63401-1500
Line B0160 29,000 LNFT $ $
63401-1600
Line B0180 10,000 LNFT $ $
63406-0200
Line B0200 320 EACH $ $
63503-0700
Line B0220 14,700 LNFT $ $
63506-0500
Line B0240 700 HOUR $ $
MOBILIZATION
CONSTRUCTION SURVEY AND STAKING
CONTRACTOR TESTING
AGGREGATE BASE (LIMEROCK)
SHOULDER RECONDITIONING
ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH NOMINAL MAXIMUM SIZE
AGGREGATE, 0.3 TO <3 MILLION ESAL, PG 64-22 (TYPE III PAVEMENT ROUGHNESS)
ASPHALT PAVEMENT MILLING
PAVEMENT MARKINGS, TYPE H, SOLID
PAVEMENT MARKINGS, TYPE H, BROKEN
RAISED PAVEMENT MARKER, NON-PLOWABLE, BI-DIRECTIONAL REFLECTIVE
TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
TEMPORARY TRAFFIC CONTROL, FLAGGER
(Government Option 1)
25.70 17,990.00
B-3
Schedule Total:___________
Submitted by:____________
Schedule C
Project No: NP-EVER 10(4)
Name: Everglades National Park
Item No. Quantity Unit Unit Price Amount
15101-0000
Line C0020 ALL LPSM $
15401-0000
Line C0040 ALL LPSM $
20301-2400
Line C0060 8 EACH $ $
20302-2600
Line C0080 2,200 LNFT $ $
55220-0000
Line C0100 12 SQYD $ $
55222-0000
Line C0120 ALL LPSM $
55224-0000
Line C0140 4,440 SQYD $ $
55225-0000
Line C0160 80 LNFT $ $
55225-0000
Line C0180 280 LNFT $ $
55235-0000
Line C0200 260 LNFT $ $
63304-0900
Line C0220 40 SQFT $ $
63401-0500
Line C0240 2,800 LNFT $ $
63406-0200
Line C0260 30 EACH $ $
63506-0500
Line C0280 500 HOUR $ $
MOBILIZATION
CONTRACTOR TESTING
REMOVAL OF SIGN
REMOVAL OF PAVEMENT MARKINGS
REPAIR CONCRETE (SUBSTRUCTURE)
REPAIR CONCRETE (SUPERSTRUCTURE)
RAISED PAVEMENT MARKER, NON-PLOWABLE, BI-DIRECTIONAL REFLECTIVE
TEMPORARY TRAFFIC CONTROL, FLAGGER
SEAL CONCRETE SURFACE
CLEAN AND RESEAL JOINTS (LOW MODULUS SILICONE)
CLEAN AND RESEAL JOINTS (HOT APPLIED JOINT SEALANT)
EXPANSION JOINTS (COMPRESSION JOINT SEAL)
SIGNS, ALUMINUM PANELS, TYPE 3 SHEETING
PAVEMENT MARKINGS, TYPE C, SOLID
(Government Option 2)
25.70 12,850.00
B-4
Schedule Total:____________
Submitted by:_____________
B - 5
BID SUMMARY
Project NP-EVER 10(4)
(1) Schedule A (Base Contract) Bid Total (from Page B-2) = (1) $____________________
(2) Schedule B (Government Option 1) Bid Total (from Page B-3) = (2) $____________________
(3) Schedule C (Government Option 2) Bid Total (from Page B-4) = (3) $____________________
Total Price of Project (for evaluation purposes only)
EVALUATION TOTAL PRICE OF PROJECT = (1) + (2) + (3) $____________________
Maximum Time Allowed for the Contract if Schedules A, B, and C are Awarded at the Same Time
If the Government awards the contract as Schedules A + B + C, the performance period to complete all contract work will be as stated in Subsection 108.01 of the Special Contract Requirements (J Pages), which specifies all work must be completed by no later than December 22, 2017.
Maximum Time Allowed for Each Schedule of Work if Awarded Separately
If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 230 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.
If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 120 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.
If Schedule C (Government Option 2) is exercised after the award of the original contract, the performance period to complete all Schedule C work will be 90 calendar days and will start on the effective date of Schedule C’s Notice to Proceed.
