SECTION B - Supplies or Services/Prices

B.1 FIXED PRICE WITH REIMBURSABLE MATERIALS

The Contractor shall furnish all equipment, travel, materials and personnel necessary to provide the Federal Highway Administration (FHWA) with non-personal services for “Identifying Data Frameworks and Governance for Establishing Future Civil Integrated Management (CIM) Standards,” as described in Section C below.

B.2 FIRM FIXED PRICE

Schedule of services for “Identifying Data Frameworks and Governance for Establishing Future Civil Integrated Management (CIM) Standards.”

CLIN Description Quantity Unit Unit Price Amount 00001 Professional research services for “Identifying Data Frameworks and Governance for Establishing Future Civil Integrated Management (CIM) Standards”

Pricing: Firm Fixed Price Price: $____________ Period of Performance: (12 months + 6 months for Government review) 18 months

1 1 $________ $_________

00002 Travel (to be reimbursed at cost, no fee) $_________

TOTAL $_________

(End of Section B)

SECTION C - Description/Specifications

C.1 BACKGROUND

Building Information Modeling (BIM) technology, having been used in the vertical construction world for many years, has more recently crossed over into civil works and, as such, transformed into the developing field of Civil Integrated Management (CIM). There has been much research over the last few years regarding what constitutes the CIM framework, and the outcomes of these efforts have all converged on the overall concept that CIM integrates full-agency processes--not simply nD design, but everything from eConstruction and asset management, to finance and planning, and the need for interconnection and data flow between all of these processes.

Key to the CIM concept is interoperability of data that is commonly sourced and maintained, as opposed to past practices of keeping data locally in need-specific “siloes”. With the accelerated adoption and use of CIM-related technologies, especially with digital design and construction in highway projects and system-wide collection of asset inventory data using Lidar, there is a demonstrated need to move towards data standards and overall data governance to support this need for data interoperability. In response to this need, this project will take a detailed look at existing data standards as they apply to systems such as CIM. Once this information is compiled, the different systems will be compared and contrasted for commonalities and, ultimately, their applicability to the needs of the CIM framework. The goal of this project’s outcome is to serve as a basis and starting point for future efforts towards data standards and governance that should unleash the ability for various stakeholders to collaborate and create robust CIM systems.

This project will involve performing a national/international synthesis of data collection and governance standards that have applicability to CIM. Once this is complete, the findings of the synthesis will be examined for commonalities and, especially, congruence with the data needs of the CIM framework. Products will then be developed with the goal of providing leadership toward future efforts in the development of CIM data management, sharing (or interoperability) and governance standards.

C.2 OBJECTIVE

The objective of this research effort will be the identification of existing, applicable, digital transportation life cycle data standards and, using these findings, the development of a conceptual data standard, a data governance approach, and an implementation plan. It is expected that this effort will be coordinated with the state highway agencies and other appropriate stakeholders. The results of this project will be documented and deployed through webinars, TechBriefs, and conference presentations. See Exhibit 1.

C.3 SCOPE

The scope of this requirement includes professional research services to synthesize and analyze national/international information on data interoperability standards and governance in the context of broad-based, data-intensive systems relating to transportation planning, design, construction, and operation/maintenance. The scope also includes the development of conceptual data standards and an accompanying plan for national/international implementation. Lastly, the scope will include the development, coordination, performance, and delivery of technical reports, webinars, and FHWA Techbriefs.

C.4 DETAILED REQUIREMENT

The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform thorough and superior-quality research.

Task 1: Organize and conduct a kickoff meeting to be held either at the Federal Highway Administration’s Turner-Fairbank Highway Research Center (TFHRC), and that will address the following:

• Introduction of research and FHWA team members;

• Review and refine, if necessary, the scope of work;

• Establish individual roles and responsibilities;

• Refine, if necessary, the working schedule;

• Produce and deliver within two weeks from the meeting date: a contact list, detailed minutes and a meeting summary that includes any action items

Task 2: Produce a literature review that reflects careful and thorough research regarding data management and interoperability standards and governances as they relate to BIM,CIM, and other data-intensive, broad-based systems. Although it is expected that the literature review will possibly capture systems outside of the scope of civil and highway management, design, and construction, it is important that the literature review is conducted such that the information gathered has relevance and focus to the goals of this project.

Task 3: Conduct a synthesis that identifies, from national and international examples, data management, interoperability and governance standards, practices, and frameworks that are applicable and appropriate for use in CIM. Once compiled, and based on the findings of Task 2 and 3, the Contractor shall develop a work plan for moving forward with Task 4 and subsequent Tasks, and this workplan shall be presented to FHWA for discussion and concurrence before proceeding with subsequent tasks.

