Amendment_1_to_RFP.pdf

PDF 147 KB Posted

Attached to
Determining Highway Asset and Data Inclusion in an Asset Management System
Solicitation number
DTFH6116R00030
Issued by

About this file

Please see attached Amendment 1 responding to a list of questions received.

View the file

Other files

File Type Posted
J1.pdf PDF
J3.docx DOCX document
RFP_DTFH6116R00030.pdf PDF
J2.docx DOCX document
Synopsis_for_DTFH6116R00030.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

DTFH6116R00030

x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

WASHINGTON DC 20590

HCFA

1200 NEW JERSEY AVENUE, SE

OFFICE OF ACQUISITION & GRANTS MGMT

OFFICE OF THE CHIEF FINANCIAL OFFICER

FEDERAL HIGHWAY ADMINISTRATION

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

This amendment to the RFP is issued to answer questions received for RFP DTFH6116R00030.

Question 1: Whether companies from Outside USA can apply for this? (like from India or

Canada)

Response: This is a full and open RFP. Any qualified company may submit a proposal;

however, it has to meet all the requirements in the RFP, registered with SAM.gov, etc.

Question 2: Whether we need to come over there for meetings?

Response: Holding the meeting at Turner-Fairbank Highway Research Center in McLean, VA is

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

HRDI41201601407/12/20160001

To all potential offerors

Guang Y. Zeng

Signed Copy in File

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

DTFH6116R00030

preferred, if there is a need for such meeting, but not required.

Questions 3: Can we perform the tasks (related to

RFP) outside USA? (like, from India or Canada)

Response: Yes, however the work must heavily reflect, and be developed in the context of, United States practices. This project is being conducted to provide guidance for US states and local agencies to assist in their asset management programs, within the greater context of the law according to MAP-21 and the FAST Act.

Although the contractor will be required to include practices outside of the US in the literature review and case studies, the work shall focus on US practices where possible and the final product shall be relevant to US stakeholders.

Question 4: Can we submit the proposals via email?

Response: No. Please follow instructions in the

RFP.

Question 5: Could you please tell me who at FHWA will be leading DTFH6116R00030 - Determining

Highway Asset and Data Inclusion in an Asset

Management System?

Response: FHWA Office of Research, Development, and Technology will be leading this project. No individual is being disclosed at this moment.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)