CONTRACT CLAUSES INDEX
FEDERAL ACQUISITION REGULATION (FAR) TRANSPORTATION ACQUISITION REGULATION (TAR)
(Updated thru FAC 2005-91 on 09/30/2016)
FAR & TAR CLAUSES INCORPORATED BY REFERENCE
CLAUSE TITLE DATE REMARKS
52.202-1 DEFINITIONS Nov-13 52.203-3 GRATUITIES Apr-84 52.203-5 COVENANT AGAINST CONTINGENT FEES May-14 52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT Sep-06 52.203-7 ANTI-KICKBACK PROCEDURES May-14 52.203-8 CANCEL & RECOVER OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY May-14 52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY May-14 52.203-11 CERTIFICATION AND DISCLOSURE REGARDING PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACT Sep-07 52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS Oct-10 52.203-13 CONTRACTOR CODE OF BUSINESS ETHICS AND CONDUCT Oct-15 52.203-14 DISPLAY OF HOTLINE POSTER(S) Oct-15 52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT PAPER May-11 52.204-7 SYSTEM FOR AWARD MANAGEMENT Jul-13 Contractor Mandatory Internet Data Input 52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS Oct-15 Contractor Mandatory Internet Data Input 52.204-14 SERVICE CONTRACT REPORTING REQUIREMENTS Jan-14 Contractor Mandatory Internet Data Input 52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING Jul-15 If applicable 52.204-17 OWNERSHIP OR CONTROL OF OFFEROR Jul-16 If applicable 52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE Jul-16 If applicable 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS Jun-16
52.209-6
PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH CONTRACTORS
DEBARRED, SUSPENDED OR PROPOSED FOR DEBARMENT Oct-15
52.209-11
REPRESENTATION BY CORPORATIONS REGARDING DELINQUENT TAX LIABILITY OR A FELONY
CONVICTION UNDER ANY FEDERAL LAW Feb-16
52.214-5 SUBMISSION OF BIDS Mar-97 If applicable 52.214-19 CONTRACT AWARD -- SEALED BIDDING-CONSTRUCTION Aug-96 If applicable 52.214-26 ALT 1 AUDIT AND RECORDS -- SEALED BIDDING (ALT 1 - (MAR 09)) Oct-10 If applicable 52.214-27 PRICE REDUCTION FOR DEFECTIVE COST OR PRICING DATA - MODIFICATIONS - SEALED BIDDING Aug-11 52.214-28 SUBCONTRACTOR COST OR PRICE DATA -- MODIFICATIONS--SEALED BIDDING Oct-10 52.214-29 ORDER OF PRECEDENCE - SEALED BIDDING Jan-86 52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE Apr-91 52.214-35 SUBMISSION OF OFFERS IN THE U.S. CURRENCY Apr-91 52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE Nov-11 52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS Oct-14 52.219-14 LIMITATIONS ON SUBCONTRACTING Nov-11 52.219-16 LIQUIDATED DAMAGES - SUBCONTRACTING PLAN Jan-99
52.252-2 Clauses Incorporated By Reference (Feb 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. The full text of a clause may be accessed electronically at this address: www.arnet.gov/far/
(End of Clause)
(Updated thru FAC 2005-91 on 09/30/2016)
52.219-29 NOTICE OF SET-ASIDE FOR, OR SOLE SOURCE AWARD TO, ECONOMICALLY DISADVANTAGES WOMEN- OWNED SNALL BUSINESS CONCERNS Dec-15
52.219-30 NOTICE OF SET-ASIDE FOR, OR SOLE SOURCE AWARD TO, WOMEN-OWNED SMALL BUSINESS CONCERNS ELIGIBLE UNDER THE WOMEN-OWNED SMALL BUSINESS PROGRAM Dec-16