Task 4: Perform analysis and distillation of the findings from Tasks 2 and 3, and incorporate input received from FHWA under Task 3. This task shall compare and contrast the findings from Task 3, compile commonalities, and develop a set of recommendations to form a basis and roadmap for moving forward toward developing CIM data standards and governance.

Specifically, the products for this task shall be the development of the following:

1. Conceptual Data Standard;

2. Data Model and Governance Approach;

3. Implementation Plan;

4. Demonstration of the business case for data integration and the concept of CIM.

This task shall be performed with emphasis on the following:

• Includes active external engagement—as an example, collaboration with the newly formed AASHTO Joint Technical Committee on Electronic Engineering Standards (JTCEES);

• Products should feed into, and be congruent with, existing CIM implementation efforts (e.g. NCHRP 10-96 - CIM Guide for DOTs).

• Recognition of, and differentiation with, past/ongoing CIM-related work (e.g. transXML, IFC adoption of BIM, NIBS, etc.)

Task 5: Development of one (1)TechBrief (in standard FHWA TechBrief document format) that captures and summarizes the goals, methods, and findings of the project and shall be developed concurrently with the other project deliverables. This Techbrief shall follow the formatting guidance of the TFHRC Research and Development (R&D) 2017 Communications Reference Guide.

Task 6: Contractor shall arrange, host, conduct, facilitate, and record one webinar presentation that describes and summarizes the project effort and findings. This shall be accomplished using contractor’s own web meeting account resources. This webinar shall be recorded, and the file provided to FHWA for posting on FHWA web resources. This task shall also include a separate virtual “practice session”, where the webinar is presented to an audience of FHWA staff for review and comment in advance of the “live” event.

Task 7: Delivery of the culminating documentation for the project, including a publication-ready final report. The final report will be presented in-person at the Turner-Fairbank Highway Research Center, at a meeting coordinated by the contractor. At this meeting, the Contractor will provide a detailed briefing and Q&A session to FHWA and invited partners regarding suggested next steps for a strong implementation of the results. All deliverable documentation shall follow the guidelines of the TFHRC R&D 2017 Communications Reference Guide.

(End of Section C) https://www.fhwa.dot.gov/publications/research/general/15058/

SECTION D - Packaging and Marking

D.1 PACKAGING

Preservation, packing, and packaging of items for shipment shall be in accordance with best commercial practices and adequate for acceptance by common carrier for safe transportation at the most economical rates.

The contractor shall clearly mark each shipment with the company name, the contract number, Task Order number (if applicable), and as appropriate, the item identification, quantity of items, and notice of partial or final delivery.

(End of Section D)

SECTION E - Inspection and Acceptance

E.1 52.246-4 INSPECTION OF SERVICES - FIXED-PRICE. (AUG 1996)

E.2 ACCEPTANCE

Acceptance of the final deliverables shall be made in writing by the Contracting Officer’s Representative.

E.3 GOVERNMENT ACCEPTANCE PERIOD

Unless stated elsewhere, the COR will have 14 calendar days to review draft deliverables and make comments. The Contractor shall have 10 calendar days to make corrections and return the corrected deliverable to the government. Upon receipt of the final deliverables, the COR will have 14 calendar days for final review prior to acceptance or providing documented reasons for non-acceptance.

(End of Section E)

SECTION F - Deliveries or Performance

F.1 52.242-15 STOP-WORK ORDER. (AUG 1989)

F.2 52.242-17 GOVERNMENT DELAY OF WORK. (APR 1984)

F.3 52.247-34 F.O.B. DESTINATION. (NOV 1991)

F.4 PERIOD OF PERFORMANCE

The period of performance is 18 months – which consists of 12 months of technical work and 6 months for the Governments editorial review and any revisions. The FHWA editorial review and publication process can take approximately six (6) months to complete before publication is approved. Consequently, this constraint should be factored into the overall project schedule.

The total contract performance period shall not exceed 18 months without written authorization from the Contracting Officer.

CLIN 00001: 18 months from date of award (12 months for the technical portion of the effort and 6 months for the Governments editorial review.)

