Amendment 002 - GA ERFO FSR 54C1.pdf

PDF 268 KB Posted

Attached to
Chattahoochee-Oconee National Forest
Solicitation number
DTFH71-11-B-00023
Issued by

About this file

Amendment 002 - GA ERFO FSR 54C1

View the file

Other files

File Type Posted
Amendment 001 - GA ERFO FSR 54C1.pdf PDF
IFB Solicitation - GA ERFO FSR 54C1.pdf PDF
FP03_Eng .pdf PDF
FP03 Errata.pdf PDF
VETS-100A - 2010.pdf PDF
Plans.pdf PDF
Soils and Foundation Report.pdf PDF
Bidder's Qualifications Form.doc DOC document
Synopsis - GA ERFO FSR 54C1.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

DTFH7111B00023

x x

0 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Sterling VA 20166-6511

EFLHD-AC

21400 Ridgetop Circle Acquisitions Office Eastern Federal Lands Highway Div.

Federal Highway Administration

SEE BLOCK 1408/30/2011002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

08/02/2011

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Project Number: GA ERFO FSR 54C1

The purpose of this Amendment will be to:

1) Replace the Solicitation B Page to modify the rock dowel and reinforcing steel bid items for Red Root Road, NFSR #92.

2) Revise the Plans to modify the tabulation of quantities.

3) Provide a summary of response to questions/clarifications asked by potential bidders.

4) Bid Opening date is extended to September 6, 2011 at 2:00 pm EST.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

Amendment No. 002

Amendment Info Page 1 of 1

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

Amendment No. 002 Project GA ERFO FSR 54C1

Chattahoochee-Oconee National Forest Solicitation: DTFH71-11-B-00023

The purpose of this Amendment will be to:

1) Replace the Solicitation B Page to modify the rock dowel and reinforcing steel bid items for Red Root Road, NFSR #92.

2) Revise the Plans to modify the tabulation of quantities.

3) Provide a summary of response to questions/clarifications asked by potential bidders.

4) Bid Opening date is extended to September 6, 2011 at 2:00 pm EST.

Solicitation Provision changes

1. Delete the Solicitation Bid Schedule pages B-1 through B-4 and substitute the amended Bid Schedule pages B-1 through B-4.

Questions / Clarifications

The following questions and issues were submitted via email at eflhd.contracts@dot.gov. The Government response or clarification is provided. The questions / clarifications are not a transcript of the actual emails sent; they have been edited to provide a clearer representation of the actual issues or concerns, and some questions have not been included. The Government’s direct email response to the sender may have been updated below for better clarity.

1. On project DTFH7111B00023, pay item 26101-0000 'ROCK DOWEL", the bid schedule calls for 50 linear feet, is that quantity correct?

Response: The pay item quantity for rock dowel will be adjusted and included in an amendment.

mailto:eflhd.contracts@dot.gov

Project: GA ERFO FSR 54C1

CHATTAHOOCHEE - OCONEE NATIONAL FOREST

B- 1

Bid Schedule A

Pay Item No.

Estimated Quantity Unit Bid Price Amount Bid

15101-0000 MOBILIZATION

ALL Lump Sum $___________________

15201-0000 CONSTRUCTION SURVEY AND STAKING

ALL Lump Sum $___________________

15401-0000 CONTRACTOR TESTING

ALL Lump Sum $___________________

15702-1000 SOIL EROSION CONTROL, TEMPORARY DIVERSION CHANNEL

(FLEXIBLE TUBING)

ALL Lump Sum $___________________

15705-0100 SOIL EROSION CONTROL, SILT FENCE

7,800

LNFT $_______________ $___________________

15705-2000 SOIL EROSION CONTROL, TURBIDITY BARRIER

LNFT $_______________ $___________________

15706-0100 SOIL EROSION CONTROL, STRAW BALE

EACH $_______________ $___________________

15706-0200 SOIL EROSION CONTROL, CHECK DAM

EACH $_______________ $___________________

15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION ENTRANCE

EACH $_______________ $___________________

15706-2200 SOIL EROSION CONTROL, FILTER BAG

EACH $_______________ $___________________

20101-0000 CLEARING AND GRUBBING

2.0

ACRE $_______________ $___________________

Project: GA ERFO FSR 54C1

CHATTAHOOCHEE - OCONEE NATIONAL FOREST

Bid Schedule A meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text

AMENDMENT 002

Pay Item No.