52.222-3 CONVICT LABOR Jun-03 52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS -- OVERTIME COMPENSATION May-14 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS - SECONDARY SITE OF THE WORK May-14 52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS May-14 Contractor Mandatory Wage Rates Posting 52.222-7 WITHHOLDING OF FUNDS May-14 52.222-8 PAYROLLS AND BASIC RECORDS May-14 Contractor Weekly Payroll Submittals 52.222-9 APPRENTICES AND TRAINEES Jul-05 52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS Feb-88 52.222-11 SUBCONTRACTS (LABOR STANDARDS) May-14 52.222-12 CONTRACT TERMINATION -- DEBARMENT May-14 52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS AND RELATED REGULATIONS May-14 52.222-14 DISPUTES CONCERNING LABOR STANDARDS Feb-88 52.222-15 CERTIFICATION OF ELIGIBILITY May-14 52.222-19 CHILD LABOR - COOPERATION WITH AUTHORITIES AND REMEDIES Feb-16 52.222-21 PROHIBITION OF SEGREGATED FACILITIES Feb-99 52.222-26 EQUAL OPPORTUNITY Sep-16 52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION Apr-15 52.222-35 EQUAL OPPORTUNITY FOR SPECIAL DISABLED VETERANS, VETERANS OF THE VIETNAM ERA, & OTHER EL Oct-15 52.222-36 AFFIRMATIVE ACTION FOR WORKERS WITH DISABILITIES Jul-14 52.222-37 EMPLOYMENT REPORTS ON VERTERANS Feb-16 52.222-38 COMPLIANCE WITH VETERANS' EMPLOYMENT REPORTING REQUIREMENTS Feb-16 Contractor Annual Mandatory Reporting Requirement 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT Mar-15 52.222-50 COMBATING TRAFFICKING IN PERSONS Mar-15 If applicable 52.222-55 MINIMUM WAGES UNDER EXECUTIVE ORDER 13658 Dec-15 52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION CONTRACT Sep-13 http://www.biopreferred.gov 52.223-5 POLLUTION PREVENTION AND RIGHT TO KNOW INFORMATION May-11 52.223-6 DRUG-FREE WORKPLACE May-01 Contractor Annual Contractor Reporting Reqt 52.223-10 WASTE REDUCTION PROGRAM May-11 52.223-17 AFFIRMATIVE PROCUREMENT OF EPA-DESIGNATED ITEMS IN SERVICE AND CONSTRUCTION CONTRACTS May-08 Mandatory 52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING Aug-11 52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES Jun-08 52.227-1 AUTHORIZATION AND CONSENT Dec-07 52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT Dec-07 52.227-4 PATENT INDEMNITY-CONSTRUCTION CONTRACTS Dec-07 52.227-14 RIGHTS IN DATA - GENERAL May-14 52.227-17 RIGHTS IN DATA - SPECIAL WORKS Dec-07 52.228-1 BID GUARANTEE Sep-96 52.228-2 ADDITION BOND SECURITY Oct-97 Contractor Submittal Requirement 52.228-5 INSURANCE - WORK ON A GOVERNMENT INSTALLATION Jan-97 52.228-11 PLEDGES OF ASSETS Jan-12 52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS May-14 52.228-14 IRREVOCABLE LETTER OF CREDIT Nov-14 Contractor Submittal Requirement 52.228-15 PERFORMANCE AND PAYMENT BONDS - CONSTRUCTION Oct-10 52.229-2 NORTH CAROLINA STATE AND LOCAL SALES AND USE TAX Apr-84 52.229-3 FEDERAL, STATE, AND LOCAL TAXES Feb-13 52.230-2 COST ACCOUNTING STANDARDS Oct-15 If applicable http://www.biopreferred.gov/
(Updated thru FAC 2005-91 on 09/30/2016)
52.230-3 DISCLOSURE AND CONSISTENCY OF COST ACCOUNTING PRACTICES Oct-15 If applicable 52.230-6 ADMINISTRATION OF COST ACCOUNTING STANDARDS Jun-10 Contractor Submittal Requirement 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS May-14 52.232-13 NOTICE OF PROGRESS PAYMENTS Apr-84 52.232-16 PROGRESS PAYMENT Apr-12 52.232-17 INTEREST May-14 52.232-18 AVAILABILITY OF FUNDS Apr-84 52.232-23 ASSIGNMENT OF CLAIMS May-14 52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS May-14 52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER - SYSTEM FOR AWARD MANAGEMENT Jul-13 52.233-1 ALT 1 DISPUTES (ALT-1, DEC-91) May-14 52.233-3 PROTEST AFTER AWARD Aug-96 52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM Oct-04 52.236-2 DIFFERING SITE CONDITIONS Apr-84 52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK Apr-84 52.236-5 MATERIAL AND WORKMANSHIP Apr-84 52.236-6 SUPERINTENDENCE BY THE CONTRACTOR Apr-84 52.236-7 PERMITS AND RESPONSIBILITIES Nov-91 52.236-8 OTHER CONTRACTS Apr-84 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES & IMPROVEMENTS Apr-84 52.236-10 OPERATIONS AND STORAGE AREAS Apr-84 52.236-11 USE AND