F.5 DELIVERABLE/DELIVERY SUMMARY

Deliverable Frequency # of Copies 508 Medium/Format Submit To

1. Kickoff Meeting Summary

One-time, up to two (2) weeks from date of kickoff meeting.

one (1) electronic copy

No

MS Word or PDF, and PowerPoint slides

COR

2. Interim Report—Literature Review.

One-time, up to three (3) months from submission of Deliverable 1 one (1) electronic copy No MS Word or PDF COR

3. Interim Deliverable:

Synthesis Report

One-time, up to three (3) months from reception of FHWA comments from Deliverable 2 one (1) electronic copy

No MS Word or PDF COR

3. Interim Deliverable:

Workplan

One-time, up to three (3) months from reciept of FHWA comments from Deliverable 2 one (1) electronic copy; one(1) in-person or webconference presentation

No MS Word or PDF COR

5. TechBrief(s) Draft(s).

One-time, up to ten (10) months

One (1) electronic copy of each.

No MS Word or PDF and PowerPoint

COR

Deliverable Frequency # of Copies 508 Medium/Format Submit To from award of contract slides

6. Publication ready TechBrief Final

One-time for each, up to twelve (12) months from award of contract

One (1) electronic copy for each, ready for publication

Yes MS Word and

PDF COR

7. Webinar(s)

One-time for each, up to twelve (12) months from award of contract.

One (1) electronic copy for each Yes Webinar format COR

8. Publication ready Final Deliverable

One-time, up to twelve (12) months from award of contract one (1) electronic copy, ready for publication

Yes MS Word and

PDF COR

Months 13-18 are reserved for the Government’s editorial review.

F.6 PLACE OF DELIVERY

All deliverables, shall be delivered to the COR at the following address:

Fill-in at Award

F.7 PLACE OF PERFORMANCE

The work to be performed under this Contract shall be performed at the Contractor’s facilities.

Exceptions to this is specifically defined meetings (Kickoff Meeting, for example) held at Turner- Fairbank Highway Research Center.

(End of Section F)

SECTION G - Contract Administration Data

G.1 PAYMENT (FFP)

Payment of the prices delineated in Section B.2 to be made after FHWA acceptance in writing, of the deliverables and receipt of a proper invoice.

G.2 TRAVEL AND PER DIEM (COST REIMBURSEMENT)

Travel (other than local) may be expected to occur throughout the duration of the contract. The COR will issue the written request for travel if required (excluding local travel). The Contractor shall invoice in accordance with FAR 31.205-46, Travel Costs, and Federal Travel Regulations, and must submit documentation of all travel costs.

Travel requirements under this contract shall be met using the most economical form of transportation available. All travel shall be scheduled sufficiently in advance to take advantage of offered discount rates, unless authorized by the Contracting Officer.

The following web site provides information on current Per Diem rates:

http://www.gsa.gov/portal/category/100120

G.3 SUBCONTRACTS – ADVANCE NOTIFICATION AND CONSENT

Under this contract, the requirement of FAR 44.2, Consent to Subcontracts, has been fulfilled for the following subcontracts:

[APPROVED SUBCONTRACTOR NAME TO BE ADDED AT AWARD]

Any future change or revision to the Statement of Work or other applicable aspects of this contract shall include the subcontract(s) only to the extent that performance of the subcontract(s) is directly affected by the change or revision.

G.4 INVOICES

All invoices and required supporting documents shall be sent via e-mail to the following e-mail address: 9-AMC-AMZ-FHWA-Invoices@faa.gov.

(a) Include the invoice as an attached PDF document

(b) Include in the e-mail subject line the following:

(1) Invoice No.

(2) Contract Number

(3) Name of your Company/Organization

(4) Attention: [Contract Specialist] http://www.gsa.gov/portal/category/100120 mailto:9-AMC-AMZ-FHWA-Invoices@faa.gov

Example: Invoice 35 – DTFH6114D00033 – Contractor Name – Attention: Mandy Wylie

If the invoice and supporting documents exceed 8 MB as an e-mail attachment, the Contractor must select one of the other submission options presented below:

Invoices submitted via an overnight service must use the following physical address:

MMAC

FHWA/AMZ-150

6500 S. MacArthur Blvd Oklahoma City, OK 73169 Attention: Contract Specialist Express Delivery Point of Contact: Lead Accounting Technician, 405-954-8252

Invoices may be submitted via regular U.S. Postal Service to the following address:

Federal Highway Administration Markview Processing P.O. Box 268865 Oklahoma City OK 73126-8865 Attention: Contract Specialist

An invoice submitted to an address other than those identified will be returned to the vendor as non-conforming.

G.5 TECHNICAL DIRECTION

Performance of the work under this contract is subject to the Technical Direction of the COR.

The term “Technical Direction” is defined to include, without limitation, the following:

(a) Direction to the Contractor which redirects the efforts, shifts work emphasis between work areas, requires pursuit of certain lines of inquiry, fills in details or otherwise serves to accomplish the statement of work;

(b) Provision of information to the Contractor that assists in the interpretation of drawings, specifications or technical portions of the work description; and,

(c) Review and approval/rejection of technical reports, drawings, specifications and technical information to be delivered by the Contractor.

All Technical Direction must be within the general scope of work stated in the contract. The COR does not have the authority to and may not issue any Technical Direction that:

(i) constitutes an assignment of additional work outside the general scope of the contract;

(ii) constitutes a change as defined in the contract clause entitled “Changes”;

(iii) in any manner causes an increase or decrease in prices set forth in Section B; or

(iv) changes any of the expressed terms, conditions or specifications of the contract.

All Technical Direction must be issued in writing, or shall be confirmed in writing by the COR within 3 working days after issuance. The Contractor shall proceed promptly with the performance of duly issued Technical Directions. However, if in the opinion of the Contractor, the direction issued but the COR is within one of the prescribed categories in (i) through (iv) above, the Contractor shall not proceed, but shall notify the Contracting Officer in writing, within 3 working days after receipt of any such direction. The Contracting Officer will determine if the Technical Direction is proper, or if a contract modification would be required to properly implement the direction. Failure of the parties to agree upon the nature of the direction or upon the contract action to be taken with respect thereto shall be subject to the clause included in Section I entitled “Disputes.”

G.6 CONTRACTING OFFICER’S REPRESENTATIVE (COR)

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work delivered under this contract.

(b) The Contracting Officer shall designate a Contracting Officer’s Representative by written notice to the Contractor. The COR’s responsibilities shall include technical monitoring of the Contractor’s performance and inspecting and accepting deliveries under the contract.

The COR shall be appointed in writing, at which time ALL of the responsibilities of the COR shall be detailed, and a copy of the appointment memorandum shall be furnished to the Contractor.

Any changes to the COR delegation shall be made in writing, either by changes to the existing memorandum, or by issuance of a new appointment memorandum. Copies of any changes shall be provided to the Contractor.

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to any modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor’s right to proceed, or issue any order causing the Contractor to stop work; or

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR’s appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer’s response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the

COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor’s risk.

G.7 CONTRACTOR SUPERVISION

The Contractor shall provide total supervision of its staff. Government personnel are not authorized or permitted to supervise any contractor personnel. The contractor's Project Manager for this contract is [Fill-in at Award], who shall communicate with the COR to determine the Government's work requirements as set forth in the Statement of Work and shall assure that these requirements are fulfilled. In the event the designated Project Manager is incapacitated due to illness or injury or otherwise is to be removed by the Contractor during the contract performance, replacement of the incumbent Project Manager shall be subject to the approval of the CO.

(End of Section G)

SECTION H - Special Contract Requirements

H.1 REQUIREMENTS FOR IMPLEMENTING SECTION 508 STANDARDS

The following applies to all FHWA Contracts issued on or after June 25, 2001, for Preparation of Technical reports or other documents that FHWA plans to post on a website.

In addition to the work requirements specified in this statement of work, vendors must ensure that all electronic documents that they prepare will meet the requirements of Section 508 of the Rehabilitation Act. The act requires that all electronic products prepared for the Federal Government be accessible to persons with disabilities, including those with vision, hearing, cognitive, and mobility impairments. Vendors can view Section 508 of the Rehabilitation Act (http://www.access-board.gov/508.htm) and the Federal IT Accessibility Initiative (Home Page) (http://section508.gov/) for detailed information.

Applicable Standards:

The following standards have been determined to be applicable to this contract.

___X_ 1194.21 Software applications and operating systems.

___X_ 1194.22 Web-based intranet and Internet information and applications.

_____ 1194.23 Telecommunications products.

_____ 1194.24 Video and multimedia products.

_____ 1194.25 Self-contained, closed products.

_____ 1194.26 Desktop and portable computers.

The standards are available at http://www.access-board.gov/508.htm. The standards do not require the installation of specific accessibility-related software or the attachment of an assistive technology device, but merely require that the Electronic and Information Technology (EIT) be compatible with such software and devices so that it can be made accessible, if so required by the agency, in the future.

H.2 POST AWARD EVALUATION OF CONTRACTOR PERFORMANCE

Contractor Performance Evaluations

(a) Interim and final evaluations of Contractor performance will be prepared on this contract in accordance with FAR 42.1502 and TAM 1242.1502. The final performance evaluations will be prepared at the time of completion of work.

(b) The Contractor can elect to review the evaluation and submit additional information or a rebuttal statement. The Contractor will be permitted 60 calendar days to respond. Contractor response is voluntary. If the Contractor does not respond within 60 days, the Government will presume that the Contractor has no comment. Any disagreement between the parties http://www.access-board.gov/508.htm http://section508.gov/ http://www.access-board.gov/508.htm regarding an evaluation will be referred to an individual at a level above the Contracting Officer, whose decision is final.