Estimated Quantity Unit Bid Price Amount Bid

B- 2

20301-0300 REMOVAL OF BOX CULVERT

EACH $_______________ $___________________

20301-1100 REMOVAL OF GATE

EACH $_______________ $___________________

20301-1900 REMOVAL OF PIPE CULVERT

EACH $_______________ $___________________

20401-0000 ROADWAY EXCAVATION

2,800

CUYD $_______________ $___________________

20420-0000 EMBANKMENT CONSTRUCTION

2,700

CUYD $_______________ $___________________

20435-2000 BACKFILL, GRANULAR (AQUATIC ORGANISM PASSAGE EMBEDMENT)

CUYD $_______________ $___________________

20701-0800 EARTHWORK GEOTEXTILE, TYPE II-B

1,050

SQYD $_______________ $___________________

20703-0000 GEOGRID

6,800

SQYD $_______________ $___________________

20801-0000 STRUCTURE EXCAVATION

1,350

CUYD $_______________ $___________________

25101-2000 PLACED RIPRAP, CLASS 2

CUYD $_______________ $___________________

25510-0000 SELECT GRANULAR BACKFILL

3,600

CUYD $_______________ $___________________

26101-0000 ROCK DOWEL

1,500

LNFT $_______________ $___________________

Project: GA ERFO FSR 54C1

CHATTAHOOCHEE - OCONEE NATIONAL FOREST

Bid Schedule A meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text

AMENDMENT 002

meseret.yigezu

Estimated Quantity Unit Bid Price Amount Bid

B- 3

30110-0000 AGGREGATE SURFACE COURSE

2,200

TON $_______________ $___________________

30303-3000 ROADWAY RECONDITIONING

5,300

SQYD $_______________ $___________________

55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)

CUYD $_______________ $___________________

55401-1000 REINFORCING STEEL

14,900

LB $_______________ $___________________

60101-0000 CONCRETE

CUYD $_______________ $___________________

60201-0800 24-INCH PIPE CULVERT

LNFT $_______________ $___________________

60220-1400 6 FEET SPAN, 8 FEET RISE PRECAST REINFORCED CONCRETE BOX

CULVERT (OPEN BOTTOM BOX)

LNFT $_______________ $___________________

60220-4050 12 FEET SPAN, 8 FEET RISE PRECAST REINFORCED CONCRETE BOX

CULVERT

LNFT $_______________ $___________________

60220-4100 12 FEET SPAN, 9 FEET RISE PRECAST REINFORCED CONCRETE BOX

CULVERT

LNFT $_______________ $___________________

60220-4650 14 FEET SPAN, 12 FEET RISE PRECAST REINFORCED CONCRETE BOX

CULVERT (OPEN BOTTOM BOX)

LNFT $_______________ $___________________

60510-0300 4-INCH COLLECTOR PIPE

LNFT $_______________ $___________________

Project: GA ERFO FSR 54C1

CHATTAHOOCHEE - OCONEE NATIONAL FOREST

Bid Schedule A meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text

AMENDMENT 002

Estimated Quantity Unit Bid Price Amount Bid

B- 4

61902-0900 GATE, METAL

EACH $_______________ $___________________

62403-0000 FURNISHING AND PLACING TOPSOIL

CUYD $_______________ $___________________

62502-0000 TURF ESTABLISHMENT

5,850

SQYD $_______________ $___________________

62511-2000 SEEDING, HYDRAULIC METHOD

1,050

SQYD $_______________ $___________________

62901-1400 ROLLED EROSION CONTROL PRODUCT, TYPE 5.C

1,050

SQYD $_______________ $___________________

62903-0000 CELLULAR CONFINEMENT SYSTEM

3,200

SQYD $_______________ $___________________

63308-3000 OBJECT MARKER, TYPE 3

EACH $_______________ $___________________

63503-0300 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3

LNFT $_______________ $___________________

63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

SQFT $_______________ $___________________

63708-0000 CELLULAR PHONE SERVICE

MO $_______________ $___________________

$_____________________TOTAL

Submitted by:

Name of Bidder

Project: GA ERFO FSR 54C1

CHATTAHOOCHEE - OCONEE NATIONAL FOREST

Bid Schedule A meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text meseret.yigezu Typewritten Text

AMENDMENT 002

Amendment 2 info.pdf
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
Amendment No. 002
Project GA ERFO FSR 54C1
Solicitation: DTFH71-11-B-00023