POSSESSION PRIOR TO COMPLETION Apr-84 52.236-12 CLEANING UP Apr-84 52.236-13 ACCIDENT PREVENTION Nov-91 Contractor Submittal Requirement 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS Apr-84 52.236-17 LAYOUT OF WORK Apr-84 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION Feb-97 52.236-26 PRECONSTRUCTION CONFERENCE Feb-95 52.242-13 BANKRUPTCY Jul-95 52.242-14 SUSPENSION OF WORK Apr-84 52.243-4 CHANGES Jun-07 If applicable 52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS Sep-16 52.245-2 GOVERNMENT PROPERTY INSTALLATION OPERATION SERVICES Apr-12 52.246-12 INSPECTION OF CONSTRUCTION Aug-96 52.246-21 WARRANTY OF CONSTRUCTION Mar-94 52.248-3 ALT 1 VALUE ENGINEERING - CONSTRUCTION (ALT-1, APR-84) Oct-15 52.249-2 ALT 1 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED PRICE) (ALT-I, Sep-96) Apr-12 52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) Apr-84 52.253-1 COMPUTER GENERATED FORMS Jan-91
TAR CLAUSES INCORPORATED BY REFERENCE
1252.211-70 INDEX FOR SPECIFICATIONS Apr-05 1252.242-73 CONTRACTING OFFICERS TECHNICAL REPRESENTATIVE Oct-94
FAR & TAR PROVISIONS INCORPORATED BY REFERENCE
52.217-3 EVALUATION EXCLUSIVE OF OPTION Apr-84 52.217-4 EVALUATION OF OPTIONS EXERCISED AT TIME OF CONTRACT AWARD Jun-88 52.217-5 EVALUATION OF OPTIONS Jul-90 52-217-7 OPTION FOR INCREASED QUANTITY -- SEPARATELY PRICED LINE ITEM Mar-89
(Updated thru FAC 2005-91 on 09/30/2016)
FAR & TAR CLAUSES INCORPORATED BY FULL TEXT
CLAUSE TITLE DATE SECTION SECTION TYPE REMARKS
52.203-17
CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO INFORM
EMPLOYEES OF WHISTELBLOWER RIGHTS Apr-14 G GEN'L CONTRACT REQS.
52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS Jul-13 G GEN'L CONTRACT REQS. If Applicable 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK Apr-84 H CONSTR. CONTRACTS REQS Government Fill In 52.211-12 LIQUIDATED DAMAGES - CONSTRUCTION Sep-00 H CONSTR. CONTRACTS REQS Government Fill In 52.211-18 VARIATION IN ESTIMATED QUANTITY Apr-84 H CONSTR. CONTRACTS REQS
52.222-23
NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT
OPPORTUNITY FOR CONSTRUCTION Feb-99 F SOCIOECON PROG REQS Contractor Reporting Reqs
52.223-3 ALT I HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA (ALT-I, JUL-95) Jan-97 G GEN'L CONTRACT REQS. Contractor Submittal Reqs 52.223-4 RECOVERED MATERIAL CERTIFICATION May-08 G GEN'L CONTRACT REQS. Contractor Submittal Reqs 52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA DESIGN ITEMS May-08 G GEN'L CONTRACT REQS. Contractor Reporting Reqs 52.225-9 BUY AMERICAN - CONSTRUCTION MATERIALS May-14 F SOCIOECON PROG REQS Govt & Contractor Fill In 52.228-15 PERFORMANCE AND PAYMENT BONDS - CONSTRUCTION Oct-10 G GEN'L CONTRACT REQS. Contractor Submittal Reqs 52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR Apr-84 H CONSTR. CONTRACTS REQS Government Fill In 52.236-4 PHYSICAL DATA Apr-84 H CONSTR. CONTRACTS REQS Government Fill In 52.248-3 Alt 1 VALUE ENGINEERING - CONSTRUCTION (ALT -I APR-84) Oct-10 G GEN'L CONTRACT REQS. Contractor Submittal Reqs
TAR CLAUSES INCORPORATED BY FULL TEXT
FAR PT 22.9 NONDISCRIMINATION BECAUSE OF AGE POLICY Feb-64 F SOCIOECON PROG REQS Executive Order 11141-Not A Clause
(Updated thru FAC 2005-91 on 09/30/2016)
FAR & TAR PROVISIONS INCORPORATED BY REFERENCE
CLAUSE TITLE DATE REMARKS
52.204-20 PREDECESSOR OF OFFEROR Jul-16 52.211-6 BRAND NAME OR EQUAL Aug-99 52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS Dec-89 52.214-4 FALSE STATEMENTS IN BIDS Apr-84 52.214-5 SUBMISSION OF BIDS Mar-97 52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS Apr-84 52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS Nov-99 52.214-18 PREPARATION OF BIDS -- CONSTRUCTION Apr-84 52.214-19 CONTRACT AWARD -- SEALED BIDDING -- CONSTRUCTION Aug-96 52.223-1 BIOBASED PRODUCT CERTIFICATION May-12 52.225-25 PROHIBITION ON CONTRACTING WITH ENTITIES ENGAGING IN CERTAIN ACTIVITIES OR TRANSACTIONS RELATIN Oct-15