(c) Copies of the evaluations, Contractor responses, and review comments, if any, will be retained as part of the contract file, and may be used to support future award decisions.

The Federal Highway Administration utilizes the Contractor Performance Assessment Reporting System (CPARS) to record and maintain past performance information. CPARS is used to document Contractor performance information that is required by Federal Regulations.

CPARS reference material can be accessed at http://www.cpars.gov/.

The registration process requires the Contractor to identify an individual that will serve as a primary contact. This individual will be authorized access to the evaluation for review and comment. In addition, the Contractor is encouraged to identify a secondary contact in the event the primary contact is unavailable to process the evaluation within the required 60-day period. After the FHWA Contract Specialist registers the contract in CPARS, the Contractor will receive a system generated e-mail notifying him/her that the contract is registered. A system generated e-mail will also provide the Contractor with a User ID if the person does not already have a CPARS User ID.

Once a performance evaluation has been prepared and is ready for comment, the Contractor representative will receive a system generated e-mail notification that the performance evaluation is electronically available for review and comment. The Contractor representative will receive an automated e-mail whenever an assessment is completed and can subsequently retrieve the completed assessment from CPARS.

Contractors may access evaluations at http://www.cpars.gov/ for review and comment in

CPARS.

H.3 GOVERNMENT FURNISHED OR CONTRACTOR ACQUIRED PROPERTY

Equipment provided by the Government or acquired by the Contractor for the performance of work under this contract shall be maintained and accounted for in accordance with the provisions of FAR Part 45. At the conclusion of the contract, all equipment provided by the Government to the Contractor shall be returned to the Government in the same condition as when provided to the Contractor, less normal wear and tear. The Contractor is responsible for transporting all equipment to FHWA, F.O.B Destination, at the conclusion of the contract.

H.4 PROTECTION OF INFORMATION

(a) It is anticipated that in performance of this contract, the Contractor through its employees may have access to, or be in receipt of, certain confidential and proprietary information of Government Contractors, and/or data relating to FHWA's plans, programs, http://www.cpars.gov/ http://www.cpars.gov/ technical requirements, budgetary matters, and such other information, the disclosure of which may give the Contractor a competitive advantage or be adverse to the interests of the Government. The Contractor shall not disclose such information acquired to anyone, other than the Government, including Contractor’s other employees, without the prior written consent of the Contracting Officer.

(b) To the extent that the work under this contract requires access to proprietary, business confidential, or financial data of other companies, and provided such data is marked “Proprietary and Confidential,” the Contractor shall protect such information from unauthorized use and disclosure and agrees not to use it to compete against such companies.

(c) For these purposes, “Proprietary and Confidential” information shall mean any information reasonably so designated that is not generally available to the public; but not information that becomes available on a non-confidential basis from another source, or was known to Contractor on a non-confidential basis prior to its disclosure to the Contractor in the performance of this contract.

(d) The Contractor shall include the substance of this confidentiality agreement in all subcontracts and Consultant agreements for performance of work under this contract unless excused in writing by the Contracting Officer.

H.5 DISSEMINATION OF CONTRACT INFORMATION

The Contractor shall not publish, permit to be published, or distribute information, oral or written, concerning the results or conclusions made pursuant to the performance of this contract, without the prior written consent of the Contracting Officer. The COR and the Contracting Officer shall be afforded the opportunity to review all Contractor communications and/or correspondence with the media regarding this effort at least 72 hours prior to public release. An electronic copy of any material proposed to be published or distributed shall be submitted to the Contracting Officer, and the COR.

H.6 ACKNOWLEDGEMENT OF SUPPORT AND DISCLAIMER

An acknowledgment of FHWA support and a disclaimer must appear in any publication of any material, whether copyrighted or not, based on or developed under this contract in the following terms:

“This material is based upon work supported by the Federal Highway Administration under contract number [To Be Determined]”

Additionally, all materials must contain the following statement:

“Any opinions, findings and conclusions or recommendations expressed in this publication are those of the author(s) and do not necessarily reflect the views of the Federal Highway

Administration.”

H.7 NON-PERSONAL SERVICES CONTRACT

This contract is a non-personal services contract as defined in the FAR at subpart 37.101. It is understood and agreed that the Contractor and/or Contractor’s employees and subcontractors:

(1) shall perform the services specified herein as independent contractors, not as employees of the government; (2) shall be responsible for their own management and administration of the work required and bear sole responsibility for complying with any and all technical, schedule, or financial requirements or constraints attendant to the performance of this contract; (3) shall be free from supervision or control by any government employee with respect to the manner or method of performance of the services specified; but (4) shall, pursuant to the government’s right and obligation to inspect, accept or reject the work, comply with such general direction of the Contracting Officer, or the duly authorized representative of the Contracting Officer, as is necessary to ensure accomplishment of the contract objectives.

H.8 PROCUREMENT AUTHORITY

The Federal Highway Administration, Office of Acquisition and Grants Management, is the only agency that is authorized to modify, suspend, or terminate performance under this Contract.

(End of Section H)

SECTION I - Contract Clauses

52.202-1 DEFINITIONS. (NOV 2013)

52.203-3 GRATUITIES. (APR 1984)

52.203-5 COVENANT AGAINST CONTINGENT FEES. (MAY 2014)

52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT. (SEP 2006)

52.203-7 ANTI-KICKBACK PROCEDURES. (MAY 2014)

52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER

ACTIVITY. (MAY 2014)

52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY. (MAY 2014)

52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS.

(OCT 2010)

52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO

INFORM EMPLOYEES OF WHISTLEBLOWER RIGHTS. (APR 2014)

52.203-18 – PROHIBITION ON CONTRACTING WITH ENTITIES THAT REQUIRE CERTAIN

INTERNAL CONFIDENTIALITY AGREEMENTS OR STATEMENTS-REPRESENTATION (JAN 2017)

52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT PAPER.

(MAY 2011)

52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (JAN 2011)

52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS.

(OCT 2016)

52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE. (OCT 2016)

52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE. (JUL 2016)

52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS. (DEC

2014)

52.209-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH

CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT. (OCT 2015)

52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY

MATTERS. (JUL 2013)

52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS.

(NOV 2015)

52.215-2 AUDIT AND RECORDS - NEGOTIATION. (OCT 2010)

52.215-8 ORDER OF PRECEDENCE - UNIFORM CONTRACT FORMAT. (OCT 1997)

52.215-14 INTEGRITY OF UNIT PRICES (OCT 2010)

52.215-19 NOTIFICATION OF OWNERSHIP CHANGES. (OCT 1997)

52.215-21 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA AND DATA OTHER THAN

CERTIFIED COST OR PRICING DATA - MODIFICATIONS. (OCT 2010)

52.217-8 OPTION TO EXTEND SERVICES. (NOV 1999)

The Government may require continued performance of any services within the limits and at the rates specified in the contract. These rates may be adjusted only as a result of revisions to prevailing labor rates provided by the Secretary of Labor. The option provision may be exercised more than once, but the total extension of performance hereunder shall not exceed 6 months. The Contracting Officer may exercise the option by written notice to the Contractor within the period of performance of this contract.

(End of clause)

52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000)

(a) The Government may extend the term of this contract by written notice to the Contractor within 1 day; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 14 days before the contract expires. The preliminary notice does not commit the Government to an extension.

(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.

(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed 30 months.

52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS. (NOV 2016)

(a) Definitions. As used in this contract-

HUBZone small business concern means a small business concern, certified by the Small Business Administration, that appears on the List of Qualified HUBZone Small Business Concerns maintained by the Small Business Administration.

Service-disabled veteran-owned small business concern-

(1) Means a small business concern-

(i) Not less than 51 percent of which is owned by one or more service-disabled veterans or, in the case of any publicly owned business, not less than 51 percent of the stock of which is owned by one or more service-disabled veterans; and

(ii) The management and daily business operations of which are controlled by one or more service-disabled veterans or, in the case of a service-disabled veteran with permanent and severe disability, the spouse or permanent caregiver of such veteran.

(2) Service-disabled veteran means a veteran, as defined in 38 U.S.C. 101(2), with a disability that is service-connected, as defined in 38 U.S.C. 101(16).

Small business concern means a small business as defined pursuant to Section 3 of the Small Business Act and relevant regulations promulgated pursuant thereto.

Small disadvantaged business concern, consistent with 13 CFR 124.1002, means a small business concern under the size standard applicable to the acquisition, that-

(1) Is at least 51 percent unconditionally and directly owned (as defined at 13 CFR 124.105) by-

(i) One or more socially disadvantaged (as defined at 13 CFR 124.103) and economically disadvantaged (as defined at 13 CFR 124.104) individuals who are citizens of the United States;

and

(ii) Each individual claiming economic disadvantage has a net worth not exceeding $750,000 after taking into account the applicable exclusions set forth at 13 CFR 124.104(c)(2); and

(2) The management and daily business operations of which are controlled (as defined at 13.CFR 124.106) by individuals, who meet the criteria in paragraphs (1)(i) and (ii) of this definition.

Veteran-owned small business concern means a small business concern-

(1) Not less than 51 percent of which is owned by one or more veterans (as defined at 38 U.S.C.

101(2)) or, in the case of any publicly owned business, not less than 51 percent of the stock of which is owned by one or more veterans; and

(2) The management and daily business operations of which are controlled by one or more veterans.

Women-owned small business concern means a small business concern-

(1) That is at least 51 percent owned by one or more women, or, in the case of any publicly owned business, at least 51 percent of the stock of which is owned by one or more women; and

(2) Whose management and daily business operations are controlled by one or more women.

(b) It is the policy of the United States that small business concerns, veteran-owned small business concerns, service-disabled veteran-owned small business concerns, HUBZone small business concerns, small disadvantaged business concerns, and women-owned small business concerns shall have the maximum practicable opportunity to participate in performing contracts let by any Federal agency, including contracts and subcontracts for subsystems, assemblies, components, and related services for major systems. It is further the policy of the United States that its prime contractors establish procedures to ensure the timely payment of amounts due pursuant to the terms of their subcontracts with small business concerns, veteran-owned small business concerns, service-disabled veteran-owned small business concerns, HUBZone small business concerns, small disadvantaged business concerns, and women-owned small business concerns.

(c) The Contractor hereby agrees to carry out this policy in the awarding of subcontracts to the fullest extent consistent with efficient contract performance. The Contractor further agrees to cooperate in any studies or surveys as may be conducted by the United States Small Business Administration or the awarding agency of the United States as may be necessary to determine the extent of the Contractor's compliance with this clause.

(d)(1) The Contractor may accept a subcontractor's written representations of its size and socioeconomic status as a small business, small disadvantaged business, veteran-owned small business, service-disabled veteran-owned small business, or a women-owned small business if the subcontractor represents that the size and socioeconomic status representations with its offer are current, accurate, and complete as of the date of the offer for the subcontract.

(2) The Contractor may accept a subcontractor's representations of its size and socioeconomic status as a small business, small disadvantaged business, veteran-owned small business, service-disabled veteran-owned small business, or a women-owned small business in the System for Award Management (SAM) if-

(i) The subcontractor is registered in SAM; and

(ii) The subcontractor represents that the size and socioeconomic status representations made in SAM are current, accurate and complete as of the date of the offer for the subcontract.

(3) The Contractor may not require the use of SAM for the purposes of representing size or socioeconomic status in connection with a subcontract.

(4) In accordance with 13 CFR 121.411, 124.1015, 125.29, 126.900, and 127.700, a contractor acting in good faith is not liable for misrepresentations made by its subcontractors regarding the subcontractor's size or socioeconomic status.

(5) The Contractor shall confirm that a subcontractor representing itself as a HUBZone small business concern is certified by SBA as a HUBZone small business concern by accessing the System for Award Management database or by contacting the SBA. Options for contacting the SBA include-

(i) HUBZone small business database search application Web page at http://dsbs.sba.gov/dsbs/search/dsp_searchhubzone.cfm; or http://www.sba.gov/hubzone;

(ii) In writing to the Director/HUB, U.S. Small Business Administration, 409 3rd Street, SW., Washington DC 20416; or

(iii) The SBA HUBZone Help Desk at hubzone@sba.gov.

52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION. (JUL 2013)

(a) Definitions. As used in this clause-

Long-term contract means a contract of more than five years in duration, including options.

However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is "not dominant in its field of operation" when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

http://dsbs.sba.gov/dsbs/search/dsp_searchhubzone.cfm http://www.sba.gov/hubzone mailto:hubzone@sba.gov

(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts-

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/table-small-business-size-standards.

(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.

(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.

(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:

The Contractor represents that it [] is, [] is not a small business concern under NAICS Code [insert NAICS Code] assigned to contract number [insert contract number]. (Contractor to sign and date and insert authorized signer's name and title).

52.222-3 CONVICT LABOR. (JUN 2003)

52.222-17 NONDISPLACEMENT OF QUALIFIED WORKERS. (MAY 2014)

52.222-21 PROHIBITION OF SEGREGATED FACILITIES. (APR 2015)

52.222-26 EQUAL OPPORTUNITY. (SEP 2016)

52.222-35 EQUAL OPPORTUNITY FOR VETERANS. (OCT 2015)

52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES. (JUL 2014)

(a) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60-741.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified individuals on the basis of disability, and requires affirmative action by the Contractor to employ and advance in employment qualified individuals with disabilities.

(b) Subcontracts. The Contractor shall include the terms of this clause in every subcontract or purchase order in excess of $15,000 unless exempted by rules, regulations, or orders of the Secretary, so that such provisions will be binding upon each subcontractor or vendor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs of the U.S. Department of Labor, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.

52.222-38 COMPLIANCE WITH VETERANS’ EMPLOYMENT REPORTING REQUIREMENTS (FEB

2016)

52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS

ACT. (DEC 2010)

52.222-41 SERVICE CONTRACT LABOR STANDARDS. (MAY 2014)

52.222-43 FAIR LABOR STANDARDS ACT AND SERVICE CONTRACT LABOR STANDARDS-PRICE

ADJUSTMENT (MULTIPLE YEAR AND OPTION CONTRACTS). (MAY 2014)

52.222-50 COMBATING TRAFFICKING IN PERSONS. (MAR 2015)

52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION. (OCT 2015)

52.222-60 PAYCHECK TRANSPARENCY (EXECUTIVE ORDER 13673) OCT 2016)

52.222-61 ARBITRATION OF CONTRACTOR EMPLOYEE CLAIMS (EXECUTIVE ORDER 13673)

(DEC 2016)

52.222-62 PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706) (JAN 2017)

52.223-6 DRUG-FREE WORKPLACE. (MAY 2001)

52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING.

(AUG 2011)

52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES. (JUN 2008)

52.227-1 AUTHORIZATION AND CONSENT. (DEC 2007)

52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT.

(DEC 2007)

52.227-3 PATENT INDEMNITY (APR 1984)

52.227-14 RIGHTS IN DATA-GENERAL (MAY 2014)

52.229-3 FEDERAL, STATE, AND LOCAL TAXES. (FEB 2013)

52.232-1 PAYMENTS. (APR 1984)

52.232-8 DISCOUNTS FOR PROMPT PAYMENT. (FEB 2002)

52.232-11 EXTRAS. (APR 1984)

52.232-17 INTEREST. (MAY 2014)

52.232-23 ASSIGNMENT OF CLAIMS. (MAY 2014)

52.232-25 PROMPT PAYMENT. (JAN 2017)

52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER - SYSTEM FOR AWARD

MANAGEMENT. (JUL 2013)

https://www.acquisition.gov/sites/default/files/current/far/html/52_227.html#wp1139081

52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS. (JUN 2013)

52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS.

(DEC 2013)

52.233-1 DISPUTES. (MAY 2014)

52.233-3 PROTEST AFTER AWARD. (AUG 1996)

52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM. (OCT 2004)

52.242-13 BANKRUPTCY. (JUL 1995)

52.243-1 CHANGES - FIXED-PRICE. (AUG 1987)

52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS (JAN 2017)

52.245-1 GOVERNMENT PROPERTY. (JAN 2017)

52.245-9 USE AND CHARGES (APR 2012)

52.246-25 LIMITATION OF LIABILITY - SERVICES. (FEB 1997)

52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE). (APR 2012)

52.249-8 DEFAULT (FIXED-PRICE SUPPLY AND SERVICE). (APR 1984)

52.252-2 CLAUSES INCORPORATED BY REFERENCE. (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.acquisition.gov

52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES. (APR 1984)

(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter

1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.

(b) The use in this solicitation or contract of any Transportation Acquisition Regulation (48 CFR

12) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

http://www.acquisition.gov/

52.253-1 COMPUTER GENERATED FORMS. (JAN 1991)

1252.223-73 SEAT BELT USE POLICIES AND PROGRAMS. (APR 2005)

1252.237-73 KEY PERSONNEL (APR 2005)

(a) The personnel as specified below are considered essential to the work being performed under this contract and may, with the consent of the contracting parties, be changed from time to time during the course of the contract by adding or deleting personnel, as appropriate.

(b) Before removing, replacing, or diverting any of the specified individuals, the Contractor shall notify the contracting officer, in writing, before the change becomes effective.

The Contractor shall submit information to support the proposed action to enable the contracting officer to evaluate the potential impact of the change on the contract.

The Contractor shall not remove or replace personnel under this contract until the Contracting Officer approves the change. The Key Personnel under this Contract is/are: (specify key personnel)

1252.242-72 DISSEMINATION OF CONTRACT INFORMATION. (OCT 1994)

1252.245-70 GOVERNMENT PROPERTY REPORTS. (OCT 1994)

(a) The Contractor shall prepare an annual report of Government property in its possession and the possession of its subcontractors.

(b) The report shall be submitted to the Contracting Officer not later than September 15 of each calendar year on Form DOT F 4220.43, Contractor Report of Government Property.