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by the paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision my be accessed electronically at this address: www.arnet.gov/far/ (End of Clause)
52.252-1 Solicitation Provisions Incorporated By Reference (Feb 1998)
(Updated thru FAC 2005-91 on 09/30/2016)
FAR PROVISIONS INCORPORATED BY FULL TEXT
PROVISION TITLE DATE SECTION SECTION TYPE REMARKS
52.203-11
CERTIFICATION AND DISCLOSURE REGARDING PAYMENTS TO INFLUENCE
CERTAIN FEDERAL TRANSACTIONS Sep-07 F
52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS Apr-16 D REPS & CERTIFICATIONS Mandatory Contractor On-Line Input 52.209-5 CERTIFICATION REGARDING RESPONSIBILITY MATTERS Oct-15 K 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS Jul-13 K If Applicable
52.211-4 AVAILABILITY FOR EXAMINATION OF SPECIFICATIONS NOT LISTED IN GSA INDEX
OF FEDERAL SPECIFICATION, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS
Jun-88 E INSTRUCTIONS TO BIDDERS Government Fill In
52.216-1 TYPE OF CONTRACT Apr-84 E INSTRUCTIONS TO BIDDERS Government Fill In 52.222-38 COMPLIANCE WITH VETERANS' EMPLOYMENT REPORTING REQUIREMENTS Sep-10 K
52.225-10 ALT
NOTICE OF BUY AMERICAN REQUIREMENT - CONSTRUCTION MATERIAL (ALT 1
MAY-14) May-14 F SOCIOECON PROG REQS
52.225-20
PROHIBITION ON CONDUCTING RESTRICTED BUSINESS OPERATIONS IN SUDAN -
CERTIFICATION Aug-09 K
52.228-1 BID GUARANTEE Sep-96 E INSTRUCTIONS TO BIDDERS Contractor Submittal Reqs 52.230-7 PROPOSAL DISCLOSURE - COST ACCOUNTING PRACTICE CHANGES Apr-05 K If Applicable 52.233-2 SERVICE OF PROTEST Sep-06 E INSTRUCTIONS TO BIDDERS Government Fill In 52.236-27 SITE VISIT (CONSTRUCTION) Feb-95 E CONSTR. CONTRACT REQS. Government Fill In
OTHER PROVISIONS INCORPORATED BY FULL TEXT
D-1
FEDERAL ACQUISITION REGULATION AND TRANSPORTATION
ACQUISITION PROVISIONS
(Updated through FAC 2005-91)
REPRESENTATIONS AND CERTIFICATIONS
Annual Representations and Certifications. Prospective contractors shall complete electronic annual representations and certifications on-line at this web address:
http://www.sam.gov (See Far 4.1201) the System for Award Management (SAM) database (see FAR 4.1102).
Vets4212 Form must also be filled-in online at http://www.dol.gov/vets/vets4212.htm in accordance with FAR Clause 52.222-37.
CONTRACTORS ARE NOT ELIGIBLE FOR AWARD
WITHOUT COMPLETING THESE REQUIREMENTS.
52.204-8 -- Annual Representations and Certifications (Apr 2016)
(a) (1) The North American Industry classification System (NAICS) code for this acquisition is 237310.
(2) The small business size standard is 36.5.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7 is not included in this solicitation, and the offeror is currently registered in the System for Award Management (SAM), and has completed the Representations and Certifications section of SAM electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certification in the solicitation.
The offeror shall indicate which option applies by checking one of the following boxes:
[_] (i) Paragraph (d) applies.
[_] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c) (1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination.
This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(iv) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(v) 52.209-2, Prohibition…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .